# Load & Date: US Data Centre Power and AI Infrastructure — Weekly, Monthly and Quarterly Newsletter Drafts

# Load & Date
## Three newsletter drafts for the Load & Date research desk

**Research cut-off: 16 October 2026.** Written for US developers assessing 20–100 MW phased projects and AI operators procuring 5–30 MW of high-density colocation. These are target buyer requirements, not claims about available inventory.

Dates, regulatory status and evidence limitations are identified below. Buyer actions are the desk’s recommendations, not engineering certification, legal advice or confirmation of site availability.

---

# Draft 1 — Weekly briefing

**Subject:** PJM’s emergency week: what to check before committing power spend

**Preview:** Backup authority was not activation. Texas submissions need receipts. Two PJM rulemaking tracks need separate treatment.

**Edition:** 12–16 October 2026

## What matters before your next payment?

**Refresh the evidence behind your power and activation dates before releasing the next land payment, utility deposit or hardware commitment.** This week’s practical priorities are operational readiness in PJM, submission evidence in Texas and a clean distinction between proposed rules and approved arrangements.

### 1. Did PJM require data centres to switch to backup generation?

**Not according to PJM’s 15 October update.** DOE issued Order 202-26-50 on 12 October, effective 13–16 October, authorising PJM to direct backup resources to operate as a last resort before or during an Energy Emergency Alert 3. PJM subsequently said it had not used that authority; it did activate demand response on 13 and 14 October. Do not turn emergency authorisation into a claim that data centres were actually disconnected or transferred to generators. ([energy.gov](https://www.energy.gov/ceser/federal-power-act-section-202c-pjm-interconnection-llc-pjm-order-no-202-26-50))

**Buyer action:** Ask your operator who receives utility instructions, who authorises a transfer, which workloads remain supported and where the tested operating procedure is recorded. Request the applicable contract and operating instructions rather than assuming every facility has the same obligation.

### 2. Has PJM’s backstop procurement timetable become dependable?

**No new procurement start date is established by this week’s filing.** On 12 October, PJM requested that FERC pause the backstop paper-hearing proceedings while it prepares a revised filing. PJM identified 22 October for stakeholder consultation and planned to file by 29 October, addressing cost allocation, transmission-owner exit responsibilities and load-serving-entity collateral. Those are procedural milestones, not commitments to deliver generation to a particular project. ([pjm.com](https://www.pjm.com/-/media/DotCom/documents/other-fed-state/20261012-el26-108-000.pdf))

**Important carry-forward from 9 October:** In a separate proceeding, Commissioner Rosner’s concurrence confirms that FERC rejected the bulk of PJM’s proposed Interim Resource Adequacy Service filing. Do not copy the earlier IRAS proposal into a current investment memorandum as though the proposed framework had been adopted intact. ([ferc.gov](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-pjm-interconnection-llc-er26-3515-000))

**Buyer action:** Give the backstop procurement and IRAS separate rows in your regulatory tracker, each with its docket, latest decision and affected underwriting assumption.

### 3. Can your Texas team prove its RFI was submitted?

**The published State and Community Impact RFI deadline was 12 October—not a future task.** ERCOT’s September notices required responses from identified recipients and clarified the treatment of certain 25 MW-to-below-75 MW data centres. Its 24 September notice distinguished mandatory responses for previously identified customers from a voluntary route for newly substantiated medium loads. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-02))

**Buyer action:** Obtain the submission confirmation from the transmission or distribution service provider, the submitted version and any subsequent clarification request. Record the status separately from the Batch Zero Eligibility RFI: ERCOT explicitly describes these as separate requests. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01))

### 4. Did ERCOT’s 15 October workshop create a new connection entitlement?

**The published agenda does not establish that.** The workshop covered the pre-batch portal process, large-load reporting and transparency, and BYOG/PCLR enhancements. An agenda demonstrates that subjects were scheduled for discussion; it is not an adopted rule or a site-specific approval. ([ercot.com](https://www.ercot.com/calendar/10152026-Batch_CTP-Workshop-3a_Batch-Scope))

**Buyer action:** If a seller cites the workshop as evidence of a faster connection route, request the resulting rule text, its implementation status and written confirmation that the project qualifies.

