Prepared for Load & Date Research’s doja research desk | Research cut-off: 16 October 2026 | United States
What should buyers compare first?
Compare usable critical IT capacity at an agreed acceptance date—not advertised campus megawatts, a headline electricity price or building completion. Our recommended decision sequence is: establish technical and delivery eligibility, identify remaining conditions, then compare monthly payment obligations and downside exposure.
This report is designed for independent developers evaluating 20–100 MW phased projects and AI infrastructure operators procuring 5–30 MW of high-density colocation. These are buyer requirement bands, not claims about available inventory.
The comparisons below distinguish three different decisions:
- What to procure: a development site, powered shell, fitted facility or compute service.
- How to supply power: utility service, conditional grid access, on-site generation or a combination.
- How to make the deployment usable: rack-compatible cooling, network integration, commissioning and workload acceptance.
There is no universal winner. The following recommendations are analytical judgements, not provider rankings or measured delivery-time benchmarks.
| Buyer situation | Starting comparison | What should decide it? |
|---|---|---|
| GPUs have a committed arrival date | Existing fitted colocation vs contracted GPU-cloud capacity | Evidence of workload acceptance by the required date, including integration |
| A developer controls land but has conditional power correspondence | Retain or extend the option vs acquire vs pursue an alternative | Which unresolved condition could invalidate the next payment? |
| The initial load is substantially smaller than ultimate demand | Phased capacity vs a full upfront reservation | Monthly minimum payments, expansion rights and the cost of securing later phases |
| A site has delayed grid service | Wait for grid service vs bridge generation vs another site | Complete alternative critical paths, not generator delivery alone |
| A facility is described as liquid-ready | Retrofit vs purpose-built liquid-cooled space | Compatibility with the exact hardware and a complete cooling acceptance scope |
| Workload demand remains uncertain | Shorter compute commitments vs owned hardware in leased space | Downside utilisation, exit rights and workload portability |
Scope limitation: this is public-source procurement research. It does not establish live capacity, certify engineering designs or interpret a buyer’s confidential agreements. Utility, engineering, environmental and legal confirmation remain necessary before consequential commitments.
How should utility service MW, critical IT MW and campus potential be normalised?
Require every proposal to identify its measurement boundary and delivery status. For this comparison, use the following procurement definitions rather than assuming suppliers use identical terminology.
| Capacity description | Definition to require in the tender | How to treat it |
|---|---|---|
| Advertised campus potential | Ultimate development ambition, with phases and dependencies identified | Exclude from near-term deliverable capacity until supported phase by phase |
| Utility service MW | Import capability or contracted demand at a specified point of connection | Record separately from power available to IT equipment |
| Contracted critical IT MW | Capacity reserved for computing, storage and networking equipment at an agreed electrical boundary | Identify whether it is reserved, installed, commissioned or accepted |
| Commissioned facility capacity | Capacity demonstrated under the agreed electrical and mechanical test programme | Obtain test scope, results and outstanding exceptions |
| Workload-accepted capacity | Capacity that has passed the buyer’s specified hardware, network and workload acceptance tests | Use as the commercial deployment endpoint |
Facility commissioning commonly uses load banks to test power and cooling infrastructure in place of IT equipment. Our inference: passing that test does not, by itself, demonstrate that the buyer’s complete GPU cluster and software environment are ready for customer workloads. (intelligence.uptimeinstitute.com)
Can PUE convert utility MW into usable IT MW?
Only as a clearly qualified screening calculation—not as proof of capacity. The Department of Energy defines power usage effectiveness, or PUE, as total facility energy divided by IT equipment energy. It is an energy-efficiency metric, not a certification of available electrical or cooling capacity. (energy.gov)
For example, an assumed 20 MW facility supply divided by an assumed overhead factor of 1.25 produces a 16 MW screening estimate. That arithmetic does not establish 16 MW of firm, deliverable IT capacity: the buyer still needs the electrical design, cooling capability, operating conditions and acceptance evidence.
Ask suppliers to disclose:
- The boundary at which each MW figure is measured.
- Whether capacity is dedicated, shared, interruptible or subject to another tenant’s ramp.
- Whether quoted electrical paths are redundant support for the same load or additive capacity.
- Supported simultaneous rack loads—not merely the highest density demonstrated in one rack.
- Whether the quoted PUE is measured, modelled or a contractual billing factor.
These are proposed diligence questions, not assumptions about any named facility.
Should you build, lease a powered shell, take colocation or buy GPU-cloud capacity?
Choose the scope that removes the dependencies your organisation cannot credibly complete before its deadline. Do not compare a building lease with a compute-service quote without adding the missing hardware, integration and operating responsibilities.
