# US Data Center Power Regulation: October 2026 Changes and 2027 Commitment Risks

# US Data Center Power Regulation: October 2026 Changes and 2027 Commitment Risks

**Research cutoff: 19 October 2026.** Prepared for Load & Date Research. Written for independent developers assessing 20–100 MW phased projects, AI operators procuring 5–30 MW of colocation, and their energy and capital teams.

## Which changes should alter a buyer’s next commitment?

**Revalidate Texas approvals, Virginia generator specifications and large-load payment obligations before releasing the next material payment.** Texas’s September permitting directive, Virginia’s July generator-permit requirements and Dominion’s approaching January 2027 contract provisions create distinct diligence questions; none should be reduced to a generic assessment of whether a state welcomes data centres. ([gov.texas.gov](https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits))

Grid reform also requires careful status checking. FERC has initiated regional tariff reforms, while SPP has obtained approval for a conditional service expressly subject to interruption. Neither development establishes firm, site-specific capacity for a buyer. ([ferc.gov](https://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration))

The newest standards development identified is NERC’s **15 October 2026 announcement that computational-load standards passed their final ballot**. That announcement describes further Board adoption and regulatory approval steps—not an already-effective compliance deadline for every data centre. ([nerc.com](https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption))

### What should each buyer prioritise?

The following priorities are **desk recommendations**, not findings about any particular project.

| Buyer | Immediate decision | Evidence to obtain before committing |
|---|---|---|
| Development decision-maker | Extend an option, acquire land or fund utility works | Current approval pathway; project-specific treatment under new rules; written capacity allocation and outstanding conditions |
| AI capacity operator | Reserve colocation or release hardware | Host-facility obligations, usable critical IT capacity, interruption conditions, generator compliance and acceptance milestones |
| Energy procurement leader | Sign service or supply arrangements | Effective tariff sheets, billing determinants, security requirements, ramp provisions and exit exposure |
| Capital gatekeeper | Approve financing or construction expenditure | A dated change memo showing which underwriting assumptions require replacement or confirmation |

## How should buyers distinguish a rule from a proposal?

This report separates **enacted requirements, adopted rules, procedural orders, proposed tariffs and published standards**. A settlement announcement is not treated as a commission approval; a standards ballot is not treated as an effective reliability obligation; and a future reporting date is not treated as an energisation date.

Coverage is selective rather than a 50-state legal survey. Where the latest implementing tariff, project exception or subsequent order was not established, that limitation is explicit. Recommended actions should be implemented with the relevant utility, permitting authority and qualified advisers; this is not a project-specific legal or engineering opinion.

## 1. What changed in Texas—and can a project still rely on its previous approval timetable?

**Do not rely on an earlier Texas development timetable without written reconfirmation of the audit and permitting conditions applicable to the project.** Three separate developments matter: the governor’s audit direction, ERCOT’s information requests and the adopted large-load interconnection standards. ([gov.texas.gov](https://gov.texas.gov/news/post/governor-abbott-directs-comprehensive-data-center-audit?trk=public_post_comment-text))

### What did the August and September directives change?

On **3 August 2026**, Governor Greg Abbott directed PUCT and ERCOT to verify and audit data centres progressing through ERCOT’s interconnection process before projects advance. The announcement states that non-compliant projects must be denied grid connection. ([gov.texas.gov](https://gov.texas.gov/news/post/governor-abbott-directs-comprehensive-data-center-audit?trk=public_post_comment-text))

On **21 September 2026**, the governor directed TCEQ to halt permits sought by data centres pending the audit information. The directive required a TCEQ compliance update by **19 October 2026**. That is a reporting deadline, not an announced reopening date. This research did not establish a subsequent general release of the permitting restriction. ([gov.texas.gov](https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits))

**Who should act:** Texas developers, buyers of partially entitled sites, operators relying on new environmental approvals, and investors underwriting either grid-connected or on-site-generation delivery strategies.

**Recommended action:** request a project-specific statement identifying:

- Which approvals are affected, including amendments and outstanding applications.
- Whether an audit response has been accepted, rather than merely submitted.
- Whether any exception or permission to proceed exists in writing.
- Which contractual milestone changes if the restriction continues.

Do not describe the directive as cancellation of every existing permit or a universal stop-work order. Those project-specific consequences were not established by the announcement reviewed.

### Does remaining below 75 MW avoid the information requirements?

**Not necessarily.** ERCOT’s **14 September 2026** State and Community Impact RFI covered specified Batch Zero projects and certain unenergised, substantiated data-centre projects with requested peak load of **at least 25 MW but below 75 MW**. It required complete responses, supporting documents and a notarised developer attestation by **5 p.m. Central Prevailing Time on 12 October 2026**. ERCOT expected to publish its report by **10 December 2026**. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01))

Separately, the governor’s **14 September 2026** water-reporting direction instructed TWDB to enforce survey requirements and coordinate with ERCOT. The official announcement identifies potential criminal and permit-related consequences for non-compliance with the applicable water-survey requirements. ([gov.texas.gov](https://gov.texas.gov/news/post/governor-abbott-directs-twdb-to-penalize-data-center-reporting-failures))

**Recommended action:** obtain the RIOO submission confirmation and an open-item register from the responsible utility and developer. Treat a missed deadline as an immediate escalation to counsel and the relevant agencies—not as something cured by a general assertion that the project is small or uses little water.