### 5. Which North Carolina costs need refreshing?

**Carry-forward from 7 October:** Duke’s announced settlement proposes non-refundable upfront funding for dedicated connection facilities, alongside deposits and security for shared grid upgrades. Duke described applicability, if approved, to customers of at least 50 MW with an 80% load factor signing an electric service agreement after 1 June 2026. The announcement itself is not an approval order. ([news.duke-energy.com](https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs))

**Buyer action:** Ask for the proposed terms, any subsequent approval and a reconciliation against your existing service agreement. Separate non-refundable expenditure, refundable security and recurring charges.

## What should each decision-maker request on Monday?

| Decision owner | Recommended evidence request | Decision it supports |
|---|---|---|
| Development lead | Current utility milestone letter, unresolved conditions and next payment | Whether to extend the option or fund works |
| AI infrastructure COO | Energisation, cooling, network and acceptance dates with named owners | Whether to release or redirect hardware |
| Energy procurement | Applicable tariff version, contract start and security schedule | Whether the proposed ramp remains affordable |
| Investment committee | One-page change log against the last approval pack | Whether approval assumptions remain supportable |

**This week’s discipline:** Mark each material claim **document-supported, conditional, conflicting or not established**. Do not let an old approval pack stand in for a current answer.

**Reply prompt:** Which milestone determines your next commitment: land control, utility service, facility acceptance or customer activation?

---

# Draft 2 — Monthly digest

**Subject:** September’s capacity test: what can actually run your GPUs?

**Preview:** Load verification, component qualification and suspended procurement—not another ranking of advertised campus megawatts.

**Coverage:** 1–30 September 2026; prepared 16 October 2026. Earlier context and post-month developments are labelled explicitly.

## What changed in September?

**The useful distinction is between evidence of an intention to build and evidence supporting a deployable configuration.** September brought new scrutiny of proposed loads, a power-and-cooling qualification programme and a reminder that an accepted regulatory filing can still leave a procurement delayed. The desk’s recommendation is to organise the shortlist around **critical IT MW, operating conditions, full costs and acceptance dates**.

### 1. What does PJM’s load review establish—and what does it not?

**PJM is testing forecast credibility, not offering a public list of available sites.** Its 29 September update described an annual review using contract information, checks for duplicate connection requests and an independent assessment of data-centre demand. PJM said it did not have a load interconnection queue and relied on load-serving entities to submit forecast adjustments. Near-term requests were expected to demonstrate firmer commitments than longer-term projects. ([insidelines.pjm.com](https://insidelines.pjm.com/pjm-kicks-off-annual-process-of-vetting-large-load-requests/))

**Procurement implication:** Ask a developer which utility submitted the load, what commitment supports it and whether the same demand appears elsewhere. Treat inclusion in a forecast as a planning input—not proof that a particular service date has been secured.

### 2. Why did Texas diligence expand beyond electrical studies?

**ERCOT’s 14 September RFI sought project information extending into water, cooling and community impacts.** Its specified recipients included conditionally classified Batch Zero projects and certain substantiated data centres requesting at least 25 MW but below 75 MW, subject to the notice’s energisation conditions. The request was separate from the Batch Zero Eligibility RFI. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01))

**Procurement implication:** Reconcile the cooling design, water assumptions, ownership information and load request before submitting them through different workstreams. For a phased development, ask your service provider how the project and its additions are classified; do not assume an individual phase determines the applicable treatment.

### 3. Does NVIDIA DSX Ready mean a facility is ready?

**No: the programme qualifies specified products against relevant requirements, not an entire deployment.** NVIDIA launched DSX Ready on 21 September with battery energy storage systems and cooling distribution units as its initial categories. NVIDIA explicitly says BESS qualification does not replace site engineering or establish site-level stability; a qualified CDU still requires assessment against the planned facility. ([blogs.nvidia.com](https://blogs.nvidia.com/blog/dsx-ready-ai-factories-power-cooling/))

**Procurement implication:** Request the exact product, qualification scope, configuration and interfaces. Replace “NVIDIA-compatible cooling” in the proposal with a responsibility matrix covering the equipment supplier, facility operator and GPU integrator.

