# US Data Centre Power and AI Infrastructure: 16 Expert Questions Before Committing Land, Capital or GPUs

# US Data Centre Power and AI Infrastructure: 16 Expert Questions Before Committing Land, Capital or GPUs

**Prepared for Load & Date Research’s Data Centre Power and AI Infrastructure Research Desk**  
**Research cut-off: 16 October 2026**  
**Format: researched interview brief—not completed interviews.** The answer frameworks below are editorial prompts, not statements attributed to the proposed interviewees. All expert quotation spaces are intentionally blank.

## What should buyers get from these interviews?

**A useful expert answer should identify the evidence that supports the next commitment—and the condition that would stop it.** The central question is: *What critical IT capacity can this project deliver, by which date, under which operating and payment obligations?*

This question set is designed for independent developers screening **20–100 MW phased projects**, AI operators seeking **5–30 MW of high-density colocation**, and the investors or lenders assessing those commitments. These are the desk’s target requirements, not claims about available inventory.

Use the interviews to produce three decision documents:

| Buyer decision | Interview output | What should remain explicit |
|---|---|---|
| Acquire land, extend an option or fund utility works | Power evidence assessment and six-gate commitment checklist | Unresolved conditions, payment exposure and authorised confirmation owners |
| Reserve colocation or release hardware | Critical IT capacity comparison and activation dependency schedule | Hardware compatibility, acceptance criteria and responsibilities |
| Approve capital or financing | Monthly downside model and evidence-change register | Slow-ramp obligations, delay exposure and conditions requiring renewed approval |

**Editorial rule:** ask for an anonymised example, the underlying document and an exception to the expert’s own conclusion. Do not accept an industry forecast as evidence of a particular site’s readiness.

## Which recognised experts should the desk approach?

The following are **proposed interview targets**, not participants or endorsers. Their published roles or relevant work were verified through the sources cited. Interview assignments are the desk’s judgement.

| Proposed expert | Verified basis for inclusion | Questions to prioritise | Perspective to balance |
|---|---|---|---|
| **Ari Peskoe** | Director of Harvard Law School’s Electricity Law Initiative, with published work on electricity regulation and transmission. ([hls.harvard.edu](https://hls.harvard.edu/faculty/ari-peskoe/)) | 1, 3, 6, 16 | Pair legal analysis with the serving utility and project counsel; public commentary is not advice on an unseen agreement. |
| **Natalie Mims Frick** | Co-author of Berkeley Lab’s August 2026 research on large-load electricity rate design. ([eta.lbl.gov](https://eta.lbl.gov/publications/electricity-rate-designs-large-0)) | 5, 6, 15 | Pair cross-utility research with a specialist who can validate the actual tariff and monthly bill. |
| **Julia Matevosyan** | Chief Engineer at the Energy Systems Integration Group; her remit includes large-load integration and reliability. ([esig.energy](https://www.esig.energy/about/leadership/julia-matevosyan/)) | 3, 7, 8, 10 | Pair system-level expertise with the relevant utility’s planning and protection engineers. |
| **Chris Brown** | Chief Technical Officer at Uptime Institute, with experience in critical-facility capacity planning, design and operations. ([uptimeinstitute.com](https://uptimeinstitute.com/about-ui/our-team)) | 2, 4, 9–12 | Establish whether any project-specific assessment or certification relationship exists. |
| **Rich Whitmore** | Identified as CEO of Motivair by Schneider Electric in the company’s 31 August 2026 factory-tour video description. ([youtube.com](https://www.youtube.com/watch?v=-Scb_4ZIPBk)) | 9, 10, 12 | Cooling-supplier perspective; request independent commissioning evidence alongside product claims. |
| **Chris Sharp** | Identified as Digital Realty’s Chief Technology Officer in the June 2026 *AI at Scale* episode on power, cooling and AI infrastructure economics. ([podcasts.apple.com](https://podcasts.apple.com/us/podcast/chris-sharp-steven-carlini-ai-factories-power-cooling/id1748494548?i=1000772806550)) | 11, 13, 14 | Colocation-provider perspective; pair with a buyer’s infrastructure and procurement leads. |
| **Varun Sivaram** | Founder and CEO of Emerald AI, as identified in its September 2026 company publication. ([emeraldai.co](https://www.emeraldai.co/blog/emerald-ai-ceo-named-a-2026-tech-titan-by-washingtonian-magazine)) | 7, 14 | Flexibility-software supplier perspective; require utility confirmation and workload-level evidence. |
| **Andy Lawrence** | Executive Director of Research at Uptime Institute. ([uptimeinstitute.com](https://uptimeinstitute.com/about-ui/our-team)) | 13, 15, 16 | Pair industry analysis with the buyer’s CFO and an actual credit decision-maker. |

For every interview, record employer, relevant commercial relationships, whether examples are first-hand, and whether supporting documents can be reviewed. Ask experts to distinguish their own observations from forecasts and supplier representations.

## Which dated developments should shape the discussion?

These are **specific developments found in the research**, not an exhaustive legal-status register. Counsel should establish the operative rules for the project before commitment.

| Dated evidence | What it establishes | Interview implication |
|---|---|---|
| **18 June 2026: FERC large-load show-cause orders** | FERC directed six jurisdictional regional grid operators to justify or reform relevant tariffs, including study processes, cost allocation, co-location and flexible transmission service. This was not a single nationwide site-connection approval. ([ferc.gov](https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration)) | Ask which filed or approved provisions actually govern the project—not whether federal policy generally supports faster connections. |
| **August 2026: NERC large-load FAQ** | NERC described proposed computational-load registration criteria and standards development, with submission of new or modified standards and registry criteria required by **31 December 2026**. That deadline remained in the future at this research cut-off. ([nerc.com](https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/large-loads-faqs.pdf)) | Separate existing obligations from proposed requirements and assess the consequences of subsequent design changes. |
| **3 September 2026: ERCOT Batch Zero notice** | ERCOT described conditional classifications that could depend on verification, correction of dynamic-model deficiencies or a regulatory exception. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-A080326-04)) | Ask for the project’s classification and outstanding conditions; inclusion alone should not be presented as unconditional readiness. |
| **Dominion GS-5: approved future commencement** | Virginia’s official legislative briefing records approval of GS-5 with an effective date of **1 January 2027**, including different minimum-demand percentages for transmission/distribution and generation. ([apps.dlas.virginia.gov](https://apps.dlas.virginia.gov/User_db/frmView.aspx?ViewId=7037&s=7)) | Model the tariff applicable during the deployment period, not only the tariff applicable when the site is shortlisted. |