### What do the adopted large-load standards add to the capital requirement?

The **2 October 2026 Texas Register** published adopted **16 TAC §25.194**. It addresses qualifying, not-yet-energised large-load interconnections, including new single-site requests of at least 75 MW and specified expansions. The intermediate-agreement requirements include a **$100,000 study fee** and **$50,000/MW financial security**; additional equipment commitments and later obligations can increase exposure. The commission rejected a blanket exemption merely because an agreement had previously been signed. Batch Zero receives specific transition treatment. ([sos.texas.gov](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html))

**Illustration, not a project quotation:** 100 MW × $50,000/MW is **$5 million of intermediate security**. That is not necessarily a cash expense or the total connection cost; the permitted security form and other obligations require separate review. ([sos.texas.gov](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html))

**Recommended action:** have counsel reconcile the existing agreement, Batch Zero classification, allocated MW, security already posted and required replacement agreements. Request a single schedule separating study fees, security, direct construction payments and potentially forfeitable amounts.

### Did Batch Zero approval itself secure power?

PUCT approved ERCOT’s Batch Zero process on **18 June 2026**, replacing individual evaluation with a grouped study framework for qualifying projects of **75 MW and above**. Its purpose includes assessing system impacts and allocating available capacity; it is not a declaration that every applicant’s requested MW can be delivered. ([ercot.com](https://www.ercot.com/news/release/06182026-puct-approves-ercots?trk=article-ssr-frontend-pulse_little-text-block))

**Commitment test:** require the project’s actual classification, study result, allocation and outstanding energisation conditions. Keep these separate from the subsequently imposed audit and permitting questions.

## 2. Has FERC created a national fast track for data-centre power?

**No universal, immediately available connection entitlement was established by the material reviewed.** On **18 June 2026**, FERC issued tailored section 206 show-cause orders to PJM, MISO, SPP, CAISO, ISO New England and NYISO. The orders required the operators and transmission owners to justify existing arrangements or propose changes, with initial 30-day information-report and 60-day tariff-response requirements. Those initial response periods are already past. ([ferc.gov](https://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration))

The subjects include transmission studies, cost shifting, co-location, flexible-load service and generation serving nearby loads. Buyers must now examine the relevant regional responses and subsequent orders—not continue treating the June announcement as the latest operative tariff. ([ferc.gov](https://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration))

FERC’s **9 October 2026** Duke concurrence also expressly described the broader DOE large-load ANOPR as still pending. It should not be confused with a completed nationwide final rule. ([ferc.gov](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-duke-energy-carolinas-llc-er26-2691-000-er26-2691))

**Recommended action:** identify three separate documents in every power evidence pack:

1. The applicable retail service arrangement.
2. The transmission service and cost-recovery arrangement.
3. The site-specific study and construction conditions.

For co-location, obtain the permitted import configuration, responsibility during a generator outage and the actual transmission product. FERC issued a further PJM co-location rehearing and compliance order on **18 June 2026**; relying only on the December 2025 announcement is therefore insufficient. This pass did not fully verify the subsequent operative PJM tariff revisions. ([ferc.gov](https://www.ferc.gov/sites/default/files/2026-06/EL25-49-002_0.pdf))

## 3. What new SPP pathways exist—and what reliability compromise must buyers price?

**SPP offers approved large-load processes, but conditional transmission must not be marketed as equivalent to firm service.** On **14 January 2026**, FERC accepted SPP’s High Impact Large Load and associated High Impact Large Load Generation Assessment processes, including an approach for generation serving qualifying nearby large loads. ([ferc.gov](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-order-accepting-tariff-revisions-subject))

On **5 June 2026**, FERC accepted **Conditional High Impact Large Load Service, or CHILLS**. FERC describes it as as-available transmission, subject to curtailment and interruption, while designated resources or network upgrades needed for long-term firm service are developed. Its maximum term is seven years. ([ferc.gov](https://www.ferc.gov/sites/default/files/2026-06/EL26-71-000.pdf))

**Who should act:** developers considering SPP sites and AI operators whose workloads might tolerate a conditional initial service arrangement.

**Recommended action:** create a separate conditional-service case rather than reducing the assumed grid lead time in the firm-service case. Ask the provider to document:

- The precise portion of load eligible for the service.
- Curtailment triggers, notice, restoration and telemetry requirements.
- What generation and upgrades are necessary for conversion to firm service.
- The consequences if that conversion is late.
- Whether the customer’s compute commitments permit the resulting interruptions.

The commercial question is not simply whether earlier connection is possible. It is whether the **permitted operating envelope** supports the proposed customer contracts.