### 4. Why did PJM’s backstop procurement not launch on 30 September?

**Acceptance came with a suspension.** PJM’s 30 September notice said FERC had accepted the backstop proposal but suspended it for five months, with an effective date of 28 February 2027, subject to refund and further proceedings. PJM therefore did not start the procurement on its previously announced date and said the timetable would be reviewed. ([insidelines.pjm.com](https://insidelines.pjm.com/ferc-accepts-pjm-reliability-backstop-proposal/))

**Post-month correction:** FERC’s separate 9 October decision rejected the bulk of the IRAS filing. Keep September descriptions of proposed market arrangements clearly labelled as historical proposals. ([ferc.gov](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-pjm-interconnection-llc-er26-3515-000))

### 5. What does the market benchmark say about negotiating leverage?

**Earlier context—not a September movement:** CBRE’s H1 2026 report, dated 27 August, recorded 1.4% vacancy across its primary markets and 80.4% preleasing of capacity under construction. These are market-level observations, not evidence of a contiguous, technically suitable block available for your start date. ([cbre.com](https://www.cbre.com/insights/books/21435420725))

**Procurement implication:** Use the figures to frame negotiations, not to skip diligence. Ask each bidder to identify the specific hall, phase, capacity reservation and remaining delivery conditions behind its offer.

## What should a high-density colocation comparison contain?

**Compare the same deployable requirement before comparing price.** For a buyer seeking 10 MW of critical IT capacity, the desk recommends the following return schedule; 10 MW is an illustrative requirement, not identified inventory.

| Comparison field | What to request from every bidder |
|---|---|
| Capacity boundary | Utility service MW, facility allocation and critical IT MW stated separately |
| Rack configuration | Supported rack count, density, electrical topology and the specified hardware generation |
| Cooling scope | CDU responsibility, facility-water conditions, technical-loop requirements, heat rejection and residual air cooling |
| Dates | Facility access, energisation, cooling completion, network availability and operational acceptance |
| Commercial commencement | Which event starts rent, power minimums and other commitments |
| Exclusions and remedies | Buyer-funded integration, acceptance tests, unresolved conditions and contractual responses to delay |

NVIDIA’s published DSX reference design illustrates why cooling needs this level of specificity: it distinguishes facility water, a separate technical cooling loop and air cooling for the data halls. Those are features of that reference architecture, not universal specifications for every AI deployment. ([docs.nvidia.com](https://docs.nvidia.com/dsx/facilities-infra/reference-design-overview))

**Do not use annual PUE as a shortcut to a guaranteed peak IT allocation.** DOE defines PUE using total annual facility energy divided by annual IT energy. Our inference: a claimed annual efficiency ratio is insufficient evidence of the electrical and cooling capacity available to a particular rack configuration at peak conditions. ([energy.gov](https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf))

## What can hiring and podcasts add to diligence?

**Use them to improve questions, not to certify delivery.** Fleet Data Centers’ commissioning-manager posting, accessed on 16 October, describes factory and site testing, first energisation, integrated systems testing, issue closure and turnover records. It is useful evidence of the work a delivery plan should address; it does not prove a labour shortage or completion at a particular campus. ([job-boards.greenhouse.io](https://job-boards.greenhouse.io/fleet/jobs/4336702009))

**Background listening:** CBRE’s 23 June episode, *Under Pressure: Can data centers keep up with AI?*, discusses power, permitting and location constraints with Digital Realty and CBRE representatives. Treat it as supplier-side context, not independent confirmation of availability. ([cbre.com](https://www.cbre.com/insights/podcasts/2026-ep26-can-data-centers-keep-up-with-ai))

## What should change in next month’s shortlist?

The desk recommends three changes:

1. **Replace one “ready” date with five dated milestones.** Give each a responsible party and supporting document.
2. **Require a common commercial commencement schedule.** Compare what becomes payable before computing capacity is accepted.
3. **Keep missing evidence visible.** Use “not established” rather than silently converting an unanswered question into either availability or unavailability.

**Reply prompt:** For your next capacity review, bring the required critical IT MW, rack configuration, activation deadline and two competing offers—not just their headline $/kW/month prices.