## 1. What does a utility will-serve letter actually guarantee—and what would you need before approving a land payment?

**Ask:** Ari Peskoe, followed by the serving utility’s authorised representative.

**Why it matters:** The interview should establish the difference between an encouraging statement and an enforceable delivery obligation. AEP Ohio’s published process, for example, describes an electric service agreement containing a good-faith energisation estimate, with the contract term beginning at actual energisation. ([aepohio.com](https://www.aepohio.com/company/about/rates/data-center-tariff/))

**A good answer should cover:**

- The document’s parties, site identifier, load definition, phase dates and expiry.
- Whether it records an enquiry, completed study, service offer or executed agreement.
- Unfinished network works, approvals, customer contributions and third-party dependencies.
- Which dates are estimates, obligations or conditions—and what remedies apply if they move.
- Whether ownership, tenant, load-profile or design changes require consent or restudy.

**Sharp follow-up:** Which exact sentence would you refuse to let a seller paraphrase as power secured?

**Evidence to request:** Redacted correspondence, the service study, executed agreements and a utility-confirmed schedule of unresolved conditions.

**Buyer use:** Attach the assessment to the next land or infrastructure payment request. Mark absent proof as **not established**, rather than assuming either availability or unavailability.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 2. How do we reconcile utility service MW, critical IT MW and advertised campus potential?

**Ask:** Chris Brown, with the project’s electrical and mechanical designers.

**Why it matters:** A buyer needs a capacity definition that survives technical review. Schneider Electric’s power-sizing guidance explicitly includes IT equipment, cooling, lighting and backup-related requirements when assessing total facility power. ([se.com](https://www.se.com/ww/en/work/solutions/data-centers-and-networks/trade-off-tools/data-center-power-sizing-calculator/))

**A good answer should cover:** A phase-by-phase reconciliation from the utility delivery point to usable rack power. Ask the expert to identify electrical losses, cooling and auxiliary demand, operating reserves, maintenance configurations and the limiting equipment path.

Request the following comparison rather than one headline MW figure:

| Capacity statement | Required clarification |
|---|---|
| Utility service | Delivery point, voltage, import limit, operating conditions and date |
| Facility electrical capacity | Installed versus planned equipment; normal and maintenance configurations |
| Critical IT capacity | Power boundary, rack allocation and supported operating conditions |
| Campus potential | Remaining land, approvals, utility and construction dependencies |

**Sharp follow-up:** Could the facility support the contracted IT load on the design hot day with the specified equipment unavailable for maintenance? Show the calculation and assumptions.

**Evidence to request:** Signed capacity reconciliation, electrical single-line diagram, equipment ratings and thermal design basis. Ask the expert to explain why any PUE-based shortcut is—or is not—appropriate for the capacity claim.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 3. Which large-load connection process applies, and what electrical behaviour could invalidate the study?

**Ask:** Julia Matevosyan and Ari Peskoe, alongside the relevant utility or grid planner.

**Why it matters:** Buyers need to distinguish physical connection, transmission service, generation arrangements and changing reliability requirements. NERC identifies rapid demand fluctuations, voltage sensitivity, modelling and operational coordination as issues for computational loads. ([nerc.com](https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/large-loads-faqs.pdf))

**A good answer should cover:**

- A responsibility map covering the utility, transmission owner, regional operator and regulator.
- Separate pathways for the load connection and any associated generation.
- The studied load ramp, power-electronics settings, protection behaviour and credible loss-of-load events.
- Ownership of dynamic models, validation data and subsequent updates.
- Changes that could trigger restudy: GPU configuration, UPS controls, on-site generation, expansion or operating strategy.

**Sharp follow-up:** If the hardware configuration changes after the study, who must approve the revised electrical behaviour before energisation?

**Evidence to request:** Study assumptions, accepted model versions, outstanding technical comments and an agreed change-control process.

**Texas-specific probe:** Ask whether the project’s ERCOT classification is conditional and which deficiencies remain. The September 2026 Batch Zero notice explicitly identifies dynamic-model deficiencies as a possible condition. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-A080326-04))

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 4. Which unresolved site dependency should stop the next capital commitment?

**Ask:** Chris Brown, the development lead and local permitting counsel.

**Why it matters:** The buyer needs an explicit stopping condition, not an average readiness score. Uptime’s building-characteristics review separates factory testing, installation checks, equipment start-up and integrated testing—useful evidence that readiness requires more than a completed building. ([ats.uptimeinstitute.com](https://ats.uptimeinstitute.com/professional-services/building-characteristics-review))

**A good answer should cover:** Apply six separate gates:

1. **Land control:** rights, access, easements and option deadlines.
2. **Planning and permits:** applicable permissions, conditions and outstanding proceedings.
3. **Utility arrangements:** agreed service and customer obligations.
4. **Network works:** scope, approvals, construction and energisation dependencies.
5. **Equipment and facility systems:** electrical, cooling, water and connectivity readiness.
6. **Commissioning:** test scope, acceptance authority and unresolved defects.

For each gate, ask what is established, what remains conditional and what must be completed before the next payment.

