Readiness quiz · Research 2026-10-16

Ready for the
next commitment?

Assess one site, one phase and one decision. Use the supplied 0–3 scoring method; known blockers and critical evidence gaps override the total.

Editorial assessment, not a certification. The supplied questions and bands are not statistically validated. Unknown means 0. Assess evidence appropriate to the commitment stage. Final approval remains with authorised reviewers.
1. Have you defined the load, deadline and decision you are actually buying for?
Evidence to attach and source context

Score your requirements brief—not the ambition of the project.

Evidence to attach: A dated, approved load-and-date brief. For a speculative development, use the approved tenant design envelope and identify which assumptions remain uncontracted.

Next action if below 2: Define the requirement before asking suppliers to compete against it. This is the desk’s recommended starting discipline, not an industry certification requirement.

2. Can you distinguish utility service MW from critical IT MW and campus potential?
Evidence to attach and source context

Score the capacity that your intended deployment can use.

Evidence to attach: A capacity reconciliation and electrical single-line diagram, with reserved, commissioned and future capacity clearly labelled.

Why this matters: Core Scientific’s 2025 Form 10-K separately defines gross utility capacity and non-redundant customer IT capacity. DOE defines PUE using facility energy divided by IT energy; this quiz therefore does not accept an annual PUE calculation alone as proof of peak deliverable IT capacity. (sec.gov)

3. What does your utility evidence actually establish?
Evidence to attach and source context

Score the substance of the documents, not the phrase “power secured”.

Evidence to attach: The complete correspondence, studies, agreements and amendments—not a presentation extract.

Why this matters: Dominion offers preliminary power plans and will-serve letters during site selection. Separately, AEP Ohio describes its service-agreement energisation date as a good-faith estimate. Treating either document’s title as an unconditional delivery guarantee is not justified by those descriptions. (dominionenergy.com)

4. Do your land or occupancy rights support the delivery plan?
Evidence to attach and source context

Score enforceable control and necessary access—not exclusivity in a sales conversation.

Evidence to attach: The executed option, lease or acquisition agreement; a rights-and-expiry schedule; and relevant easement information.

Why this matters: AEP Ohio’s published load-study process requires property control through ownership, a lease or an option. That is a territory-specific example, not a national rule. (aepohio.com)

5. Have you checked the actual planning and permitting pathway?
Evidence to attach and source context

Score a parcel-specific permissions register, not the description “industrial land”.

Evidence to attach: Official decisions, application references and an adviser-reviewed permissions register. Include water, discharge, noise and generation matters where relevant.

Why this matters: On 18 March 2025, Loudoun County approved changes requiring special-exception approval for data centres in specified zoning districts, alongside grandfathering provisions. The county explicitly says project circumstances and controlling documents determine the outcome. (loudoun.gov)

6. Are the utility network works and their dependencies visible?
Evidence to attach and source context

Score the route to service, not just the target energisation date.

Evidence to attach: The utility work scope, dependency schedule, milestone confirmations and responsibility matrix.

Why this matters: Dominion’s published connection process includes design, rights of way, permitting, materials, possible regulatory filings and construction. It also explains that projects of similar size can have different delivery times. (dominionenergy.com)

7. Have you tested service restrictions and any bridge-power assumptions?
Evidence to attach and source context

Score the operating conditions behind the MW claim.

Evidence to attach: Service conditions, workload response assumptions and, where applicable, generation authorisations and fuel arrangements.

Why this matters: TCEQ’s electric-generating-unit guidance requires assessment against the relevant authorisation criteria. FERC’s June 2026 large-load proceedings also address different transmission-service arrangements; they are not evidence that a particular site has unrestricted service. (tceq.texas.gov)

8. Is the electrical and physical deployment plan supported by procurement evidence?
Evidence to attach and source context

Score equipment and installation readiness—not a generic equipment lead-time estimate.

Evidence to attach: The long-lead register, supplier confirmations, relevant design reviews and installation plan.