---

# Draft 3 — Quarterly outlook

**Subject:** Q4 power outlook: fund delivery milestones, not headline MW

**Preview:** Virginia’s 2027 obligations, Texas verification and PJM’s revised proposals should shape the next capital commitment.

**Edition:** Q4 2026 outlook, updated 16 October 2026

**Forward horizon:** 16 October–31 December 2026, with explicitly identified 2027 milestones.

## What is the desk’s base view for the rest of Q4?

**Prioritise documented delivery conditions and manageable commitment sizes over the largest advertised power allocation.** This is a decision framework, not a forecast of prices, returns or universal connection delays.

The near-term work is specific: establish applicable Virginia obligations before 2027 contracting, close Texas information gaps, track PJM’s revised filings and make technical acceptance—not merely facility access—the endpoint of the deployment plan.

## Which territory-specific developments should affect underwriting?

### Virginia: what starts changing in 2027?

Dominion says the approved GS-5 class and tariff become effective on **1 January 2027**. The SCC explains that new qualifying large-load customers contracting on or after that date face a minimum 14-year service obligation. Its guidance also describes minimum transmission and distribution charges and potential collateral requirements for customers without sufficient credit. ([sustainability.dominionenergy.com](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf))

Dominion’s report states demand-charge floors of **85% of contracted demand for transmission and distribution and 60% for generation**. These are different billing components—not an 85% minimum on every element of an electricity bill. ([sustainability.dominionenergy.com](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf))

**Desk recommendation:** Commission a contract-specific monthly ramp model. Ask the utility to confirm applicability, exceptions, phase treatment, collateral, reduction rights and exit provisions before comparing sites on an energy-only rate.

### North Carolina: which proposed costs belong in the sensitivity case?

Duke’s 7 October announcement describes a settlement, subject to regulatory approval, covering upfront connection expenditure and security for shared upgrades. This review has not established a subsequent approval order. ([news.duke-energy.com](https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs))

**Desk recommendation:** Carry proposed obligations as an explicit scenario until applicability is confirmed. Require the approved tariff or order before treating the settlement’s terms as settled contract economics.

### Texas: what does the December reporting milestone mean?

ERCOT’s September notice said it expected to publish conclusions from its **State and Community Impact RFI by 10 December 2026**. That is an expected reporting milestone; the notice does not promise that publication grants an individual project permission to energise. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01))

**Desk recommendation:** Keep separate evidence for classification, completed submissions, study results, network works and permission to energise. Where the remaining process is unclear, identify the uncertainty rather than assigning an unsupported connection date.

### PJM: what should remain outside the base delivery assumption?

FERC’s 29 September backstop order accepted the filing subject to a five-month suspension, refund and further proceedings. PJM’s 12 October motion then set out plans for a revised filing by 29 October. Neither establishes that a particular buyer will receive new supply by its required date. ([pjm.com](https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9154/20260929-er26-3380-000.pdf))

**Desk recommendation:** Underwrite site delivery against the actual utility, supply and construction arrangements. Record prospective regulatory improvements separately as potential upside, not as completed dependencies.

## Does behind-the-meter generation remove the permitting problem?

**No single Texas authorisation covers every operating model.** TCEQ distinguishes portable or emergency engines and turbines, electric-generating-unit standard permits and case-by-case construction permits where other authorisations do not apply. Its guidance also states that the stationary-engine-and-turbine permit by rule identified there cannot be used for electric generators. ([tceq.texas.gov](https://www.tceq.texas.gov/permitting/air/guidance/newsourcereview/turbines/nsrauth_turb.html))

**Desk recommendation:** Before accepting a bridge-power timetable, request evidence for:

- The proposed operating duty and matching authorisation route.
- Net usable output under the design conditions—not only equipment nameplate output.
- Fuel delivery arrangements and operating constraints.
- Equipment delivery, installation and acceptance milestones.
- Grid-transition responsibilities and the treatment of stranded temporary equipment.

Have qualified engineering and environmental advisers confirm these points. Do not treat an emergency-use permission as evidence supporting continuous commercial operation.

## How should the committee test time-to-compute exposure?

**Run separate delay cases for utility service, facility integration and customer ramp.** Do not apply one generic “cost per month of delay” to all three.