## 4. What changes for Dominion customers from January 2027?

**Qualifying customers need a revised minimum-payment and credit model, not just an updated energy price.** The Virginia SCC’s **24 February 2026** factsheet explains its large-load provisions in Case **PUR-2025-00058**:

- New qualifying customers contracting for service on or after **1 January 2027** face a minimum **14-year** service obligation.
- Minimum transmission and distribution payment obligations apply to qualifying new and existing customers, with an exemption identified for customers whose service began before **1 January 2016**.
- Customers without sufficient credit may need guarantees covering up to **60% of minimum charges over the contract term**. ([scc.virginia.gov](https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf))

The SCC describes the transmission/distribution minimum as **85% of the costs incurred to serve the customer each month**. This is not a basis for assuming that 85% of every electricity bill—or 85% of annual kWh—is payable under every contract. Obtain the approved billing determinants and applicability provisions. ([scc.virginia.gov](https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf))

### What additional transmission-cost change needs attention?

The SCC’s current facts page describes **2026 Rider T1** changes: a forecast adjustment for expanding large loads, incorporation of the previously approved transmission minimum, and a prospective framework to directly assign certain transmission facilities needed for new or expanding large-load customers. It also states that further proceedings are required to implement the line-extension details. The final implementing amendments were not established in this pass. ([scc.virginia.gov](https://www.scc.virginia.gov/about-the-scc/scc-facts/))

**Recommended action:** ask Dominion for a written applicability matrix covering the customer entity, existing service date, expansion, contract execution date, ramp schedule, billing demand, security and direct-connect costs. Do not assume that an existing campus’s treatment automatically extends to a new phase.

For a colocation buyer, request an explicit allocation of those obligations between landlord and tenant. Underwriting should distinguish what the utility can charge the operator from what the lease permits the operator to pass through.

## 5. Why must buyers separate Duke’s October federal approval from its North Carolina settlement?

**They are different regulatory instruments at different jurisdictional levels.** Duke announced a North Carolina large-load settlement on **7 October 2026**, involving Duke Energy Carolinas, Duke Energy Progress, Public Staff and other parties. On **14 October 2026**, the North Carolina Department of Justice still described the retail arrangement as a proposal before the Utilities Commission. A final state approval was not established in this research. ([news.duke-energy.com](https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs))

Separately, FERC accepted Duke Energy Carolinas’ transmission proposal in **ER26-2691-000 and ER26-2691-001** on **9 October 2026**, as confirmed by Commissioner Rosner’s concurrence. That federal action does not establish approval of the North Carolina retail settlement. ([ferc.gov](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-duke-energy-carolinas-llc-er26-2691-000-er26-2691))

**Recommended action:** maintain separate federal-transmission and state-retail entries in the diligence register. For each, record the approved or proposed text, effective date, covered entities and transition provisions.

Do not insert percentages or contract terms taken from settlement coverage into the committed base-case model until the executed arrangement and applicable regulatory treatment have been checked. This pass did not independently extract the complete filed North Carolina settlement schedules.

### What should Ohio buyers retain as an existing baseline?

Ohio’s change is older but remains relevant to comparison. On **9 July 2025**, PUCO ordered AEP Ohio to create data-centre-specific tariffs in **24-508-EL-ATA** and lift its connection moratorium as soon as possible. This is a historical baseline, not a newly announced October 2026 reform. ([content.govdelivery.com](https://content.govdelivery.com/accounts/OHPUC/bulletins/3e8bb79))

AEP’s announcement describes an **85% minimum subscription payment** for large new data-centre customers. The current complete tariff book was not successfully retrieved in this pass, so this report does **not** certify the current customer-specific formula, exceptions, riders or delivered electricity price. ([aepohio.com](https://www.aepohio.com/company/news/view?releaseID=10326))

**Recommended action:** obtain the effective Schedule DCT and signed service agreement before using an Ohio quote in a cross-market comparison. Do not copy Dominion’s minimum-payment mechanics into an AEP model because the headline percentage looks similar.

## 6. What did NERC change on 15 October 2026?

**The standards-development process reached a major milestone; universal enforceability was not established.** NERC announced on **15 October 2026** that its Computational Loads Reliability Standards and implementation plans passed final ballot under **Project 2026-02**. The announcement says the standards would next go to the Board of Trustees for adoption and then to FERC for US regulatory approval. ([nerc.com](https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption))

NERC links the work to its May 2026 Level 3 Essential Action Alert, incident reviews and Large Loads Working Group. The reviewed announcement does not establish a final, generally applicable compliance date or demonstrate that every data-centre owner must register in a particular category. ([nerc.com](https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption))

**Recommended preparation—not a statement of current mandatory requirements:**

- Assign an owner for monitoring adoption, approval and implementation milestones.
- Ask the utility and grid adviser which modelling and performance information they require now.
- Include model delivery, control-setting access and technical cooperation in equipment and operator contracts.
- Identify who pays if later accepted requirements necessitate changes before energisation.

For an AI operator, put these questions to the facility operator rather than assuming that the operator’s existing resilience certification resolves grid-interface compliance.

## 7. Do recent EPA changes make behind-the-meter gas generation an easier regulatory shortcut?

**Some federal requirements are changing, but the sources do not support treating on-site generation as permit-free.** Separate turbine standards, greenhouse-gas rules and emergency-engine operating permissions.

### What changed for stationary turbines?

EPA’s official rule index lists a **15 January 2026 final rule for stationary gas and combustion turbines, subpart KKKKa**. A procurement review should therefore identify the applicable final subpart rather than relying on a memorandum written against the November 2024 proposal. This pass did not extract the complete final emissions tables and unit-specific applicability tests. ([epa.gov](https://www.epa.gov/stationary-sources-air-pollution/stationary-gas-and-combustion-turbines-new-source-performance))

**Recommended action:** require the environmental adviser and supplier to agree a written applicability matrix covering equipment type, construction or modification trigger, fuel, operating profile, controls and permit assumptions before issuing an irrevocable order.