**Sharp follow-up:** If every other workstream were on time, which single unresolved item could still prevent operation?

**Evidence to request:** A permit register and dependency schedule linking each condition to its source, owner and required completion date. For Texas air permitting, use the current TCEQ search route: the agency announced a transition to its Permit Search Portal beginning **31 August 2026**. ([tceq.texas.gov](https://www.tceq.texas.gov/permitting/air/airpermit-applications-notices))

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 5. What does the electricity bill look like if the data centre ramps six months late?

**Ask:** Natalie Mims Frick and a tariff specialist able to validate the actual service arrangement.

**Why it matters:** The relevant comparison is a monthly payment obligation, not an isolated energy rate. Berkeley Lab’s August 2026 tariff research distinguishes monthly demand charges, minimum billing demand, minimum bills and other contractual provisions. ([eta-publications.lbl.gov](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf))

**A good answer should cover:** Build expected-ramp, delayed-ramp and lower-utilisation cases using separately confirmed inputs for metered energy, peak demand, contract capacity, billing ratchets, applicable riders and supply arrangements. Keep deposits and infrastructure contributions outside recurring electricity expense.

**A concrete interview test:** AEP Ohio’s published contract-capacity calculation for the relevant 25–75 MW band is 15 MW plus 85% of capacity above 25 MW. For an illustrative **50 MW contract**, that limb is **36.25 MW**. This is a billing-demand calculation—not a requirement to purchase 36.25 MW continuously as energy; other tariff determinants and ramp provisions still require checking. ([aepohio.com](https://www.aepohio.com/company/about/rates/data-center-tariff/))

**Sharp follow-up:** Which charges remain if the racks draw little power, and which genuinely fall with consumption?

**Evidence to request:** The operative tariff, riders, service agreement, supply contract and a reproducible monthly workbook reconciled to an example bill.

**Buyer use:** Compare effective recurring cost per metered MWh alongside total cash commitments. Do not use either metric alone.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 6. Which deposits, guarantees and exit obligations survive a slower tenant ramp or cancellation?

**Ask:** Natalie Mims Frick and Ari Peskoe, with the buyer’s treasury and legal teams.

**Why it matters:** The financial commitment can extend beyond the monthly bill. Berkeley Lab’s review treats collateral, minimum contract duration, exit fees, direct cost assignment and capacity-resizing provisions as distinct tariff elements. ([eta-publications.lbl.gov](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf))

**A good answer should cover:** Create a dated obligation schedule showing the trigger, amount or calculation, beneficiary, release condition and responsible legal entity for every deposit, guarantee, infrastructure contribution and cancellation payment.

Ask specifically about:

- A tenant default while the developer’s utility commitment continues.
- A change of control or assignment to a replacement tenant.
- A smaller first phase or abandoned later phase.
- Collateral increases following a credit deterioration.
- Refunds, offsets and treatment of infrastructure already constructed.

**Sharp follow-up:** If phase two never opens, which obligations can be resized, which can be transferred, and which remain payable?

**Evidence to request:** Executed terms and a counsel-reviewed obligation matrix, not a supplier’s summary slide.

**Buyer use:** Ask finance to show restricted cash, recurring expense and contingent liabilities separately. The interview should identify where the buyer needs a legal interpretation rather than imply that all utilities use the same protections.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 7. Can flexible AI workloads obtain earlier power without undermining customer commitments?

**Ask:** Varun Sivaram and Julia Matevosyan; seek an independent response from the serving utility.

**Why it matters:** There is experimental evidence worth interrogating, but the scale and measurement boundary matter. A published Phoenix field demonstration reported a **25% reduction in cluster power for three hours on a 256-GPU cluster**, while maintaining the trial’s AI quality-of-service guarantees. That result should not be presented as proof of equivalent flexibility across an entire proposed campus. ([arxiv.org](https://arxiv.org/abs/2507.00909))

**A good answer should cover:**

- Flexible workload share, response time, event duration and recovery behaviour.
- Reduction measured at the GPU, cluster or utility meter.
- Effects on throughput, latency, job completion and customer service levels.
- Rebound demand, alternative-site capacity and the cost of moving work.
- The utility’s contractual recognition of flexibility and consequences of non-performance.

**Sharp follow-up:** What service commitment would your solution refuse to make, and what evidence would persuade the utility to recognise the claimed flexibility?

**Evidence to request:** Event telemetry, workload mix, test protocol, customer constraints and the actual utility agreement.

**Texas-specific probe:** ERCOT’s September notice described proposed implementation mechanics and draft revisions for SB6-related curtailment. Ask the expert to distinguish those proposals from operative requirements. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-A090226-01))

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 8. Does bridge power shorten the critical path—or create a second power project?

**Ask:** Julia Matevosyan, a generation engineer and jurisdiction-specific environmental counsel.

**Why it matters:** An on-site generation proposal needs its own evidence. TCEQ provides a specific standard-permit route for qualifying natural-gas electric generating units; EPA’s May 2025 clarification addressed specified non-emergency uses of certain emergency engines, not unrestricted operation. ([tceq.texas.gov](https://www.tceq.texas.gov/permitting/air/newsourcereview/standard))

**A good answer should cover:** Compare grid-only delivery with bridge-power delivery on a common schedule and operating basis. Require assessment of fuel availability and pressure, equipment delivery, emissions authorisation, noise, electrical protection, maintenance, staffing and transition to permanent service.

Separate three questions:

1. Can the equipment physically support the load?
2. Can it legally operate for the intended duty cycle?
3. Can it do so at an acceptable all-in cost and resilience level?

**Sharp follow-up:** If permanent grid service arrives a year later than assumed, can the bridge arrangement lawfully and commercially continue?

**Evidence to request:** Duty-cycle-specific permit analysis, fuel agreement, performance guarantees, maintenance plan and a fully costed transition or removal plan.

**Buyer use:** Treat the faster date as unproven until the generation project’s dependencies have been tested alongside the grid programme.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 9. What must liquid-ready mean for our exact racks—not a generic AI deployment?