Public supplier descriptions illustrate the distinction. Digital Realty describes build-to-suit arrangements with custom structural, electrical, mechanical and cooling design; its disclosures also distinguish fitted facilities from powered buildings intended for customers able to build and operate their own facility. These descriptions establish procurement categories, not current site availability or suitability. (digitalrealty.com)
The table is an analyst-designed tender framework. Allocate each responsibility explicitly in the contract rather than relying on the category label.
| Approach | Scope to request | Responsibilities the buyer should expect to allocate | When it fits | What should stop commitment? |
|---|---|---|---|---|
| Owner-developed greenfield | Land, service arrangements, complete facility and operating model | Development, utility interfaces, construction, equipment, operations and IT deployment | A developer needs design control and has the delivery organisation and funding to execute | Unresolved power, permits or equipment dependencies incompatible with the required date |
| Powered land or powered shell | Precisely defined land/building and electrical handover boundary | Remaining mechanical and electrical fit-out, cooling, controls, commissioning and operations | A buyer can deliver the fit-out and values control over the technical design | A seller’s power claim is unsupported, or the remaining scope has no integrated programme |
| Existing facility retrofit | Existing asset plus a priced, engineered conversion scope | Structural checks, distribution changes, cooling conversion and interference with existing operations | An existing location has useful infrastructure and an acceptable conversion path | The retrofit relies on unverified spare cooling, power or structural capacity |
| Existing fitted colocation | Dedicated critical IT capacity, operating services and a defined integration scope | Hardware, network and software deployment; cooling interfaces as negotiated | The hardware deadline is the primary constraint | Facility acceptance does not cover the actual rack configuration or deployment footprint |
| Build-to-suit or new-build wholesale lease | Custom facility delivery with milestones, acceptance tests and operating scope | Buyer design decisions, IT deployment and management of contractual interfaces | Custom density or resilience is important and the buyer can wait for delivery | Rent commencement and remedies do not address the buyer’s material delivery dependencies |
| GPU cloud or dedicated managed cluster | Specified accelerators, topology, storage, networking, software and capacity rights | Workload migration, security, performance validation and commitment management | The buyer wants compute rather than ownership of the infrastructure stack | The offer provides a price but no adequate capacity, topology or performance commitment |
Does cloud eliminate capacity-commitment risk?
No: examine the reservation product, not just the hourly price. AWS documents that EC2 Capacity Blocks are purchased for a reserved period and charged upfront, with pricing fixed after purchase. Separately, EC2 Capacity Reservations are billed whether the reserved instances are used or not. These are examples of distinct commercial structures—not a description of every cloud provider. (docs.aws.amazon.com)
For colocation vs GPU cloud, request a workload-equivalent comparison:
- Same accelerator model, memory and usable cluster topology.
- Same workload, precision, dataset and performance target.
- Same storage, networking, support and security scope.
- Same availability window and treatment of interruptions.
- Same utilisation scenarios and measurement period.
- Explicit hardware financing, maintenance and residual-value assumptions for ownership options.
Our recommendation is to compare cost per accepted workload outcome alongside infrastructure cost. A universal GPU-utilisation break-even percentage is not established by the evidence reviewed.
Which power approach fits: grid service, flexible access or behind-the-meter generation?
Compare the complete power-service architecture and its failure conditions. On-site generation and storage can reduce grid dependence, but the Department of Energy describes them as a range of technologies and configurations—not a single substitute for utility service. (energy.gov)
The following is a procurement comparison, not a claim that every arrangement is available in every territory.
| Approach | What to establish | Suggested fit | Main comparison questions |
|---|---|---|---|
| Utility service without a negotiated curtailment arrangement | Contracted service, required works, energisation conditions and applicable tariff | Loads whose operating model requires continuous access to the contracted supply, subject to normal service conditions | What remains before service? What is the date commitment? What are the minimum payments and outage provisions? |
| Conditional or flexible grid access | The precise circumstances in which consumption can be restricted | Workloads that can demonstrably tolerate the specified restrictions | Who calls curtailment? How much notice? What duration and frequency assumptions are acceptable? What happens after non-performance? |
| Grid-parallel behind-the-meter generation | Import limits, generation controls, protection, fuel and treatment of generator outages | A buyer with a documented reason to reduce imports or supplement service | Can the site import replacement power after a generator trip? What standby, demand or other charges remain? |
| Islanded on-site generation | A complete independent supply and operating architecture | A project with credible fuel, permitting, equipment and resilience plans | What supports maintenance and failures? What net output is available under site conditions? What changes if grid connection is added later? |
| Load co-located with an existing generator | Rights to supply, the electrical configuration and applicable grid-service arrangements | A buyer able to diligence generation and load as one project | What happens when the generator is unavailable? What transmission and ancillary services are required? |
| Temporary bridge power followed by grid service | Two complete operating configurations and an executable transition plan | A time-bounded deployment where the bridge and transition are both supported | Who pays if grid service arrives late? How are fuel, rental extensions, testing and demobilisation treated? |
Federal arrangements are evolving. On 18 June 2026, FERC issued tailored show-cause orders directing the six regional grid operators under its jurisdiction to justify or reform large-load tariff provisions. An order initiating or directing tariff reform is not evidence that a particular site has permission or capacity to connect. (ferc.gov)
Is behind-the-meter gas generation faster than a grid connection?
That cannot be answered from the technology label. Our recommended comparison is between two dependency schedules: the grid route and the complete generation route, including fuel delivery, permits, equipment, controls, installation, testing and operations.
For each generation proposal, request a schedule and cost pack covering:
- Net power delivered to the facility boundary, after auxiliary consumption and agreed operating allowances.
- Fuel availability, transport rights, pressure requirements and interruption provisions.
- Permitted operating mode and hours, emissions controls and monitoring obligations.
- Equipment allocation, installation scope and acceptance tests.
- Maintenance coverage, spares and the consequences of the largest relevant equipment outage.
- Grid-parallel protection and operating permissions, where applicable.
- Transition and exit costs if the arrangement is described as temporary.