### What is changing on 16 November 2026?

EPA’s **17 September 2026** final partial repeal of power-sector carbon standards has an effective date of **16 November 2026**. It removes specified requirements, including the CCS-based Phase 2 standards for new baseload combustion turbines. The same Federal Register notice distinguishes that final action from a separate proposal to rescind all remaining greenhouse-gas requirements for fossil-fuel electric generating units. ([govinfo.gov](https://www.govinfo.gov/content/pkg/FR-2026-09-17/html/2026-19071.htm))

**Buyer implication:** do not treat the proposed broader repeal as enacted, or apply the partial repeal before its effective date. Also do not assume every behind-the-meter machine is an affected electric generating unit; have counsel determine applicability to the actual configuration.

The litigation and stay position was not comprehensively verified in this pass. Recheck it before relying on the November effective date in procurement or financing documents.

### Can emergency generators support ordinary bridge-power operations?

EPA’s data-centre guidance says that operation pursuant to specified **spring and summer 2026 DOE section 202(c) emergency orders** is treated as emergency operation under the cited stationary-engine rules. Such hours do not count against the specified non-emergency allowance. That explanation is tied to the emergency orders; it does not establish unrestricted permission for routine economic dispatch or normal bridge-power operation. ([epa.gov](https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers))

**Recommended action:** obtain a permitted-operating-modes schedule showing emergency response, testing, maintenance, demand response and planned bridge operation separately. The authority relied upon, fuel availability and operating records should be identified for each mode.

## 8. What changed for Virginia data-centre generator permits on 1 July 2026?

**The permit-application date now matters directly to generator specifications.** Virginia Code **§10.1-1322.6**, added in 2026, provides that for data-centre permit applications submitted on or after **1 July 2026**, DEQ may not issue the relevant permit unless each generator set’s permitted emissions are no higher than those achieved by a **Tier 4-equivalent** set. The provision includes coverage under a general permit. ([law.lis.virginia.gov](https://law.lis.virginia.gov/vacodeupdates/title10.1/section10.1-1322.6/))

The statute defines Tier 4 equivalence through nitrogen-oxide, carbon-monoxide and particulate controls or equivalents, and preserves authority to impose more stringent requirements. It is not simply a requirement that a vendor attach a particular marketing label to the equipment. ([law.lis.virginia.gov](https://law.lis.virginia.gov/vacodeupdates/title10.1/section10.1-1322.6/))

**Who should act:** Virginia developers submitting new applications, operators planning relevant expansions or permit changes, and buyers considering generator orders made against older specifications.

**Recommended action:** reconcile the application submission date, permit scope and proposed emissions limits with the purchase specification. Obtain written advice on the treatment of any amendment or previously submitted application; this report does not infer a blanket retrofit obligation for every existing generator.

For the GPU-to-power timetable, require the delivery programme to include any necessary emissions controls, integration and testing—not just arrival of the engine-generator package.

## 9. What does ASHRAE 90.4-2025 change for procurement?

**Use the current edition deliberately, but do not confuse publication with local legal adoption.** ASHRAE lists **Standard 90.4-2025, Energy Standard for Data Centers**, as published and superseding the 2022 edition. Its scope covers new facilities, additions and modifications to relevant systems and equipment. The publisher listing reviewed did not establish an exact publication day. ([ashrae.org](https://www.ashrae.org/technical-resources/standards-and-guidelines/titles-purposes-and-scopes?trk=article-ssr-frontend-pulse_little-text-block))

ASHRAE’s description identifies three notable changes: an expanded purpose addressing wider environmental considerations; updated process-heat and ventilation definitions; and clarified UPS/electrical-loss calculations requiring UPS efficiency to be based on total available capacity, including redundancy. ([resourcecenter.ashrae.org](https://resourcecenter.ashrae.org/technical-resources/translated-publications))

ASHRAE describes its standards as voluntary consensus standards. Publication alone is therefore not evidence that a particular jurisdiction or contract has adopted the new edition. ([ashrae.org](https://www.ashrae.org/file%20library/about/government%20affairs/public%20policy%20resources/ashrae-letter-to-doe-on-data-centers.pdf))

**Recommended action:** add an edition-and-adoption schedule to the design basis:

| Question | Required response |
|---|---|
| Which edition governs the project? | Identify the adopted code, permit condition or contractual specification |
| What changed from the existing design basis? | Provide a documented design comparison, not a generic compliance statement |
| How is redundancy represented? | State the UPS configuration and calculation basis |
| Does the efficiency claim establish AI compatibility? | Provide a separate rack, coolant, heat-rejection and commissioning assessment |

Treat the final row as an independent procurement requirement. An energy-standard reference should not substitute for equipment-specific evidence of usable high-density capacity.