### Illustrative capacity-rent exposure—not a market quote

Assume a buyer contracts for **10,000 kW of critical IT capacity at $175/kW/month**. These are illustrative assumptions, not observed pricing or a statement of available capacity.

| Assumed billing outcome during three full months before usable compute | Capacity rent paid during that period |
|---|---:|
| Rent commencement is deferred until acceptance | $0 |
| Full contracted rent has already commenced | $5.25 million |

The second calculation is **10,000 × $175 × 3**. Monthly rent is $1.75 million. This isolates one contract cash-flow item; it is neither a universal delay loss nor necessarily incremental to the entire lease term.

For the actual project, build four separate schedules:

1. **Recurring cash:** capacity rent, applicable utility charges, staffing and other contractual payments.
2. **Incremental delay cash:** storage, remobilisation, extra financing and buyer-confirmed penalties.
3. **Liquidity commitments:** deposits, letters of credit and collateral, distinguishing balances from fees or expenses.
4. **Commercial impact:** deferred contribution and demonstrably lost business, without treating every delayed sale as permanently lost.

Apply demand floors and ratchets according to the actual tariff; do not add a “minimum bill” again when it has already replaced the relevant billing quantity. The need for component-specific treatment is illustrated by Dominion’s separate transmission/distribution and generation floors. ([sustainability.dominionenergy.com](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf))

## Which evidence should release the next tranche of capital?

**Use separate commitment gates rather than a blended readiness score.** The following is the desk’s proposed checklist, to be tailored with the buyer’s legal, utility and engineering advisers.

| Gate | Evidence to request | Suggested reason to pause the next commitment |
|---|---|---|
| Land control | Executable control documents, access rights and relevant easements | Required rights remain unresolved |
| Planning and permits | Permission register, operating conditions and outstanding decisions | A necessary permission lacks a supportable path |
| Utility arrangements | Applicable agreement, load definition, service conditions and payment schedule | The commercial claim exceeds the supplied document |
| Network works | Defined scope, responsible party, funding and dated milestones | The activation case assumes unfinished works away |
| Equipment and facility systems | Confirmed configuration, delivery records, cooling interfaces and network scope | A critical interface or delivery remains unowned |
| Commissioning and acceptance | Test plan, witnessed results, defect closure and acceptance responsibility | A building-completion date substitutes for tested operation |

This emphasis on documented tests and turnover is consistent with the activities described in Fleet’s commissioning role and Strategic Mission Critical’s mechanical commissioning role, including functional tests, integrated systems testing and deficiency resolution. The postings substantiate the work involved, not readiness at any named facility. ([job-boards.greenhouse.io](https://job-boards.greenhouse.io/fleet/jobs/4336702009))

## Which dates belong on the watchlist?

| Date or period | Published milestone | What the buyer should verify |
|---|---|---|
| 22 October 2026 | PJM consultation identified in its motion | Whether proposed changes affect costs or obligations. ([pjm.com](https://www.pjm.com/-/media/DotCom/documents/other-fed-state/20261012-el26-108-000.pdf)) |
| By 29 October 2026 | PJM’s planned revised backstop filing | Whether it was filed and what changed; filing is not approval. ([pjm.com](https://www.pjm.com/-/media/DotCom/documents/other-fed-state/20261012-el26-108-000.pdf)) |
| November 2026 | PJM said it would explain final load adjustments for the 2027 forecast | Whether assumptions relevant to the project have changed. ([insidelines.pjm.com](https://insidelines.pjm.com/pjm-kicks-off-annual-process-of-vetting-large-load-requests/)) |
| By 10 December 2026 | ERCOT’s expected community-impact report | Findings and any subsequent project-specific requests. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)) |
| 1 January 2027 | Dominion’s stated GS-5 effective date | Actual tariff and contract applicability. ([sustainability.dominionenergy.com](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf)) |

**The quarter-end test:** Can another reviewer trace every material MW, date and payment assumption to a current document, identify its conditions and name the person responsible for the next unresolved action?

**Reply prompt:** Which assumption would stop your next approval if it changed tomorrow? Make that the first item in the Investment Committee Change Radar.