Do not substitute an emergency-generator permission for a prime-power assessment. EPA’s current data-centre resources distinguish emergency-engine operation, specified non-emergency operation and operation under particular emergency orders. Those distinctions require configuration-specific review. (epa.gov)
A useful recent example of regulatory scope is EPA’s 16 July 2026 memorandum on islanded generators. It states that the Acid Rain Program does not apply to generation facilities unconnected to the wider grid, while expressly declining to determine applicability of other Clean Air Act requirements; later grid connection can change the analysis. That is not a blanket air-permitting exemption. (epa.gov)
Can a battery replace missing long-duration power supply?
Treat storage as a separately specified resource. DOE describes battery storage as storing electricity for later use, including demand reduction, time shifting and transitions between operating states. Our procurement inference: a battery proposal must identify both available energy and a credible charging source; a MW rating alone is insufficient for evaluating a prolonged supply gap. (betterbuildingssolutioncenter.energy.gov)
Is a data center PPA an alternative to a utility tariff?
Often they address different parts of the arrangement. EPA distinguishes physical PPAs, which involve delivery of electricity, from financial or virtual PPAs, under which the buyer does not take delivery of the project’s electricity. A virtual PPA therefore does not establish physical service to the buyer’s site. (epa.gov)
| Arrangement | Question it primarily answers | What to verify separately |
|---|---|---|
| Utility connection and service arrangement | How can the site receive electricity, under what conditions? | Works, service dates, capacity, tariff and operating restrictions |
| Retail supply arrangement | Who supplies or settles the site’s electricity purchases? | Physical service, applicable delivery charges and market eligibility |
| Physical PPA | What project electricity is purchased and delivered under the contract? | Delivery arrangements, site connection, residual supply and applicable charges |
| Financial or virtual PPA | How are financial settlements and associated environmental attributes structured? | Physical site supply, settlement exposure, credit and accounting treatment |
The table is a functional comparison, not a jurisdiction-independent statement of customer rights. EPA notes that non-utility physical PPAs generally depend on competitive-market arrangements. Obtain territory-specific advice before treating procurement structures as interchangeable. (epa.gov)
How do AEP Ohio and Dominion’s large-load obligations compare?
Compare payment commitments and ramp exposure before comparing energy prices. The two examples below are not substitutes available to the same parcel, and they do not establish which territory is cheaper.
The distinction matters because large-load tariff design explicitly addresses underused infrastructure and stranded-investment risk. DOE and Lawrence Berkeley National Laboratory identify these issues as central to emerging large-load rate structures. (energy.gov)
| Criterion | AEP Ohio / Ohio Power DCT | Dominion Energy Virginia GS-5 and related provisions |
|---|---|---|
| Status and date | DCT became effective 23 July 2025. (aepohio.com) | Approved in the SCC’s 25 November 2025 ruling; GS-5 takes effect 1 January 2027, after this report’s cut-off. (scc.virginia.gov) |
| Applicability screen | New data-centre loads above 25 MW, subject to expansion and affiliated-load aggregation rules. (aepohio.com) | The SCC announcement identifies customers demanding 25 MW or more. Confirm full classification, load-factor and transition criteria from the applicable tariff. (scc.virginia.gov) |
| Contract duration | Ramp period of up to four years, followed by eight years. (aepohio.com) | At least 14 years for new large-load customers contracting for service on or after 1 January 2027. (scc.virginia.gov) |
| Minimum-payment mechanism | Graduated contract-capacity minimum demand plus a historical-demand ratchet; do not reduce it to a flat percentage of energy use. (aepohio.com) | SCC identifies minimums of 85% of contracted transmission and distribution demand and 60% of generation demand for applicable customers. (scc.virginia.gov) |
| Credit support | Where the specified exemption tests are not met, guarantee or collateral equal to 50% of minimum charges for the full term. (aepohio.com) | Customers without sufficient credit may need guarantees covering up to 60% of minimum charges; the SCC identifies applicability to new customers contracting from 1 January 2027. (scc.virginia.gov) |
| Delivery-date evidence | AEP describes its ESA energisation date as a good-faith estimate. (aepohio.com) | Obtain the project’s service agreement and works schedule; the cited rate-class announcement does not establish a site delivery date. |
Why is the AEP Ohio minimum-demand formula worth checking carefully?
AEP’s published framework includes a contract-capacity floor of 15 MW plus 85% of capacity above 25 MW for the relevant 25–75 MW band. It also includes an 85% historical billing-demand ratchet. (aepohio.com)
Illustrative calculation—not a customer bill: for a fully ramped, standalone 50 MW contract, the contract-capacity component is:
15 MW + 0.85 × (50 − 25) MW = 36.25 MW
It is not simply 50 MW × 85% = 42.5 MW. Actual-demand provisions, the historical ratchet, aggregation and other applicable terms must still be evaluated. The tariff book’s graduated structure is the basis for this calculation. (aepohio.com)
The buyer lesson: minimum billing demand is not the same as a commitment to purchase that percentage of energy in MWh. Ask the utility or energy adviser to reproduce the monthly bill, including each relevant charge, rather than applying a headline percentage to total electricity consumption.
What should Texas buyers revalidate before relying on a power date?
Distinguish the project’s study status, verification status and permission to energise. ERCOT’s 20 August 2026 presentation reported paused energisation approvals for data centres and cryptocurrency facilities of at least 75 MW, while stating that 25–<75 MW medium loads were outside that particular pause. It also explicitly said inclusion in a Quarterly Stability Assessment did not itself authorise energisation. (ercot.com)
ERCOT’s 14 September 2026 notice subsequently required community-impact information from specified unenergised projects, including qualifying 25–<75 MW data centres. The submission deadline was 12 October 2026, which had passed by this report’s cut-off. Submission or expiry of that deadline is not evidence of project approval. (ercot.com)
This review does not establish whether a particular project’s restrictions have been resolved. Require a fresh, project-specific confirmation from the relevant utility and ERCOT process participants before releasing capital against a Texas energisation assumption.