## 10. What is changing in Loudoun’s data-centre planning pathway?

**Separate the already-adopted special-exception requirement from the next package of proposed standards.** Loudoun adopted Phase 1 on **18 March 2025**, requiring special-exception approval for data centres in the specified Industrial Park, General Industry and Mineral Resources–Heavy Industry districts. Its grandfathering resolution provides a route for certain applications accepted before **12 February 2025**; it is not an automatic exemption for every previously discussed project. ([loudoun.gov](https://www.loudoun.gov/6221/Phase-1-Project-Plan-for-Data-Center-Sta))

The more recent change is the active **Phase 2** process. The county held open houses on **28 and 30 September 2026** and published proposed amendments and materials covering matters including siting, noise, on-site energy, substations and battery storage. These materials are proposals, not evidence that every discussed restriction is already binding. ([loudoun.gov](https://www.loudoun.gov/m/NewsFlash/Home/Detail/10823))

The county’s project information anticipated Planning Commission consideration in **February 2027**. That is a planning expectation, not a guaranteed approval date. ([loudoun.gov](https://www.loudoun.gov/DataCenterStandards))

**Recommended action before land acquisition:**

- Obtain a parcel-specific planning pathway and grandfathering assessment.
- Identify the approved use and conditions for each phase, not merely the campus concept.
- Screen the proposed layout against the published Phase 2 materials as a sensitivity case.
- Ask which changes to cooling, generation, substations or storage would require further approvals.
- Preserve an approval-related exit or extension mechanism where commercially achievable.

A strong utility package should not be used to close a separate gap in the land-use evidence.

## What dates belong in the investment committee’s change register?

| Date | Event or milestone | How to use it |
|---|---|---|
| **12 October 2026 — passed** | Response deadline for ERCOT’s specified State and Community Impact RFI | Check submission evidence and unresolved questions; do not assume a late response has been accepted. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)) |
| **19 October 2026** | TCEQ update due to the governor under the September directive | Request the update and implementation position; this is not an automatic permit-restart date. ([gov.texas.gov](https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits)) |
| **16 November 2026 — upcoming** | Scheduled effective date of EPA’s partial carbon-standard repeal | Recheck applicability and any intervening legal action before reliance. ([govinfo.gov](https://www.govinfo.gov/content/pkg/FR-2026-09-17/html/2026-19071.htm)) |
| **10 December 2026 — expected** | ERCOT’s stated target for its State and Community Impact report | Treat as an expected report milestone, not project clearance. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)) |
| **1 January 2027 — upcoming** | Dominion contract-date trigger for specified new-customer obligations | Confirm execution-date and customer applicability before signing. ([scc.virginia.gov](https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf)) |
| **February 2027 — anticipated** | Loudoun Phase 2 Planning Commission consideration | Monitor the schedule and draft changes; do not assume adoption. ([loudoun.gov](https://www.loudoun.gov/DataCenterStandards)) |

NERC adoption and approval, the North Carolina retail settlement and regional FERC implementation should remain **event-triggered monitoring items** until their relevant orders and implementation dates are verified.

## What should a buyer do before the next land, utility or GPU payment?

**Use a short regulatory change pack that maps directly to the commitment being requested.** The following is the desk’s recommended operating method.

### 1. Build a project-specific applicability sheet

Record the legal customer, parcel, utility territory, grid operator, connection voltage, phase dates and separately defined utility service MW and critical IT MW. Add the permit-application, agreement-execution and first-service dates where the relevant rule uses them.

### 2. Create a dated obligation register

For each material requirement, record:

- Issuing authority and docket or statutory section.
- Publication, adoption and effective dates separately.
- Status: effective, adopted but future, proposed, procedural or not established.
- The project-specific trigger and any claimed exception.
- The document proving that the exception applies.
- Responsible owner and next verification date.

### 3. Separate four types of financial exposure

| Exposure | Questions for the project team |
|---|---|
| Recurring minimum payments | What starts billing, what determines the minimum, and what happens during a slow ramp? |
| Security and collateral | Is cash required, is a guarantee acceptable, and what releases or increases the obligation? |
| Construction contributions | Which assets are funded, when are payments due, and what is refundable? |
| Withdrawal and redesign | What remains payable after cancellation, a smaller phase or a changed operating mode? |

Do not count the same utility contribution once as construction expenditure and again as a separate regulatory contingency. Keep any financing cost of collateral distinct from the collateral principal.

### 4. Link utility exposure to the tenant contract

For colocation, ask the operator to identify how changes in tariff, minimum demand, security, curtailment, generator permissions and commissioning requirements reach the tenant. Seek a responsibility matrix for redesign, delay and acceptance testing.

For capital approval, show three cases using buyer-confirmed assumptions: the agreed programme, a later activation date, and a lower or slower load ramp. Separate direct cash expenditure from deferred operating contribution; do not automatically classify all delayed revenue as permanently lost.

### 5. Set explicit stop conditions

Recommended stop conditions include an unresolved permit restriction, reliance on an unapproved tariff product, an unsupported grandfathering claim, unmodelled minimum payments, or generator specifications that do not match the permit pathway.

**The decision standard:** regulatory progress is useful only when its scope, conditions and timing support the specific commitment. An adopted process, proposed settlement or standards announcement should never be presented as proof that a particular parcel can deliver the required usable AI capacity on time.

## Sources

Primary authorities and official publications used below. URLs are provided for the underlying evidence; the inline citations identify the propositions they support.