**Ask:** Rich Whitmore and Chris Brown, with the hardware supplier’s infrastructure specialist.

**Why it matters:** Buyers need equipment-specific compatibility. NVIDIA’s DGX GB200 reference architecture explicitly describes a combination of direct liquid cooling and air cooling. A liquid-cooled platform therefore does not, by itself, establish that the facility’s residual air-cooling obligation is zero. ([docs.nvidia.com](https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html))

**A good answer should cover:** Require a jointly reviewed interface schedule rather than a general liquid-ready statement.

| Interface | Evidence the expert should specify |
|---|---|
| Rack and electrical | Exact hardware configuration, power profile, feeds and installation constraints |
| Facility-to-CDU | Available flow, temperatures, pressure, water quality and operating envelope |
| CDU-to-IT | Coolant specification, materials compatibility, filtration and connection requirements |
| Heat rejection | Performance at the agreed ambient design conditions and failure scenarios |
| Residual air load | Components and network equipment still requiring air cooling |
| Controls and service | Leak detection, alarm integration, isolation, maintenance and warranty boundaries |

**Sharp follow-up:** Which interface is currently accepted by neither the facility operator nor the hardware supplier?

**Evidence to request:** The equipment-specific design basis, approved interfaces, manufacturer confirmation and an allocation of integration responsibility.

**Buyer use:** Keep unsupported parameters visible. Do not substitute a CDU’s advertised capacity for acceptance of the complete cooling system.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 10. Which commissioning test would prove this liquid-cooled deployment is ready—and which failure could it miss?

**Ask:** Chris Brown and Rich Whitmore, alongside the independent commissioning authority.

**Why it matters:** Uptime’s January 2026 research identifies CDU integration and testing as commissioning challenges. Its October 2026 publication describes the use of liquid-cooled load simulation for direct-liquid-cooling facilities. ([intelligence.uptimeinstitute.com](https://intelligence.uptimeinstitute.com/index.php/resource/coolant-distribution-units-can-complicate-commissioning))

**A good answer should cover:** Explain what is demonstrated at the factory, during installation, through functional testing and during integrated system testing. Ask how the proposed load simulation represents the intended combination of liquid heat, air heat and electrical behaviour.

Request explicit treatment of:

- Loss of a pump, CDU, electrical feed or controls component.
- Utility-to-backup transitions and recovery.
- Planned maintenance under the contracted operating configuration.
- Leak detection, isolation and restoration.
- Retesting after a defect or design change.

**Sharp follow-up:** Which test has been shortened, deferred or replaced by a calculation to preserve the advertised handover date?

**Evidence to request:** Witnessed test procedures, acceptance criteria, calibrated results, exception logs and named signatories.

**Buyer use:** Make the distinction between an approved design and demonstrated operation explicit. Ask the expert which unresolved defects should prevent acceptance and which can safely remain on a controlled completion list.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 11. What is the real time to compute after utility energisation?

**Ask:** Chris Sharp, the AI operator’s deployment lead and the hardware integration team.

**Why it matters:** NVIDIA’s deployment documentation separates infrastructure checks, networking, firmware, workload validation, performance checks and final acceptance. Its pre-deployment checklist also requires software, firmware and licensing preparation before installation. ([docs.nvidia.com](https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/deployment-summary-validation-checklist.html))

**A good answer should cover:** Build a dependency schedule that separates these milestones:

1. Facility access.
2. Utility energisation.
3. Facility-system acceptance.
4. Rack installation and cooling connection.
5. Network, storage and management readiness.
6. Cluster validation and buyer acceptance.
7. Customer workload activation.

For every task, request the owner, predecessor, evidenced duration, acceptance condition and available schedule float. Identify which activities can run in parallel and which cannot.

**Sharp follow-up:** What is the latest acceptable date for each predecessor if the customer activation date cannot move?

**Evidence to request:** An integrated programme agreed by the operator, hardware supplier, network provider and commissioning team—not separate schedules with incompatible handover assumptions.

**Buyer use:** Put contract billing commencement on the same timeline. Ask the expert to identify any period in which the buyer pays for reserved capacity without having accepted usable compute.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 12. What proves the equipment, specialist labour and operating team will be available when needed?

**Ask:** Chris Brown and the operator’s procurement and commissioning leaders.

**Why it matters:** Public recruitment can reveal the functions involved, but not whether a specific project is adequately staffed. Crusoe’s careers page, for example, lists distinct commissioning, controls, construction, electrical, mechanical and facility-operations functions. That is a research lead—not evidence of a shortage or a missed milestone. ([crusoe.ai](https://www.crusoe.ai/about/careers))

**A good answer should cover:** Distinguish an indicative quotation, purchase order, acknowledged production slot, completed factory test, shipment and installed equipment. Apply the same discipline to labour: a proposed team is not the same evidence as an agreed mobilisation schedule.

Ask for:

- Equipment-specific delivery confirmations and substitution controls.
- Factory-test dates and unresolved engineering approvals.
- Named commissioning and controls resources for the required period.
- Operations training, spare parts and escalation arrangements.
- The consequences of rescheduling a supplier’s attendance.

**Sharp follow-up:** Which date in the programme is supported only by a verbal assurance or an unaccepted purchase order?

**Evidence to request:** Supplier acknowledgements, production and testing milestones, resource commitments and the operator’s handover plan.

**Buyer use:** Record each unsupported assumption as a dependency requiring confirmation—not as a generic contingency allowance.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 13. How should buyers compare high-density colocation offers without rewarding the least complete proposal?

**Ask:** Chris Sharp, a buyer-side procurement lead and transaction counsel.

**Why it matters:** The comparison should reach beyond facility capacity to accepted deployment scope. NVIDIA’s validation framework includes infrastructure, software, networks, performance and final sign-off, providing a useful technical reference for separating facility delivery from cluster readiness. ([docs.nvidia.com](https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/deployment-summary-validation-checklist.html))

**A good answer should cover:** Ask each supplier to complete the same offer schedule:

- Deliverable critical IT kW by phase and date.
- Supported rack configuration and cooling scope.
- Capacity rent, electricity treatment, service charges and escalators.
- Installation, network, commissioning and integration inclusions.
- Minimum commitments, deposits and expansion rights.
- Acceptance milestones, billing commencement and remedies.
- Exclusions, customer responsibilities and permitted substitutions.