How should the true cost of power and colocation be compared?
Build a monthly cash-obligation model, not a single blended cents-per-kWh ranking. Large-load rate design can include minimum-payment, credit-support and infrastructure-cost protections; these deserve separate treatment in the buyer’s model. (eta-publications.lbl.gov)
The following is the desk’s recommended model structure. A line belongs in the comparison only when the applicable proposal, tariff or agreement supports it.
| Cost or obligation | Model treatment | Clarification to request |
|---|---|---|
| Capacity rent | Reserved critical IT kW × applicable monthly charge | Billing commencement, phased reservations, escalators and unused-capacity treatment |
| Metered electricity | Interval or monthly energy under the applicable charging formula | Meter boundary, losses, billing PUE and pass-through mark-ups |
| Demand charges and minimums | Apply each tariff component’s own demand and ratchet rules | Measurement interval, historical lookback and contract-capacity treatment |
| Riders, taxes and credits | Separate, dated line items | Applicable classes, adjustment mechanisms and reconciliation |
| Utility contributions and connection works | One-off cash-flow schedule | Refundability, cancellation exposure and ownership of funded assets |
| Deposits and collateral | Separate liquidity schedule | Cash versus guarantee, release conditions and financing cost |
| Cooling and electrical integration | Priced project scope, with contingency shown explicitly | Boundary between landlord, tenant, OEM and integrator |
| Network and operating services | Recurring and one-off charges | Cross-connects, remote hands, monitoring and support |
| Exit, relocation and restoration | Scenario-dependent cash flows | Early termination, equipment removal and reinstatement requirements |
Do not assume every minimum bill is an additional charge. Where a minimum is already embedded in a demand-charge calculation, adding it again would double-count the obligation. The model should reproduce the agreement’s mechanics, not impose a generic formula.
What assumptions must remain separate?
Use separate inputs for:
- Reserved capacity: what the buyer must pay to hold.
- Installed IT capacity: what has physically been deployed.
- Average IT electrical load: what the equipment consumes over the period.
- Metered peak demand: what the tariff’s measurement method records.
- Compute utilisation: how much useful workload the hardware performs.
Do not derive metered peak demand from average energy consumption. Likewise, do not treat GPU utilisation as a direct substitute for measured IT electrical load. These are modelling controls: obtain the buyer’s actual load assumptions and equipment profiles.
For an energy scenario, a period-appropriate PUE assumption can relate IT energy to facility energy. Because DOE defines PUE using energy quantities, an annual value should not silently become a guaranteed monthly billing factor. (energy.gov)
Can a higher $/kW/month offer cost less during ramp-up?
Yes, under the following explicitly hypothetical assumptions. This example is original arithmetic, not a supplier quote, tariff estimate or market benchmark.
Assume both offers meet the same technical and acceptance requirements, with identical integration costs and electricity treatment. Offer B’s expansion is contractually secured—not merely subject to future availability.
| Assumption or result | Offer A: lower unit price | Offer B: phased reservation |
|---|---|---|
| Capacity price | $170/kW/month | $185/kW/month |
| Reserved capacity, months 1–6 | 10 MW | 5 MW |
| Reserved capacity, months 7–12 | 10 MW | 10 MW |
| Average IT electrical load, months 1–6 | 2.5 MW | 2.5 MW |
| Average IT electrical load, months 7–12 | 7.5 MW | 7.5 MW |
| Annual capacity rent | $20.40m | $16.65m |
| Assumed energy component | $4.38m | $4.38m |
| Rent-plus-energy subtotal | $24.78m | $21.03m |
The energy illustration assumes two equal 4,380-hour periods, a constant PUE of 1.25 and an energy-only rate of $80/MWh:
(2.5 + 7.5) MW × 4,380 hours × 1.25 × $80/MWh = $4.38m
Offer B’s subtotal is $3.75m lower despite its higher unit rent. Before differences in other charges, its rent-only break-even price is approximately $226.67/kW/month: $20.40m ÷ 90,000 reserved kW-months.
This is deliberately not a full bill. It excludes demand charges, taxes, deposits, integration differences, financing and exit costs. Any of those could change the ranking. The example demonstrates the value of modelling reservation timing—not a guaranteed saving.
Which cooling approach fits high-density AI colocation?
Start with the hardware’s requirements and the complete heat-removal path. Do not select a cooling category from an advertised rack-density ceiling alone.
