Put responsibilities, technical boundaries and commitment conditions side by side. No named provider is scored by the desk.
No requirements recorded yet. Add them below, then note how each option meets them.
Saved to My buying file in this browser.
Compare usable critical IT capacity at an agreed acceptance date—not advertised campus megawatts, a headline electricity price or building completion. Our recommended decision sequence is: establish technical and delivery eligibility, identify remaining conditions, then compare monthly payment obligations and downside exposure.
Require every proposal to identify its measurement boundary and delivery status. For this comparison, use the following procurement definitions rather than assuming suppliers use identical terminology.
Choose the scope that removes the dependencies your organisation cannot credibly complete before its deadline. Do not compare a building lease with a compute-service quote without adding the missing hardware, integration and operating responsibilities.
Compare the complete power-service architecture and its failure conditions. On-site generation and storage can reduce grid dependence, but the Department of Energy describes them as a range of technologies and configurations—not a single substitute for utility service. ( energy.gov )
Often they address different parts of the arrangement. EPA distinguishes physical PPAs, which involve delivery of electricity, from financial or virtual PPAs, under which the buyer does not take delivery of the project’s electricity. A virtual PPA therefore does not establish physical service to the buyer’s site. ( epa.gov )
Compare payment commitments and ramp exposure before comparing energy prices. The two examples below are not substitutes available to the same parcel, and they do not establish which territory is cheaper.
Build a monthly cash-obligation model, not a single blended cents-per-kWh ranking. Large-load rate design can include minimum-payment, credit-support and infrastructure-cost protections; these deserve separate treatment in the buyer’s model. ( eta-publications.lbl.gov )
Start with the hardware’s requirements and the complete heat-removal path. Do not select a cooling category from an advertised rack-density ceiling alone.
Record multiple milestones and connect payment commencement to the scope actually being purchased. Energisation, access, facility acceptance and compute acceptance should not be collapsed into one ambiguous ready date.
Assign each evidence question to the party capable of answering it, then reconcile the answers. The following is a proposed responsibility map—not a ranking of named suppliers or a claim that every organisation offers the same scope.
Use separate gates; do not average away a blocker. This is the desk’s recommended decision tool.
This review does not establish a live shortlist of 10 MW in Dallas, 20 MW in Northern Virginia or any other specific inventory requirement. Nor does it establish a national electricity-price league table, a universal cost of delay or a guaranteed delivery advantage for on-site generation.
Sources were accessed for this review on 16 October 2026. Living pages and tariff summaries should be refreshed before commitment. URLs are provided below for the evidence register.