### Texas

- Texas Governor, comprehensive data-centre audit, 3 August 2026: `https://gov.texas.gov/news/post/governor-abbott-directs-comprehensive-data-center-audit
- Texas Governor, TCEQ permitting directive, 21 September 2026: `https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits
- Texas Governor, TWDB reporting enforcement, 14 September 2026: `https://gov.texas.gov/news/post/governor-abbott-directs-twdb-to-penalize-data-center-reporting-failures
- ERCOT, State and Community Impact RFI, 14 September 2026: `https://www.ercot.com/services/comm/mkt_notices/M-B091426-01
- Texas Register, adopted §25.194, 2 October 2026: `https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html
- ERCOT, Batch Zero approval, 18 June 2026: `https://www.ercot.com/news/release/06182026-puct-approves-ercots

### Federal and regional electricity regulation

- FERC, regional large-load show-cause orders, 18 June 2026: `https://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration
- FERC, PJM co-location rehearing and compliance order, 18 June 2026: `https://www.ferc.gov/sites/default/files/2026-06/EL25-49-002_0.pdf
- FERC, SPP HILL/HILLGA concurrence, 14 January 2026: `https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-order-accepting-tariff-revisions-subject
- FERC, official discussion of the CHILLS approval in its CAISO order, 18 June 2026: `https://www.ferc.gov/sites/default/files/2026-06/EL26-71-000.pdf
- FERC, Duke transmission concurrence, 9 October 2026: `https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-duke-energy-carolinas-llc-er26-2691-000-er26-2691

### State tariffs and utility implementation

- Virginia SCC, data-centre factsheet, 24 February 2026: `https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf
- Virginia SCC, current facts page and 2026 Rider T1 explanation: `https://www.scc.virginia.gov/about-the-scc/scc-facts/
- North Carolina DOJ, large-load proposal statement, 14 October 2026: `https://ncdoj.gov/attorney-general-jeff-jackson-governor-stein-respond-to-duke-energys-proposal-for-ncs-first-large-load-tariff/
- Duke Energy, settlement announcement, 7 October 2026: `https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs
- PUCO, AEP Ohio tariff order announcement, 9 July 2025: `https://content.govdelivery.com/accounts/OHPUC/bulletins/3e8bb79
- AEP Ohio, implementation announcement, 9 July 2025: `https://www.aepohio.com/company/news/view?releaseID=10326

### Reliability, environmental requirements and technical standards

- NERC, computational-load standards final ballot, 15 October 2026: `https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption
- EPA, stationary turbine NSPS rule index: `https://www.epa.gov/stationary-sources-air-pollution/stationary-gas-and-combustion-turbines-new-source-performance
- Federal Register, partial carbon-standard repeal, 17 September 2026: `https://www.govinfo.gov/content/pkg/FR-2026-09-17/html/2026-19071.htm
- EPA, Clean Air Act resources and emergency-engine explanation: `https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers
- Virginia Code, §10.1-1322.6, 2026 update: `https://law.lis.virginia.gov/vacodeupdates/title10.1/section10.1-1322.6/
- ASHRAE, published standards and scope: `https://www.ashrae.org/technical-resources/standards-and-guidelines/titles-purposes-and-scopes
- ASHRAE, description of 90.4-2025 changes: `https://resourcecenter.ashrae.org/technical-resources/translated-publications
- ASHRAE, letter to DOE describing its standards framework: `https://www.ashrae.org/file%20library/about/government%20affairs/public%20policy%20resources/ashrae-letter-to-doe-on-data-centers.pdf

### Local planning

- Loudoun County, Phase 1 and grandfathering: `https://www.loudoun.gov/6221/Phase-1-Project-Plan-for-Data-Center-Sta
- Loudoun County, September 2026 open-house announcement: `https://www.loudoun.gov/m/NewsFlash/Home/Detail/10823
- Loudoun County, Phase 2 proposals: `https://www.loudoun.gov/6222/Phase-2-Data-Center-Standards-Locations
- Loudoun County, project schedule and overview: `https://www.loudoun.gov/DataCenterStandards

## FAQs
### Does Texas’s October 19, 2026 deadline mean data-centre permitting restarts that day?
No. The September 21 directive required TCEQ to provide a compliance update by October 19, 2026; it did not designate that date as an automatic reopening. Obtain written project-specific confirmation before relying on a revised permitting timetable. ([gov.texas.gov](https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits))
### Can a Texas data centre below 75 MW avoid the audit-related information requests?
Not necessarily: ERCOT’s September 14, 2026 RFI included certain unenergised, substantiated projects from 25 MW to below 75 MW. Applicability depends on the project’s classification and circumstances, so check the notice and the utility’s submission records. ([ercot.com](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01))
### Does FERC’s large-load reform guarantee faster data-centre interconnection?
No. The June 18, 2026 orders initiated region-specific tariff reviews and required responses; they did not guarantee a connection date or capacity allocation for an individual site. Verify the subsequent regional tariff and project-specific studies. ([ferc.gov](https://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration))
### Is SPP’s CHILLS service equivalent to firm transmission?
No. FERC describes CHILLS as as-available service subject to curtailment and interruption, with a maximum seven-year term. Buyers should evaluate the permitted interruption exposure and the requirements for obtaining long-term firm service separately. ([ferc.gov](https://www.ferc.gov/sites/default/files/2026-06/EL26-71-000.pdf))
### Has North Carolina already approved Duke’s October 2026 retail large-load settlement?
A final state approval was not established in this research; North Carolina DOJ still described it as a proposal on October 14, 2026. FERC’s separate October 9 acceptance of Duke’s transmission proposal should not be mistaken for approval of the state retail settlement. ([ncdoj.gov](https://ncdoj.gov/attorney-general-jeff-jackson-governor-stein-respond-to-duke-energys-proposal-for-ncs-first-large-load-tariff/))
### Are NERC’s computational-load standards already mandatory for every data centre?
That conclusion is not supported by the latest primary announcement reviewed. NERC’s October 15, 2026 update reported final-ballot passage and identified Board adoption and FERC approval as subsequent steps; applicability and compliance dates require the final approved documents. ([nerc.com](https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption))
### What generator requirement applies to new Virginia data-centre permit applications?
For covered applications submitted on or after July 1, 2026, Virginia Code §10.1-1322.6 requires permitted generator-set emissions no higher than Tier 4-equivalent performance. Check the application and permit scope rather than assuming an equipment purchase date establishes the applicable treatment. ([law.lis.virginia.gov](https://law.lis.virginia.gov/vacodeupdates/title10.1/section10.1-1322.6/))
### Does ASHRAE 90.4-2025 automatically become law everywhere in the United States?
No: publication of a voluntary consensus standard does not establish its adoption by a particular jurisdiction or contract. Ask the design team to identify the governing edition and adoption basis, then document any differences from the 2025 edition. ([ashrae.org](https://www.ashrae.org/file%20library/about/government%20affairs/public%20policy%20resources/ashrae-letter-to-doe-on-data-centers.pdf))
### Can emergency diesel generators be assumed to provide unrestricted bridge power?
No. EPA’s 2026 explanation addresses operation under specified DOE emergency orders, not blanket permission for routine bridge-power or economic operation. Obtain a permit-specific operating-modes assessment before including generator-backed capacity in a delivery commitment. ([epa.gov](https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers))