NVIDIA’s DGX GB200 SuperPOD reference architecture explicitly describes both direct liquid cooling and air cooling. This is a useful warning against assuming that every liquid-cooled deployment eliminates the need for room air cooling; the exact requirement remains hardware-specific. (docs.nvidia.com)
| Cooling approach | Technical distinction | Suggested procurement fit | Evidence to request |
|---|---|---|---|
| Room or row air cooling | Heat is removed through the IT equipment’s air path | Hardware expressly supported by the proposed air environment | Rack-by-rack thermal assessment, airflow and failure-condition tests |
| Rear-door heat exchanger | A traditional arrangement transfers rack exhaust heat to facility coolant | Retaining suitable air-cooled equipment while adding liquid heat removal | Door/rack compatibility, coolant conditions, airflow effects and room heat balance. (opencompute.org) |
| Direct-to-chip with a facility liquid interface | Cold plates, manifolds, connections and CDUs form a technology cooling system | Hardware designed for direct liquid cooling, with compatible facility infrastructure | The complete interface specification—not merely a CDU nameplate. (opencompute.org) |
| Direct-to-chip with air-assisted heat rejection | Heat from the liquid loop is ultimately discharged to facility air in the described arrangement | A retrofit candidate where the existing air plant can support the verified heat load | Total room heat rejection and available air-system capacity. (opencompute.org) |
| Immersion cooling | Equipment and materials must be compatible with the chosen dielectric-fluid environment | A deliberately selected hardware and operating ecosystem | Material compatibility, service procedures, support and warranty confirmation. (opencompute.org) |
The fit assessments are analyst recommendations. The sources do not establish universal cost, density or deployment-speed rankings across these approaches.
What should a liquid-ready evidence audit contain?
Request a jointly completed compatibility schedule covering:
- Hardware identity: OEM, system configuration and specification revision.
- Electrical envelope: normal operation, relevant transients and agreed rack limits.
- Liquid interface: supply temperature, flow, pressure, fluid chemistry and connector requirements.
- Residual air cooling: the load not captured by the liquid system.
- Heat rejection: performance under the site’s design conditions and any relevant water constraints.
- Failure behaviour: CDU, pump, valve, controls and leak-response scenarios.
- Cleaning and commissioning: flushing, filtration, fluid sampling and acceptance responsibilities.
- Operating ownership: who maintains each side of the interface and resolves alarms.
OCP’s cold-plate work spans the system from cold plates to CDUs, including tubing, manifolds and quick disconnects. Uptime Institute’s commissioning analysis also identifies integration of CDUs into the wider fluid network as a distinct challenge. Our recommendation: make the boundary between facility and IT cooling a signed responsibility schedule. (opencompute.org)
A relevant operational cross-check is Align Communications’ published liquid-cooling project role, which includes design coordination, installation, testing, commissioning and turnover. That supports the importance of assigning the complete integration scope; it does not demonstrate capacity or readiness at any particular facility. (job-boards.greenhouse.io)
Which delivery date should the contract use?
Record multiple milestones and connect payment commencement to the scope actually being purchased. Energisation, access, facility acceptance and compute acceptance should not be collapsed into one ambiguous ready date.
Uptime Institute describes integrated systems testing as testing power and cooling under operating conditions using load banks. This provides a foundation for facility acceptance, while the buyer should separately specify its IT and workload acceptance requirements. (journal.uptimeinstitute.com)
The table below is a proposed negotiation and programme-control framework, not a statement that suppliers must accept these terms.
| Milestone | Evidence to request | Commercial issue to resolve |
|---|---|---|
| Land and access rights | Executed rights and relevant conditions | What payments become irreversible before technical feasibility is established? |
| Utility energisation | Project-specific service confirmation and completed dependencies | Does the electricity contract begin before tenant deployment is usable? |
| Facility access | Access scope, logistics and safety restrictions | Can hardware be delivered and installed, or only stored? |
| Electrical and cooling acceptance | Agreed tests, results and exceptions | What level of capacity can be accepted and billed? |
| Network readiness | Delivered circuits, physical routes and acceptance results | Which party bears a connectivity delay? |
| Rack and cluster integration | OEM and integrator sign-offs | Who owns cooling, cabling, firmware and configuration defects? |
| Workload acceptance | Buyer-defined performance and operational tests | When can customer commitments credibly begin? |
How should time to compute be calculated?
Build a dependency schedule using actual task owners, durations and predecessor relationships. For each task:
Earliest finish = latest finish of required predecessors + task duration
This is a scheduling method, not a forecast of any project. Parallel tasks should not be added sequentially, and missing durations should remain unresolved rather than being replaced with a universal installation allowance.
Compare at least three buyer-selected cases:
- The documented base programme.
- Delay to the most consequential external dependency.
- A slower hardware or customer ramp after facility acceptance.
How should delay exposure be shown without exaggeration?
Separate four categories in the investment committee model:
| Category | Treatment |
|---|---|
| Payments already included in the base case | Identify how much is paid before useful deployment; do not automatically add it again as incremental loss |
| Incremental cash costs | Include only additional storage, extension, remobilisation, financing or other supported costs |
| Contractual customer exposure | Use actual remedies, caps, exclusions and mitigation assumptions |
| Deferred contribution | Model timing and recoverability; do not automatically classify all delayed revenue as permanently lost |
In the hypothetical Offer A above, three months of rent equals $5.10m. If rent begins before compute acceptance, that is $5.10m paid during the pre-acceptance period. It is not necessarily an additional $5.10m loss on top of the already modelled lease payments.
How should buyers compare provider types and advisers?