**Sharp follow-up:** If the supplier misses the technical acceptance criteria but the building is accessible, does rent begin—and what can the buyer actually recover or terminate?

**Evidence to request:** A reconciled technical-commercial schedule and a counsel-reviewed remedies matrix. Treat service credits, damages, termination rights and guarantees as separate provisions to examine, not assumed equivalents.

**Buyer use:** Publish a list of unresolved differences alongside the price comparison. Do not rank an offer as cheaper by silently treating missing scope as included.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 14. Does the location support our workload and network architecture, or only our power requirement?

**Ask:** Chris Sharp and the buyer’s network and workload architects.

**Why it matters:** Power is one input to a functioning cluster. NVIDIA’s DGX SuperPOD architecture distinguishes compute, storage and management fabrics; the required connectivity cannot be reduced to a statement that fibre is nearby. ([docs.nvidia.com](https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/network-fabrics.html))

**A good answer should cover:** Start with the actual workload: training, batch inference, interactive inference or a mixture. Require buyer-defined limits for latency, data movement, storage performance, recovery and geographical placement.

Then distinguish:

- **Inside the deployment:** compute fabric, storage fabric, management connectivity and performance validation.
- **Outside the deployment:** carrier access, physical route diversity, service activation, customer connectivity and contractual service levels.

**Sharp follow-up:** What measured workload result would cause you to reject an otherwise attractive power location?

**Evidence to request:** Network designs, route and service confirmations, relevant performance tests and the cost of maintaining any alternative location.

**Buyer use:** Ask the expert to compare a cheaper-power site with a closer or better-connected alternative using buyer-supplied workload economics. Require the trade-off to be explicit rather than assuming all AI activity has the same location flexibility.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 15. How should an investment committee model delay without inventing a universal cost per MW?

**Ask:** Andy Lawrence, the buyer’s CFO and a lender’s underwriting representative.

**Why it matters:** Uptime’s 2026 outlook explicitly identifies uncertainty around the speed and ultimate scale of AI infrastructure build-out. The buyer therefore needs scenarios tied to its own commitments, rather than a generic growth forecast converted into a revenue assumption. ([professionalservices.uptimeinstitute.com](https://professionalservices.uptimeinstitute.com/about-ui/press-releases/uptime-institute-announces-five-data-center-predictions-report-for-2026))

**A good answer should cover:** Ask finance to maintain four separate schedules:

| Schedule | What to establish |
|---|---|
| Continuing contractual payments | Capacity rent, utility minimums and other obligations payable under the relevant contracts |
| Incremental delay cash costs | Additional storage, insurance, financing, remobilisation or other expenditure relative to the baseline |
| Deferred contribution | The timing change in revenue less associated variable costs—not automatically permanent loss |
| Permanent losses and remedies | Supported cancellation exposure, penalties, unrecoverable costs and realistically collectible recoveries |

**Sharp follow-up:** Which cost appears twice in the model, and which assumed recovery is unsupported by the contract or counterparty credit?

**Evidence to request:** Buyer-approved assumptions, contract references and monthly cash-flow scenarios for energisation delay, integration delay, slow utilisation and tenant default.

**Buyer use:** Show deposits and restricted cash separately from expense. Present uncertainty explicitly; do not manufacture probabilities or promise returns.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## 16. What new evidence should force the buyer to reopen an approved decision?

**Ask:** Andy Lawrence and Chris Brown, with the investment or credit committee chair.

**Why it matters:** The reviewed sources show multiple moving interfaces: NERC’s August 2026 document describes standards under development, while NVIDIA’s pre-deployment checklist was updated on **12 October 2026**. An approval pack should therefore identify its document versions and revalidation triggers. ([nerc.com](https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/large-loads-faqs.pdf))

**A good answer should cover:** Agree the changes that require renewed review, including:

- A revised utility or network milestone.
- A change in service conditions, tariff applicability or collateral.
- A different rack configuration or cooling interface.
- An equipment substitution or altered commissioning scope.
- Changed tenant credit, activation date or cancellation rights.
- A permit condition or unresolved technical finding.

**Sharp follow-up:** Who has authority to stop the next payment when one approval assumption becomes unsupported?

**Evidence to request:** A before-and-after change memo showing the original assumption, new evidence, commercial consequence, decision owner and required action.

**Buyer use:** Set refresh frequency according to the next irreversible commitment and rate of change. Do not describe a site as currently verified merely because it passed a historical review.

**Expert quote:** [Awaiting interview, attribution and publication approval.]

## How should the desk turn expert answers into a buyer-ready evidence pack?

**Use a consistent evidence record, not a blended readiness percentage.** The following is the desk’s proposed editorial and diligence framework:

| Field | Required entry |
|---|---|
| Claim | The exact capacity, date, cost or operating assertion |
| Scope | Site, phase, hardware configuration and measurement boundary |
| Source | Document title, issuer, date, version and relevant provision |
| Status | Document-supported; conditional; conflicting; or not established |
| Remaining condition | What must happen before the claim can support commitment |
| Accountable owner | Party authorised to confirm or resolve it |
| Decision consequence | Proceed, seek clarification, renegotiate, defer or reject—determined by the buyer |
| Revalidation trigger | Date, design change, regulatory event or commercial change |

Before publishing an expert quotation:

- Confirm the exact wording and attribution.
- Preserve qualifications that change its meaning.
- Label forecasts and recommendations as such.
- Disclose relevant commercial relationships.
- Check that a project example is authorised for publication.
- Never convert a general expert opinion into a utility guarantee, engineering certification or legal conclusion.