## Sources
- [Governor Abbott Directs TCEQ To Halt Data Center Permits | Office of the Texas Governor | Greg Abbott](https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits)
- [FERC Launches Aggressive Targeted Action to Speed Large Load Integration | Federal Energy Regulatory Commission](https://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration)
- [NERC’s Computational Loads Standards Pass Final Ballot, Advance to Board Adoption](https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption)
- [Governor Abbott Directs Comprehensive Data Center Audit | Office of the Texas Governor | Greg Abbott](https://gov.texas.gov/news/post/governor-abbott-directs-comprehensive-data-center-audit?trk=public_post_comment-text)
- [Market Notice Details](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)
- [Governor Abbott Directs TWDB To Penalize Data Center Reporting Failures | Office of the Texas Governor | Greg Abbott](https://gov.texas.gov/news/post/governor-abbott-directs-twdb-to-penalize-data-center-reporting-failures)
- [Adopted Rules Title 16](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html)
- [PUCT Approves ERCOT's Batch Zero Process for Connecting Large Electricity Users While Protecting System Reliability for Texans](https://www.ercot.com/news/release/06182026-puct-approves-ercots?trk=article-ssr-frontend-pulse_little-text-block)
- [Commissioner Rosner’s Concurrence in Duke Energy Carolinas, LLC (ER26-2691-000, ER26-2691-001) | Federal Energy Regulatory Commission](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-duke-energy-carolinas-llc-er26-2691-000-er26-2691)
- [Docket No. EL25-49-002, et al. - 2 -](https://www.ferc.gov/sites/default/files/2026-06/EL25-49-002_0.pdf)
- [Commissioner Rosner's Concurrence to Order Accepting Tariff Revisions, Subject to Condition re Southwest Power Pool, Inc. under ER26-247 | Federal Energy Regulatory Commission](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-order-accepting-tariff-revisions-subject)
- [Docket No. EL26-71-000 - 16 -](https://www.ferc.gov/sites/default/files/2026-06/EL26-71-000.pdf)
- [SCC Data Center Initiatives Facts and Figures Feb2026](https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf)
- [Virginia SCC - SCC Facts](https://www.scc.virginia.gov/about-the-scc/scc-facts/)
- [Duke Energy protects customers from data center costs | Duke Energy | News Center](https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs)
- [PUCO orders AEP Ohio to create data center specific tariff](https://content.govdelivery.com/accounts/OHPUC/bulletins/3e8bb79)
- [AEP Ohio Proposal on Data Centers to Protect Ohio Consumers Adopted by PUCO](https://www.aepohio.com/company/news/view?releaseID=10326)
- [Stationary Gas and Combustion Turbines: New Source Performance Standards (NSPS) | US EPA](https://www.epa.gov/stationary-sources-air-pollution/stationary-gas-and-combustion-turbines-new-source-performance)
- [Federal Register, Volume 91 Issue 179 (Thursday, September 17, 2026)](https://www.govinfo.gov/content/pkg/FR-2026-09-17/html/2026-19071.htm)
- [Clean Air Act Resources for Data Centers | US EPA](https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers)
- [Code of Virginia (2026 Updates)](https://law.lis.virginia.gov/vacodeupdates/title10.1/section10.1-1322.6/)
- [TPS - Titles, Purposes, and Scopes](https://www.ashrae.org/technical-resources/standards-and-guidelines/titles-purposes-and-scopes?trk=article-ssr-frontend-pulse_little-text-block)
- [Translated Publications](https://resourcecenter.ashrae.org/technical-resources/translated-publications)
- [1255 23rd Street NW, Suite 825, Washington, DC 20037 • Tel 202.833.1830 • www.ashrae.org Bill McQuade Email: bmcquade@baltimoreaircoil.com None | Email: bmcquade@baltimoreaircoil.com | --- | --- | ---](https://www.ashrae.org/file%20library/about/government%20affairs/public%20policy%20resources/ashrae-letter-to-doe-on-data-centers.pdf)
- [Phase 1: Project Plan for Data Center Standards & Locations | Loudoun County, VA - Official Website](https://www.loudoun.gov/6221/Phase-1-Project-Plan-for-Data-Center-Sta)
- [County to Host Open Houses in September on Data Center Policies and Regulations • Loudoun County, VA](https://www.loudoun.gov/m/NewsFlash/Home/Detail/10823)
- [Data Center Standards & Locations | Loudoun County, VA - Official Website](https://www.loudoun.gov/DataCenterStandards)
- [Market Notice Details](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)
- [Attorney General Jeff Jackson, Governor Stein Respond to Duke Energy’s Proposal for NC’s First Large Load Tariff - NCDOJ](https://ncdoj.gov/attorney-general-jeff-jackson-governor-stein-respond-to-duke-energys-proposal-for-ncs-first-large-load-tariff/)