Assign each evidence question to the party capable of answering it, then reconcile the answers. The following is a proposed responsibility map—not a ranking of named suppliers or a claim that every organisation offers the same scope.
| Provider type | Evidence or service to seek | What not to infer from it |
|---|---|---|
| Utility or relevant network provider | Service studies, connection conditions, works and tariff applicability | That a preliminary discussion establishes a binding delivery date |
| Energy supplier or PPA counterparty | Supply terms, settlement structure, credit and environmental attributes | That an energy contract alone establishes site connection rights |
| Data-centre landlord or operator | Allocated critical IT capacity, integration boundaries, operating services and acceptance terms | That campus potential equals capacity reserved for this buyer |
| Electrical, cooling or IT OEM | Configuration-specific requirements, performance evidence and support terms | That component capability proves whole-facility readiness |
| Engineering, EPC or commissioning firm | Scoped technical assessments, programme dependencies and test evidence | That work outside the engagement scope has also been verified |
| Broker or property adviser | Alternatives, transaction support and commercial negotiation | That a listing constitutes technical or utility confirmation |
| Independent buyer-side research team | Evidence reconciliation, comparable alternatives and change tracking | Engineering certification, legal interpretation or authority to promise power |
The distinctions are consistent with the separate service, supply, build-to-suit and technical scopes documented in the primary sources. Their practical purpose is to prevent evidence from one layer being treated as proof of another. (aepohio.com)
For every adviser, request scope boundaries, reliance rights, relevant insurance and disclosure of referral or transaction remuneration. Those are recommended selection criteria, not findings about a particular firm.
What should the final commitment gatecard contain?
Use separate gates; do not average away a blocker. This is the desk’s recommended decision tool.
| Gate | Minimum question | Example of evidence to request |
|---|---|---|
| 1. Land control | Can the buyer legally access and develop the required site? | Executed rights, conditions and expiry dates |
| 2. Planning and permits | Are the permissions necessary for the selected configuration established? | Jurisdiction-specific permit register and status evidence |
| 3. Utility arrangements | What service has actually been agreed? | Executed arrangements, capacity definition, conditions and applicable tariff |
| 4. Network works | Which external works remain on the delivery path? | Scope, responsible party, programme and dependencies |
| 5. Equipment and facility systems | Can the intended racks operate in the proposed design? | Electrical, cooling, structural and connectivity compatibility evidence |
| 6. Commissioning and acceptance | What must pass before the buyer regards capacity as usable? | Approved test programme, responsibility matrix and acceptance criteria |
Classify each material claim as:
- Document-supported: the document supports the specific claim within its stated scope.
- Conditional: it depends on an identified event or obligation.
- Conflicting: material evidence disagrees.
- Not established: sufficient evidence was not obtained.
Not established does not mean unavailable. It means the comparison cannot yet rely on the claim.
What should go into the final comparison sheet?
For each option, record:
- Required and offered critical IT MW, by phase.
- Rack configuration and cooling requirements.
- Acceptance date and evidence supporting it.
- Remaining dependencies, owners and latest required completion dates.
- Monthly recurring costs, upfront expenditure and separate collateral requirements.
- Base, delayed and slow-ramp scenarios.
- Cancellation, expansion, assignment and transition rights requiring legal review.
- Source dates, document versions, assessment dates and next revalidation triggers.
Recommended decision rule: first exclude—or explicitly escalate—options that cannot substantiate the essential technical and delivery requirements. Rank the remaining options by supported economics, contractual flexibility and downside exposure. A low price should not compensate for a missing prerequisite unless the decision-maker knowingly accepts and funds that risk.
What remains unknown from public evidence?
This review does not establish a live shortlist of 10 MW in Dallas, 20 MW in Northern Virginia or any other specific inventory requirement. Nor does it establish a national electricity-price league table, a universal cost of delay or a guaranteed delivery advantage for on-site generation.
The public evidence is sufficient to build a materially better comparison process. To choose an actual site or provider, the next step is to obtain dated, project-specific proposals and reconcile them against the buyer’s hardware, load ramp, acceptance requirements and next irreversible payment.
Research method
Primary sources were prioritised for regulatory, tariff and technical statements. Discovery searches also covered industry broadcasting, hiring pages, OCP’s video-session index and podcast descriptions; those materials were used to identify diligence themes, not to infer live inventory or undocumented performance. No claim here depends on an unreviewed audio or video transcript. (datacenterdynamics.com)
Sources
Sources were accessed for this review on 16 October 2026. Living pages and tariff summaries should be refreshed before commitment. URLs are provided below for the evidence register.