**Suggested buyer next step:** Submit a redacted utility letter, facility proposal or deployment schedule for a **Power Claim Reality Check**, **Liquid-Ready Evidence Audit** or **GPU-to-Power Deadline Test**. The initial output should identify what the evidence establishes and the next questions to resolve—not promise a connection date or available inventory.

## What are the research limits?

No expert interviews were completed for this document, and no private utility agreement, facility offer or project commissioning record was reviewed. The named experts have not endorsed these questions or answer frameworks.

Research included official regulatory and utility material, technical documentation, industry research, recruitment pages, and published video and podcast descriptions. DCD’s investment programme was used for interview-topic discovery; podcast and video descriptions were used to verify relevant speakers, not treated as transcripts or independently validated technical results. ([datacenterdynamics.com](https://www.datacenterdynamics.com/en/dcd-broadcasts/data-center-investment-markets/2025/how-is-power-availability-driving-data-center-investment/))

This is a public-source interview agenda, not a site-availability database or a substitute for project-specific engineering, legal, environmental or financial diligence.

## Sources

### Power, regulation and electricity economics

1. AEP Ohio — Data Center Tariff and service-request process. `https://www.aepohio.com/company/about/rates/data-center-tariff/
2. FERC — Large-load integration orders, 18 June 2026. `https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration
3. NERC — Large Loads Frequently Asked Questions, August 2026. `https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/large-loads-faqs.pdf
4. ERCOT — Batch Zero conditional classification notice, 3 September 2026. `https://www.ercot.com/services/comm/mkt_notices/M-A080326-04
5. ERCOT — Proposed SB6 curtailment implementation workshop notice, 2 September 2026. `https://www.ercot.com/services/comm/mkt_notices/M-A090226-01
6. Berkeley Lab — Electricity Rate Designs for Large Loads: 2026 Update, publication and author record. `https://eta.lbl.gov/publications/electricity-rate-designs-large-0
7. Berkeley Lab — Full technical brief, August 2026. `https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf
8. Virginia legislative briefing — Dominion biennial rate-case outcome, 2 December 2025, especially slide 5. `https://apps.dlas.virginia.gov/User_db/frmView.aspx?ViewId=7037&s=7
9. TCEQ — Pending air permits and Permit Search Portal transition. `https://www.tceq.texas.gov/permitting/air/airpermit-applications-notices
10. TCEQ — Standard air permits, including natural-gas electric generating units. `https://www.tceq.texas.gov/permitting/air/newsourcereview/standard
11. EPA — Emergency-engine regulatory clarification, 1 May 2025. `https://www.epa.gov/newsreleases/epa-issues-clarification-help-power-data-centers-ensure-us-ai-capital-world

### Technical readiness, deployment and operating evidence

12. Schneider Electric — Data centre power-sizing methodology. `https://www.se.com/ww/en/work/solutions/data-centers-and-networks/trade-off-tools/data-center-power-sizing-calculator/
13. NVIDIA — DGX GB200 SuperPOD architecture and hybrid cooling. `https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html
14. NVIDIA — Mission Control pre-deployment checklist, updated 12 October 2026. `https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/pre-deployment-checklist.html
15. NVIDIA — Deployment summary validation checklist. `https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/deployment-summary-validation-checklist.html
16. NVIDIA — DGX SuperPOD network fabrics. `https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/network-fabrics.html
17. Uptime Institute — Building Characteristics Review. `https://ats.uptimeinstitute.com/professional-services/building-characteristics-review
18. Uptime Intelligence — Coolant distribution units can complicate commissioning, 12 January 2026; publicly visible article text. `https://intelligence.uptimeinstitute.com/index.php/resource/coolant-distribution-units-can-complicate-commissioning
19. Uptime Intelligence — Liquid-cooled load simulation for DLC commissioning, 6 October 2026; publicly visible article text. `https://intelligence.uptimeinstitute.com/index.php/resource/liquid-cooled-load-simulation-dlc-commissioning
20. Uptime Institute — Five Data Center Predictions announcement, 13 January 2026. `https://professionalservices.uptimeinstitute.com/about-ui/press-releases/uptime-institute-announces-five-data-center-predictions-report-for-2026
21. Crusoe — Careers and functional recruitment categories; dynamic page. `https://www.crusoe.ai/about/careers
22. Field-demonstration research — Turning AI Data Centers into Grid-Interactive Assets: Results from a Field Demonstration in Phoenix, Arizona. `https://arxiv.org/abs/2507.00909

### Expert credentials and interview discovery

23. Harvard Law School — Ari Peskoe biography. `https://hls.harvard.edu/faculty/ari-peskoe/
24. ESIG — Julia Matevosyan biography. `https://www.esig.energy/about/leadership/julia-matevosyan/
25. Uptime Institute — Leadership biographies. `https://uptimeinstitute.com/about-ui/our-team
26. Schneider Electric — Motivair factory-tour video description, 31 August 2026. `https://www.youtube.com/watch?v=-Scb_4ZIPBk
27. AI at Scale — Chris Sharp and Steven Carlini episode description, 15 June 2026. `https://podcasts.apple.com/us/podcast/chris-sharp-steven-carlini-ai-factories-power-cooling/id1748494548?i=1000772806550
28. Emerald AI — Varun Sivaram role identification, 9 September 2026. `https://www.emeraldai.co/blog/emerald-ai-ceo-named-a-2026-tech-titan-by-washingtonian-magazine
29. DCD — Power availability and data-centre investment programme. `https://www.datacenterdynamics.com/en/dcd-broadcasts/data-center-investment-markets/2025/how-is-power-availability-driving-data-center-investment/