---

# Sources

Primary sources support the technical and regulatory items. Company announcements are attributed to their issuers; market research, recruitment materials and podcasts are used within their stated limits. All sources were reviewed for this 16 October 2026 research cut-off.

1. **DOE — Order 202-26-50 overview**, issued 12 October 2026: `https://www.energy.gov/ceser/federal-power-act-section-202c-pjm-interconnection-llc-pjm-order-no-202-26-50
2. **PJM — Providing Reliable Electricity in a New Reality**, 15 October 2026: `https://insidelines.pjm.com/providing-reliable-electricity-in-a-new-reality/
3. **PJM — Motion for Abeyance**, 12 October 2026: `https://www.pjm.com/-/media/DotCom/documents/other-fed-state/20261012-el26-108-000.pdf
4. **FERC — Commissioner Rosner’s concurrence, ER26-3515-000**, 9 October 2026: `https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-pjm-interconnection-llc-er26-3515-000
5. **ERCOT — Medium-load RFI clarification**, 24 September 2026: `https://www.ercot.com/services/comm/mkt_notices/M-B091426-02
6. **ERCOT — State and Community Impact RFI notice**, 14 September 2026: `https://www.ercot.com/services/comm/mkt_notices/M-B091426-01
7. **ERCOT — Batch/CTP workshop agenda**, 15 October 2026: `https://www.ercot.com/calendar/10152026-Batch_CTP-Workshop-3a_Batch-Scope
8. **Duke Energy — North Carolina large-load settlement announcement**, 7 October 2026: `https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs
9. **PJM — Annual large-load review**, 29 September 2026: `https://insidelines.pjm.com/pjm-kicks-off-annual-process-of-vetting-large-load-requests/
10. **NVIDIA — DSX Ready launch**, 21 September 2026: `https://blogs.nvidia.com/blog/dsx-ready-ai-factories-power-cooling/
11. **PJM — Backstop procurement update**, 30 September 2026: `https://insidelines.pjm.com/ferc-accepts-pjm-reliability-backstop-proposal/
12. **CBRE — North America Data Center Trends H1 2026**, 27 August 2026: `https://www.cbre.com/insights/books/21435420725
13. **NVIDIA — DSX Facilities Infrastructure Reference Design Overview**, referencing the 19 August 2026 design guide: `https://docs.nvidia.com/dsx/facilities-infra/reference-design-overview
14. **DOE — Best Practices Guide for Energy-Efficient Data Center Design**, 2024: `https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf
15. **Fleet Data Centers — Commissioning Senior Manager, Electrical**, recruitment page accessed 16 October 2026: `https://job-boards.greenhouse.io/fleet/jobs/4336702009
16. **CBRE — Under Pressure: Can data centers keep up with AI?**, podcast and transcript, 23 June 2026: `https://www.cbre.com/insights/podcasts/2026-ep26-can-data-centers-keep-up-with-ai
17. **Virginia SCC — Data Center Initiatives and related rate explanations**, accessed 16 October 2026: `https://www.scc.virginia.gov/about-the-scc/scc-facts/
18. **Dominion Energy — GS-5 Large-Load Rate Class Report**, accessed 16 October 2026: `https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf
19. **FERC — Backstop procurement order, ER26-3380-000**, 29 September 2026, hosted by PJM: `https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9154/20260929-er26-3380-000.pdf
20. **TCEQ — Types of Authorization for Turbines**, last modified 23 January 2026: `https://www.tceq.texas.gov/permitting/air/guidance/newsourcereview/turbines/nsrauth_turb.html
21. **Strategic Mission Critical — Mechanical Commissioning Advisor**, recruitment page accessed 16 October 2026: `https://job-boards.greenhouse.io/strategicmissioncritical/jobs/4361711009