Power, tariffs and regulation
- AEP Ohio — Data Center Tariff: service process, effective date, term, minimum-demand and collateral summary. `https://www.aepohio.com/company/about/rates/data-center-tariff/
- Ohio Power tariff book — Schedule DCT: graduated minimum-demand and aggregation language; indexed extract reviewed, not a complete independently rebuilt bill. `https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/AEP_Ohio_Tariff_Bookv1.pdf
- Virginia SCC — 25 November 2025 ruling announcement: GS-5 effective date and demand minimums. `https://www.scc.virginia.gov/about-the-scc/newsreleases/release/scc-issues-order-on-dev-biennial-review-2025/scc-rules-in-dev-biennial-review-case.html
- Virginia SCC — Data Center Initiatives, posted 24 February 2026: contract duration, collateral and applicability qualifications. `https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf
- DOE — Electricity Rate Designs for Large Loads, 17 January 2025. `https://www.energy.gov/policy/articles/electricity-rate-designs-large-loads-evolving-practices-and-opportunities
- Lawrence Berkeley National Laboratory — Large-load rate-design technical brief, January 2025. `https://eta-publications.lbl.gov/sites/default/files/2025-01/electricity_rate_designs_for_large_loads_evolving_practices_and_opportunities_final.pdf
- FERC — Large-load integration show-cause orders, 18 June 2026. `https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration
- ERCOT — Batch Zero verification and audit presentation, 20 August 2026. `https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf
- ERCOT — Community-impact RFI market notice, 14 September 2026. `https://www.ercot.com/services/comm/mkt_notices/M-B091426-01
- EPA — Physical PPAs. `https://www.epa.gov/green-power-markets/physical-ppa
- EPA — Customer Power Purchase Agreements. `https://www.epa.gov/statelocalenergy/customer-power-purchase-agreements
- DOE — Onsite Energy Program. `https://www.energy.gov/cmei/ito/onsite-energy-program
- DOE — Onsite Energy Technologies. `https://betterbuildingssolutioncenter.energy.gov/onsite-energy/technologies
- EPA — Clean Air Act Resources for Data Centers. `https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers
- EPA — Islanded generators and Acid Rain Program memorandum, 16 July 2026. `https://www.epa.gov/system/files/documents/2026-07/epa-issues-clarification-on-islanded-power-generators-and-acid-rain-program-provisions.pdf
Facilities, compute and cooling
- DOE — Best Practices Guide for Energy-Efficient Data Center Design, July 2024: PUE definition and measurement scope. `https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf
- Digital Realty — Build-to-Suit: supplier-described design scope, not verified availability. `https://www.digitalrealty.com/platform-digital/colocation/build-to-suit
- Digital Realty — Annual-report disclosure: historical description of fitted and powered-building product categories. `https://investor.digitalrealty.com/static-files/1ed6d476-e916-4426-8bb1-e9d6a0e33404
- AWS — EC2 Capacity Blocks pricing and billing. `https://docs.aws.amazon.com/us_en/AWSEC2/latest/UserGuide/capacity-blocks-pricing-billing.html
- AWS — EC2 Capacity Reservation pricing and billing. `https://docs.aws.amazon.com/AWSEC2/latest/UserGuide/capacity-reservations-pricing-billing.html
- NVIDIA — DGX GB200 SuperPOD architecture: hybrid liquid and air cooling. `https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html
- Open Compute Project — Door heat-exchanger white paper. `https://www.opencompute.org/documents/acs-door-hx-whitepaper-final-230419-pdf
- Open Compute Project — Cold Plate Sub-Project. `https://www.opencompute.org/projects/cooling-environments/cold-plate/
- Open Compute Project — Design Guidelines for Immersion-Cooled IT Equipment. `https://www.opencompute.org/documents/design-guidelines-for-immersion-cooled-it-equipment-revision-1-01-pdf
- Uptime Institute — Liquid-cooled load simulation for DLC commissioning: public article extract. `https://intelligence.uptimeinstitute.com/index.php/resource/liquid-cooled-load-simulation-dlc-commissioning
- Uptime Institute — Coolant distribution units can complicate commissioning: public article extract. `https://intelligence.uptimeinstitute.com/index.php/resource/coolant-distribution-units-can-complicate-commissioning
- Uptime Institute — Lessons Learned from Tier Certification of Constructed Facilities. `https://journal.uptimeinstitute.com/tiercertificationpreparation/
Discovery and operational cross-checks
- Align Communications — Liquid-cooling project-manager role: evidence of described integration responsibilities only. `https://job-boards.greenhouse.io/align46/jobs/5233408007
- Open Compute Project — 2025 Global Summit session and video index. `https://www.opencompute.org/events/ocp-summit/2025-ocp-global-summit/
- DCD — Accelerating data center time to power: broadcast description. `https://www.datacenterdynamics.com/en/dcd-broadcasts/data-center-power-design-2026/accelerating-data-center-time-to-power/
- The Strategic Podcast — Powering the Data Center, 3 September 2026: episode description. `https://podcasts.apple.com/us/podcast/powering-the-data-center/id6787825340?i=1000787697920
FAQs
Should an AI infrastructure operator build a data centre, lease colocation or buy GPU-cloud capacity?
Compare the complete scope and the buyer’s ability to deliver it before the required acceptance date. Build-to-suit can provide a custom facility, while cloud reservations purchase defined compute-capacity rights; neither category alone establishes a superior cost or timetable. (digitalrealty.com)
What does a utility will-serve letter guarantee?
The label alone does not establish its legal effect: review the actual wording, conditions, capacity definition and date provisions with the utility and counsel. Even AEP Ohio’s published description of its electric service agreement characterises energisation as a good-faith estimate, illustrating why buyers must examine the specific document rather than its title. (aepohio.com)
What is the difference between utility service MW and critical IT MW?
For procurement, record utility service at the connection boundary separately from capacity allocated to IT equipment. DOE’s PUE definition distinguishes total facility energy from IT energy, but that ratio does not certify how much IT capacity a particular electrical and cooling design can deliver. (energy.gov)
Does a data centre PPA prove that power is available at the site?
No: a virtual PPA does not deliver the project’s electricity to the buyer, while a physical PPA has a different delivery structure. Establish the site’s connection and service conditions separately from the energy-purchase arrangement. (epa.gov)
Does AEP Ohio require every data centre to buy 85% of its contracted energy?
That is an inaccurate simplification of the published DCT structure. The relevant provisions concern minimum billing demand, including graduated contract-capacity treatment and a historical-demand ratchet, rather than a universal requirement to purchase 85% of energy in MWh. (aepohio.com)
Is behind-the-meter generation automatically faster or exempt from air permitting?
Neither conclusion follows from the label; compare the complete generation and grid delivery schedules. EPA’s July 2026 islanded-generation memorandum addresses Acid Rain Program applicability and expressly does not determine applicability of other Clean Air Act requirements. (epa.gov)
What should liquid-ready colocation mean for an AI deployment?