Why this matters: NVIDIA’s DGX H100 data-centre design guide addresses electrical provisioning, rack installation and load-bearing paths from the loading dock to the equipment location. Apply the documentation for your actual hardware—not H100 specifications by default. (docs.nvidia.com)

9. Does “liquid-ready” mean compatible with your exact deployment?
Evidence to attach and source context

Score an approved cooling interface, not a marketing label.

Evidence to attach: The cooling compatibility matrix, design conditions and agreed commissioning scope.

Why this matters: Schneider Electric explains that CDU performance depends on specified flow, pressure, temperature and rating conditions, including filtration. NVIDIA’s DGX GB200 reference architecture uses both direct liquid and air cooling; that example should not be generalised to every AI system. (blog.se.com)

10. Is connectivity part of the activation plan?
Evidence to attach and source context

Score end-to-end connectivity, not proximity to a fibre route.

Evidence to attach: Carrier confirmations, network design and acceptance criteria; request physical-path evidence where diversity is a requirement.

Why this matters: NVIDIA’s DGX SuperPOD architecture includes networking, management nodes and storage alongside the compute systems. This quiz therefore treats the complete deployment—not GPU installation alone—as the unit of readiness. (docs.nvidia.com)

11. Does your programme reach accepted compute, rather than just energisation?
Evidence to attach and source context

Score the complete delivery sequence and its hand-offs.

Evidence to attach: The integrated schedule, commissioning plan, acceptance protocol and relevant test results.

Why this matters: AWS’s commissioning role explicitly covers factory, functional and integrated-system testing. NVIDIA separately describes delivery, installation, testing and operational handover within SuperPOD deployment engagements. (amazon.jobs)

12. Have you modelled the full electricity bill through the load ramp?
Evidence to attach and source context

Score the monthly obligation—not the quoted cents per kWh.

Evidence to attach: The tariff, riders, service terms and inspectable monthly workbook.

Why this matters: AEP Ohio’s published DCT information includes minimum billing-demand formulas, collateral and exit provisions. A demand minimum is not interchangeable with a minimum purchase of energy. DOE’s PUE definition is energy-based, so peak billing demand needs its own defensible input. (aepohio.com)

13. Are offers comparable, and do contracts allocate delivery risk clearly?
Evidence to attach and source context

Score a reconciled commercial scope and a reviewed obligations schedule.

Evidence to attach: A like-for-like comparison and contract-issues schedule. For self-build, use the construction and supply package comparison instead.

Why this matters: CoreWeave’s 2025 Form 10-K describes multi-year, fixed-capacity data-centre leases and the exposure from leasing more capacity than customers use. Your own documents must establish when that exposure begins. (sec.gov)

14. Can the project withstand a delay or slower customer ramp?
Evidence to attach and source context

Score a decision-ready downside model—not a universal “cost of delay” estimate.

Evidence to attach: Base, delay and slower-ramp cases, plus a fallback decision tree.

Modelling discipline: Identify costs already included in the base case before adding delay exposure. Keep debt principal, interest, depreciation and operating expenditure distinct; do not count the same obligation twice. These are this quiz’s proposed modelling controls, not a forecast of losses.

Source context: CoreWeave discloses both capacity-mismatch exposure and development-delay risks, supporting the need for buyer-specific scenarios rather than a single industry loss figure. (sec.gov)

15. Will the evidence still be valid when you sign or pay?
Evidence to attach and source context

Score change control and accountability.

Evidence to attach: The evidence register and latest change memo. Record adviser scope and any supplier or referral remuneration separately.

Why this matters: ERCOT’s 8 July 2026 notice ended further reviews and approvals under its then-existing LLIS process after 10 July 2026 as it moved into Batch Zero. An older process description is therefore not enough to establish a project’s current position. (ercot.com)

Six separate delivery gates.

Gate indications are derived from your answers; they are not independent verification. Keep mandate, economics, contracts and governance controls separate.