- [https://gov.texas.gov/news/post/governor-abbott-directs-comprehensive-data-center-audit](https://gov.texas.gov/news/post/governor-abbott-directs-comprehensive-data-center-audit)
- [https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits](https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits)
- [https://gov.texas.gov/news/post/governor-abbott-directs-twdb-to-penalize-data-center-reporting-failures](https://gov.texas.gov/news/post/governor-abbott-directs-twdb-to-penalize-data-center-reporting-failures)
- [https://www.ercot.com/services/comm/mkt_notices/M-B091426-01](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)
- [https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html](https://www.sos.texas.gov/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html)
- [https://www.ercot.com/news/release/06182026-puct-approves-ercots](https://www.ercot.com/news/release/06182026-puct-approves-ercots)
- [https://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration](https://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration)
- [https://www.ferc.gov/sites/default/files/2026-06/EL25-49-002_0.pdf](https://www.ferc.gov/sites/default/files/2026-06/EL25-49-002_0.pdf)
- [https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-order-accepting-tariff-revisions-subject](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-order-accepting-tariff-revisions-subject)
- [https://www.ferc.gov/sites/default/files/2026-06/EL26-71-000.pdf](https://www.ferc.gov/sites/default/files/2026-06/EL26-71-000.pdf)
- [https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-duke-energy-carolinas-llc-er26-2691-000-er26-2691](https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-duke-energy-carolinas-llc-er26-2691-000-er26-2691)
- [https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf](https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf)
- [https://www.scc.virginia.gov/about-the-scc/scc-facts/](https://www.scc.virginia.gov/about-the-scc/scc-facts/)
- [https://ncdoj.gov/attorney-general-jeff-jackson-governor-stein-respond-to-duke-energys-proposal-for-ncs-first-large-load-tariff/](https://ncdoj.gov/attorney-general-jeff-jackson-governor-stein-respond-to-duke-energys-proposal-for-ncs-first-large-load-tariff/)
- [https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs](https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs)
- [https://content.govdelivery.com/accounts/OHPUC/bulletins/3e8bb79](https://content.govdelivery.com/accounts/OHPUC/bulletins/3e8bb79)
- [https://www.aepohio.com/company/news/view?releaseID=10326](https://www.aepohio.com/company/news/view?releaseID=10326)
- [https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption](https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption)
- [https://www.epa.gov/stationary-sources-air-pollution/stationary-gas-and-combustion-turbines-new-source-performance](https://www.epa.gov/stationary-sources-air-pollution/stationary-gas-and-combustion-turbines-new-source-performance)
- [https://www.govinfo.gov/content/pkg/FR-2026-09-17/html/2026-19071.htm](https://www.govinfo.gov/content/pkg/FR-2026-09-17/html/2026-19071.htm)
- [https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers](https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers)
- [https://law.lis.virginia.gov/vacodeupdates/title10.1/section10.1-1322.6/](https://law.lis.virginia.gov/vacodeupdates/title10.1/section10.1-1322.6/)
- [https://www.ashrae.org/technical-resources/standards-and-guidelines/titles-purposes-and-scopes](https://www.ashrae.org/technical-resources/standards-and-guidelines/titles-purposes-and-scopes)
- [https://resourcecenter.ashrae.org/technical-resources/translated-publications](https://resourcecenter.ashrae.org/technical-resources/translated-publications)
- [https://www.ashrae.org/file%20library/about/government%20affairs/public%20policy%20resources/ashrae-letter-to-doe-on-data-centers.pdf](https://www.ashrae.org/file%20library/about/government%20affairs/public%20policy%20resources/ashrae-letter-to-doe-on-data-centers.pdf)
- [https://www.loudoun.gov/6221/Phase-1-Project-Plan-for-Data-Center-Sta](https://www.loudoun.gov/6221/Phase-1-Project-Plan-for-Data-Center-Sta)
- [https://www.loudoun.gov/m/NewsFlash/Home/Detail/10823](https://www.loudoun.gov/m/NewsFlash/Home/Detail/10823)
- [https://www.loudoun.gov/6222/Phase-2-Data-Center-Standards-Locations](https://www.loudoun.gov/6222/Phase-2-Data-Center-Standards-Locations)
- [https://www.loudoun.gov/DataCenterStandards](https://www.loudoun.gov/DataCenterStandards)