## FAQs
### What should I ask an expert before buying land for a data centre?
Ask which documents establish the site’s load, delivery conditions and remaining dependencies, and which unresolved condition should stop the next payment. AEP Ohio’s published process illustrates why this matters: even an electric service agreement can contain a good-faith energisation estimate rather than an unconditional delivery date. ([aepohio.com](https://www.aepohio.com/company/about/rates/data-center-tariff/))
### Does a utility will-serve letter guarantee power by a particular date?
Do not assume a guarantee without reviewing the document’s wording, conditions and applicable agreements. Ask the utility and counsel to distinguish an estimate from an enforceable obligation and identify the available remedies; AEP Ohio explicitly describes estimated service timing in its published process. ([aepohio.com](https://www.aepohio.com/company/about/rates/data-center-tariff/))
### Why should utility service MW and critical IT MW be compared separately?
Total facility power requirements include cooling and other supporting loads as well as IT equipment. Request a project-specific reconciliation showing the power boundary, operating configuration and limiting systems rather than treating the two MW figures as interchangeable. ([se.com](https://www.se.com/ww/en/work/solutions/data-centers-and-networks/trade-off-tools/data-center-power-sizing-calculator/))
### How do large-load tariff minimums affect a slow data-centre ramp?
Minimum billing demand and minimum-bill provisions can maintain payment obligations despite lower actual consumption. Model the applicable tariff monthly, including demand determinants and riders, rather than applying a headline energy rate to forecast consumption alone. ([eta-publications.lbl.gov](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf))
### What evidence should support a liquid-ready colocation claim?
Request an equipment-specific interface schedule covering coolant, flow, temperatures, pressure, heat rejection, controls and residual air cooling. NVIDIA’s DGX GB200 architecture uses both direct liquid cooling and air cooling, so a liquid-cooled designation does not establish that the entire deployment can operate without air cooling. ([docs.nvidia.com](https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html))
### Is utility energisation the same as usable AI compute availability?
No: deployment validation also includes networking, firmware, software, workload checks and final acceptance. Put those activities on an integrated schedule and distinguish their completion from facility access, energisation and billing commencement. ([docs.nvidia.com](https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/deployment-summary-validation-checklist.html))
### Can flexible AI workloads help a project obtain earlier power?
Flexibility merits investigation, but the buyer needs evidence for its workload and an arrangement recognised by the serving utility. A Phoenix demonstration reported a 25% cluster-power reduction for three hours on 256 GPUs; that does not establish equivalent capability for an entire proposed campus. ([arxiv.org](https://arxiv.org/abs/2507.00909))
### How should expert interviews support an investment committee decision?
Use the interviews to produce a dated evidence register, unresolved-condition list and buyer-specific downside scenarios. This document recommends separating continuing contractual payments, incremental delay costs, deferred contribution and permanent losses so that unsupported assumptions and double-counting remain visible.
### Have the experts named in this document provided answers or endorsed the research?
No. They are proposed interview targets selected using published credentials and relevant work; the answer frameworks are editorial preparation, and every quotation space remains blank pending an actual interview and publication approval.