## FAQs
### Did PJM force data centres to use backup generators during the October 2026 emergency?
PJM’s 15 October update said it had not used the backup-generation authority provided by DOE. That is distinct from demand-response activation, which PJM reported on 13 and 14 October. ([insidelines.pjm.com](https://insidelines.pjm.com/providing-reliable-electricity-in-a-new-reality/))
### Does inclusion in PJM’s load forecast prove power is available to a site?
No: PJM describes a forecasting process using utility submissions, contract information and checks on project credibility. Our diligence recommendation is to obtain separate site-specific evidence for service conditions, network works and delivery dates. ([insidelines.pjm.com](https://insidelines.pjm.com/pjm-kicks-off-annual-process-of-vetting-large-load-requests/))
### Are utility service MW and critical IT MW interchangeable?
No: facility energy includes supporting infrastructure as well as IT equipment, a distinction reflected in DOE’s PUE definition. Request both capacity boundaries explicitly and have the project engineer validate the usable IT allocation rather than deriving a guaranteed peak capacity from annual PUE. ([energy.gov](https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf))
### Does NVIDIA DSX Ready certify that an entire data centre is ready for deployment?
The programme qualifies specified products against applicable requirements, beginning with BESS and CDUs. NVIDIA says qualification still requires site-specific engineering and assessment of how the equipment fits the planned facility. ([blogs.nvidia.com](https://blogs.nvidia.com/blog/dsx-ready-ai-factories-power-cooling/))
### What should buyers check about Dominion’s large-load minimum bills?
Dominion’s report distinguishes transmission and distribution demand floors from the generation demand floor; these should not be treated as one percentage applied to the whole bill. Obtain the applicable tariff and service agreement, then model each component against the proposed monthly ramp. ([sustainability.dominionenergy.com](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf))
### Was Duke’s North Carolina large-load settlement already approved when announced?
Duke’s 7 October announcement expressly described the agreement as subject to state regulatory approval. This research did not establish a subsequent approval, so buyers should request the controlling order and tariff before treating the announced terms as final. ([news.duke-energy.com](https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs))
### Can emergency-generation permissions support continuous bridge power in Texas?
Do not assume they can: TCEQ identifies different authorisation routes for emergency equipment and electricity-generating facilities. Have an environmental specialist confirm that the permission matches the actual operating duty and equipment configuration. ([tceq.texas.gov](https://www.tceq.texas.gov/permitting/air/guidance/newsourcereview/turbines/nsrauth_turb.html))
### What evidence should support a data centre’s operational acceptance date?
Request the commissioning plan, functional and integrated test results, unresolved-defect register and signed turnover responsibilities. Employer commissioning specifications explicitly include these activities, but a recruitment posting is not evidence that any particular facility has completed them. ([job-boards.greenhouse.io](https://job-boards.greenhouse.io/strategicmissioncritical/jobs/4361711009))