Require written compatibility with the exact rack configuration, including liquid conditions, residual air cooling, heat rejection and commissioning responsibilities. NVIDIA’s DGX GB200 reference architecture uses both liquid and air cooling, so a generic liquid-ready claim is not sufficient evidence of compatibility. (docs.nvidia.com)
Which date matters most when comparing AI colocation offers?
Our recommended endpoint is buyer-defined workload acceptance, supported by separate energisation, facility-testing, network and integration milestones. Facility integrated systems testing evaluates power and cooling, so the buyer should specify additional acceptance tests for its deployed cluster. (journal.uptimeinstitute.com)
Can a higher colocation price per kW be cheaper overall?
Yes, depending on reservation timing and the rest of the contract. In the report’s hypothetical example, a $185/kW/month phased reservation produces lower first-year rent than a $170/kW/month full reservation; this is scenario arithmetic, not a market quote or guaranteed saving.
Sources
- Liquid-cooled load simulation for DLC commissioning | Uptime Intelligence
- Best Practices Guide for Energy-Efficient Data Center Design
- Built in Data Center Solution | Digital Realty
- Capacity Blocks pricing and billing - Amazon Elastic Compute Cloud
- Onsite Energy Program | Department of Energy
- FERC Launches Aggressive Targeted Action to Speed Large Load Integration | Federal Energy Regulatory Commission
- Clean Air Act Resources for Data Centers | US EPA
- EPA issues clarification on Islanded Power Generators and Acid Rain Program Provisions
- Onsite Energy Technologies | Better Buildings & Better Plants Initiative
- Physical PPA | US EPA
- Electricity Rate Designs for Large Loads: Evolving Practices and Opportunities | Department of Energy
- Data Center Tariff
- Virginia SCC - SCC Issues Order on DEV Biennial Review 2025
- OHIO POWER COMPANY Original Sheet No. 223-4
- SCC Data Center Initiatives Facts and Figures Feb2026
- https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf
- Market Notice Details
- https://eta-publications.lbl.gov/sites/default/files/2025-01/electricity_rate_designs_for_large_loads_evolving_practices_and_opportunities_final.pdf
- DGX SuperPOD Architecture — NVIDIA DGX SuperPOD: Next Generation Scalable Infrastructure for AI Leadership Reference Architecture Featuring NVDIA DGX GB200
- https://www.opencompute.org/documents/acs-door-hx-whitepaper-final-230419-pdf
- Cold Plate - Open Compute Project
- https://www.opencompute.org/documents/design-guidelines-for-immersion-cooled-it-equipment-revision-1-01-pdf
- Job Application for Field Project Manager - Data Center Liquid Cooling at Align Communications
- Lessons Learned from Tier Certification of Constructed Facilities
- Accelerating data center time to power - DCD
- Customer Power Purchase Agreements | US EPA
- https://www.aepohio.com/company/about/rates/data-center-tariff/
- https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/AEP_Ohio_Tariff_Bookv1.pdf
- https://www.scc.virginia.gov/about-the-scc/newsreleases/release/scc-issues-order-on-dev-biennial-review-2025/scc-rules-in-dev-biennial-review-case.html
- https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf
- https://www.energy.gov/policy/articles/electricity-rate-designs-large-loads-evolving-practices-and-opportunities
- https://eta-publications.lbl.gov/sites/default/files/2025-01/electricity_rate_designs_for_large_loads_evolving_practices_and_opportunities_final.pdf
- https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration
- https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf
- https://www.ercot.com/services/comm/mkt_notices/M-B091426-01
- https://www.epa.gov/green-power-markets/physical-ppa
- https://www.epa.gov/statelocalenergy/customer-power-purchase-agreements
- https://www.energy.gov/cmei/ito/onsite-energy-program
- https://betterbuildingssolutioncenter.energy.gov/onsite-energy/technologies
- https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers
- https://www.epa.gov/system/files/documents/2026-07/epa-issues-clarification-on-islanded-power-generators-and-acid-rain-program-provisions.pdf
- https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf
- https://www.digitalrealty.com/platform-digital/colocation/build-to-suit
- https://investor.digitalrealty.com/static-files/1ed6d476-e916-4426-8bb1-e9d6a0e33404
- https://docs.aws.amazon.com/us_en/AWSEC2/latest/UserGuide/capacity-blocks-pricing-billing.html
- https://docs.aws.amazon.com/AWSEC2/latest/UserGuide/capacity-reservations-pricing-billing.html
- https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html
- https://www.opencompute.org/documents/acs-door-hx-whitepaper-final-230419-pdf
- https://www.opencompute.org/projects/cooling-environments/cold-plate/
- https://www.opencompute.org/documents/design-guidelines-for-immersion-cooled-it-equipment-revision-1-01-pdf
- https://intelligence.uptimeinstitute.com/index.php/resource/liquid-cooled-load-simulation-dlc-commissioning
- https://intelligence.uptimeinstitute.com/index.php/resource/coolant-distribution-units-can-complicate-commissioning
- https://journal.uptimeinstitute.com/tiercertificationpreparation/
- https://job-boards.greenhouse.io/align46/jobs/5233408007
- https://www.opencompute.org/events/ocp-summit/2025-ocp-global-summit/
- https://www.datacenterdynamics.com/en/dcd-broadcasts/data-center-power-design-2026/accelerating-data-center-time-to-power/
- https://podcasts.apple.com/us/podcast/powering-the-data-center/id6787825340?i=1000787697920