## Sources
- [Ari Peskoe - Harvard Law School | Harvard Law School](https://hls.harvard.edu/faculty/ari-peskoe/)
- [Electricity Rate Designs for Large Loads: Evolving Practices and Opportunities 2026 Update | Energy Technologies Area](https://eta.lbl.gov/publications/electricity-rate-designs-large-0)
- [Julia Matevosyan | ESIG Leadership](https://www.esig.energy/about/leadership/julia-matevosyan/)
- [Our Team | Leadership at UI - Uptime Institute](https://uptimeinstitute.com/about-ui/our-team)
- [Inside the Factory Building Liquid Cooling for AI Data Centers | Schneider Electric - YouTube](https://www.youtube.com/watch?v=-Scb_4ZIPBk)
- [Chris Sharp & Steven Carlini: … - AI at Scale - Apple Podcasts](https://podcasts.apple.com/us/podcast/chris-sharp-steven-carlini-ai-factories-power-cooling/id1748494548?i=1000772806550)
- [Emerald AI Founder and CEO Named a 2026 Tech Titan by Washingtonian Magazine - Emerald AI](https://www.emeraldai.co/blog/emerald-ai-ceo-named-a-2026-tech-titan-by-washingtonian-magazine)
- [FERC Launches Aggressive Targeted Action to Speed Large Load Integration | Federal Energy Regulatory Commission](https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration)
- [https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/large-loads-faqs.pdf](https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/large-loads-faqs.pdf)
- [Market Notice Details](https://www.ercot.com/services/comm/mkt_notices/M-A080326-04)
- [https://apps.dlas.virginia.gov/User_db/frmView.aspx?ViewId=7037&s=7](https://apps.dlas.virginia.gov/User_db/frmView.aspx?ViewId=7037&s=7)
- [Data Center Tariff](https://www.aepohio.com/company/about/rates/data-center-tariff/)
- [Data center power sizing calculator | Schneider Electric](https://www.se.com/ww/en/work/solutions/data-centers-and-networks/trade-off-tools/data-center-power-sizing-calculator/)
- [Data Center Building Characteristics Review - Uptime Institute](https://ats.uptimeinstitute.com/professional-services/building-characteristics-review)
- [Pending Air Permits: Information on Current Applications - Texas Commission on Environmental Quality - www.tceq.texas.gov](https://www.tceq.texas.gov/permitting/air/airpermit-applications-notices)
- [https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf)
- [Turning AI Data Centers into Grid-Interactive Assets: Results from a Field Demonstration in Phoenix, Arizona](https://arxiv.org/abs/2507.00909)
- [Market Notice Details](https://www.ercot.com/services/comm/mkt_notices/M-A090226-01)
- [Standard Air Permits - Texas Commission on Environmental Quality - www.tceq.texas.gov](https://www.tceq.texas.gov/permitting/air/newsourcereview/standard)
- [DGX SuperPOD Architecture — NVIDIA DGX SuperPOD: Next Generation Scalable Infrastructure for AI Leadership Reference Architecture Featuring NVDIA DGX GB200](https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html)
- [Coolant distribution units can complicate commissioning | Uptime Intelligence](https://intelligence.uptimeinstitute.com/index.php/resource/coolant-distribution-units-can-complicate-commissioning)
- [Deployment Summary Validation Checklist — NVIDIA Mission Control Management Plane and Rack Setup with NVIDIA GB200/GB300 NVL72 Systems Installation Guide](https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/deployment-summary-validation-checklist.html)
- [Careers at Crusoe | Build the future of AI infrastructure](https://www.crusoe.ai/about/careers)
- [Network Fabrics — NVIDIA DGX SuperPOD: Next Generation Scalable Infrastructure for AI Leadership Reference Architecture Featuring NVDIA DGX GB200](https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/network-fabrics.html)
- [Uptime Institute Announces Five Data Center Predictions Report for 2026 - Uptime Institute](https://professionalservices.uptimeinstitute.com/about-ui/press-releases/uptime-institute-announces-five-data-center-predictions-report-for-2026)
- [How is power availability driving data center investment? - DCD](https://www.datacenterdynamics.com/en/dcd-broadcasts/data-center-investment-markets/2025/how-is-power-availability-driving-data-center-investment/)
- [https://www.aepohio.com/company/about/rates/data-center-tariff/](https://www.aepohio.com/company/about/rates/data-center-tariff/)
- [https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration](https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration)
- [https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/large-loads-faqs.pdf](https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/large-loads-faqs.pdf)
- [https://www.ercot.com/services/comm/mkt_notices/M-A080326-04](https://www.ercot.com/services/comm/mkt_notices/M-A080326-04)
- [https://www.ercot.com/services/comm/mkt_notices/M-A090226-01](https://www.ercot.com/services/comm/mkt_notices/M-A090226-01)
- [https://eta.lbl.gov/publications/electricity-rate-designs-large-0](https://eta.lbl.gov/publications/electricity-rate-designs-large-0)
- [https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf](https://eta-publications.lbl.gov/sites/default/files/2026-08/rate_designs_large_loads_2026.08.10.pdf)
- [https://apps.dlas.virginia.gov/User_db/frmView.aspx?ViewId=7037&s=7](https://apps.dlas.virginia.gov/User_db/frmView.aspx?ViewId=7037&s=7)
- [https://www.tceq.texas.gov/permitting/air/airpermit-applications-notices](https://www.tceq.texas.gov/permitting/air/airpermit-applications-notices)
- [https://www.tceq.texas.gov/permitting/air/newsourcereview/standard](https://www.tceq.texas.gov/permitting/air/newsourcereview/standard)
- [https://www.epa.gov/newsreleases/epa-issues-clarification-help-power-data-centers-ensure-us-ai-capital-world](https://www.epa.gov/newsreleases/epa-issues-clarification-help-power-data-centers-ensure-us-ai-capital-world)
- [https://www.se.com/ww/en/work/solutions/data-centers-and-networks/trade-off-tools/data-center-power-sizing-calculator/](https://www.se.com/ww/en/work/solutions/data-centers-and-networks/trade-off-tools/data-center-power-sizing-calculator/)
- [https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html](https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html)
- [https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/pre-deployment-checklist.html](https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/pre-deployment-checklist.html)
- [https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/deployment-summary-validation-checklist.html](https://docs.nvidia.com/mission-control/docs/rack-bring-up-install/latest/deployment-summary-validation-checklist.html)
- [https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/network-fabrics.html](https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/network-fabrics.html)
- [https://ats.uptimeinstitute.com/professional-services/building-characteristics-review](https://ats.uptimeinstitute.com/professional-services/building-characteristics-review)
- [https://intelligence.uptimeinstitute.com/index.php/resource/coolant-distribution-units-can-complicate-commissioning](https://intelligence.uptimeinstitute.com/index.php/resource/coolant-distribution-units-can-complicate-commissioning)
- [https://intelligence.uptimeinstitute.com/index.php/resource/liquid-cooled-load-simulation-dlc-commissioning](https://intelligence.uptimeinstitute.com/index.php/resource/liquid-cooled-load-simulation-dlc-commissioning)
- [https://professionalservices.uptimeinstitute.com/about-ui/press-releases/uptime-institute-announces-five-data-center-predictions-report-for-2026](https://professionalservices.uptimeinstitute.com/about-ui/press-releases/uptime-institute-announces-five-data-center-predictions-report-for-2026)
- [https://www.crusoe.ai/about/careers](https://www.crusoe.ai/about/careers)
- [https://arxiv.org/abs/2507.00909](https://arxiv.org/abs/2507.00909)
- [https://hls.harvard.edu/faculty/ari-peskoe/](https://hls.harvard.edu/faculty/ari-peskoe/)
- [https://www.esig.energy/about/leadership/julia-matevosyan/](https://www.esig.energy/about/leadership/julia-matevosyan/)
- [https://uptimeinstitute.com/about-ui/our-team](https://uptimeinstitute.com/about-ui/our-team)
- [https://www.youtube.com/watch?v=-Scb_4ZIPBk](https://www.youtube.com/watch?v=-Scb_4ZIPBk)
- [https://podcasts.apple.com/us/podcast/chris-sharp-steven-carlini-ai-factories-power-cooling/id1748494548?i=1000772806550](https://podcasts.apple.com/us/podcast/chris-sharp-steven-carlini-ai-factories-power-cooling/id1748494548?i=1000772806550)
- [https://www.emeraldai.co/blog/emerald-ai-ceo-named-a-2026-tech-titan-by-washingtonian-magazine](https://www.emeraldai.co/blog/emerald-ai-ceo-named-a-2026-tech-titan-by-washingtonian-magazine)
- [https://www.datacenterdynamics.com/en/dcd-broadcasts/data-center-investment-markets/2025/how-is-power-availability-driving-data-center-investment/](https://www.datacenterdynamics.com/en/dcd-broadcasts/data-center-investment-markets/2025/how-is-power-availability-driving-data-center-investment/)