## Sources
- [Federal Power Act Section 202(c): PJM Interconnection, L.L.C. (PJM) Order No. 202-26-50 | Department of Energy](https://www.energy.gov/ceser/federal-power-act-section-202c-pjm-interconnection-llc-pjm-order-no-202-26-50)
- [Microsoft Word - Motion for Abeyance - RBP Paper Hearing](https://www.pjm.com/-/media/DotCom/documents/other-fed-state/20261012-el26-108-000.pdf)
- [Commissioner Rosner’s Concurrence in PJM Interconnection, L.L.C. (ER26-3515-000) | Federal Energy Regulatory Commission](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-pjm-interconnection-llc-er26-3515-000)
- [Market Notice Details](https://www.ercot.com/services/comm/mkt_notices/M-B091426-02)
- [Market Notice Details](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)
- [Event Details](https://www.ercot.com/calendar/10152026-Batch_CTP-Workshop-3a_Batch-Scope)
- [Duke Energy protects customers from data center costs | Duke Energy | News Center](https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs)
- [PJM Kicks Off Annual Process of Vetting Large Load Requests | PJM Inside Lines](https://insidelines.pjm.com/pjm-kicks-off-annual-process-of-vetting-large-load-requests/)
- [Market Notice Details](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)
- [NVIDIA Launches DSX Ready to Qualify Power and Cooling Products for AI Factories | NVIDIA Blog](https://blogs.nvidia.com/blog/dsx-ready-ai-factories-power-cooling/)
- [FERC Accepts PJM Reliability Backstop Proposal | PJM Inside Lines](https://insidelines.pjm.com/ferc-accepts-pjm-reliability-backstop-proposal/)
- [North America Data Center Trends H1 2026 | CBRE](https://www.cbre.com/insights/books/21435420725)
- [DSX Facilities Infrastructure Reference Design Overview | NVIDIA DSX Documentation](https://docs.nvidia.com/dsx/facilities-infra/reference-design-overview)
- [Best Practices Guide for Energy-Efficient Data Center Design](https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf)
- [page_title](https://job-boards.greenhouse.io/fleet/jobs/4336702009)
- [Under Pressure: Can data centers keep up with AI? | CBRE](https://www.cbre.com/insights/podcasts/2026-ep26-can-data-centers-keep-up-with-ai)
- [Dominion Energy’s High-Load Customer Proposal](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf)
- [20260929-3099_ER26-3380-000.docx](https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9154/20260929-er26-3380-000.pdf)
- [Types of Authorization for Turbines - Texas Commission on Environmental Quality - www.tceq.texas.gov](https://www.tceq.texas.gov/permitting/air/guidance/newsourcereview/turbines/nsrauth_turb.html)
- [Providing Reliable Electricity in a New Reality | PJM Inside Lines](https://insidelines.pjm.com/providing-reliable-electricity-in-a-new-reality/)
- [Job Application for Mechanical Commissioning Advisor - Mission Critical at Strategic Mission Critical](https://job-boards.greenhouse.io/strategicmissioncritical/jobs/4361711009)
- [https://www.energy.gov/ceser/federal-power-act-section-202c-pjm-interconnection-llc-pjm-order-no-202-26-50](https://www.energy.gov/ceser/federal-power-act-section-202c-pjm-interconnection-llc-pjm-order-no-202-26-50)
- [https://insidelines.pjm.com/providing-reliable-electricity-in-a-new-reality/](https://insidelines.pjm.com/providing-reliable-electricity-in-a-new-reality/)
- [https://www.pjm.com/-/media/DotCom/documents/other-fed-state/20261012-el26-108-000.pdf](https://www.pjm.com/-/media/DotCom/documents/other-fed-state/20261012-el26-108-000.pdf)
- [https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-pjm-interconnection-llc-er26-3515-000](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-pjm-interconnection-llc-er26-3515-000)
- [https://www.ercot.com/services/comm/mkt_notices/M-B091426-02](https://www.ercot.com/services/comm/mkt_notices/M-B091426-02)
- [https://www.ercot.com/services/comm/mkt_notices/M-B091426-01](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)
- [https://www.ercot.com/calendar/10152026-Batch_CTP-Workshop-3a_Batch-Scope](https://www.ercot.com/calendar/10152026-Batch_CTP-Workshop-3a_Batch-Scope)
- [https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs](https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs)
- [https://insidelines.pjm.com/pjm-kicks-off-annual-process-of-vetting-large-load-requests/](https://insidelines.pjm.com/pjm-kicks-off-annual-process-of-vetting-large-load-requests/)
- [https://blogs.nvidia.com/blog/dsx-ready-ai-factories-power-cooling/](https://blogs.nvidia.com/blog/dsx-ready-ai-factories-power-cooling/)
- [https://insidelines.pjm.com/ferc-accepts-pjm-reliability-backstop-proposal/](https://insidelines.pjm.com/ferc-accepts-pjm-reliability-backstop-proposal/)
- [https://www.cbre.com/insights/books/21435420725](https://www.cbre.com/insights/books/21435420725)
- [https://docs.nvidia.com/dsx/facilities-infra/reference-design-overview](https://docs.nvidia.com/dsx/facilities-infra/reference-design-overview)
- [https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf](https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf)
- [https://job-boards.greenhouse.io/fleet/jobs/4336702009](https://job-boards.greenhouse.io/fleet/jobs/4336702009)
- [https://www.cbre.com/insights/podcasts/2026-ep26-can-data-centers-keep-up-with-ai](https://www.cbre.com/insights/podcasts/2026-ep26-can-data-centers-keep-up-with-ai)
- [https://www.scc.virginia.gov/about-the-scc/scc-facts/](https://www.scc.virginia.gov/about-the-scc/scc-facts/)
- [https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf](https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf)
- [https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9154/20260929-er26-3380-000.pdf](https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9154/20260929-er26-3380-000.pdf)