Home / Research Your decision Choose a situation Secure a development site Procure AI colocation Review power costs Prepare a capital decision Open buying file ↗ Editorial assessment, not a certification. The supplied questions and bands are not statistically validated. Unknown means 0. Assess evidence appropriate to the commitment stage. Final approval remains with authorised reviewers.
Site, building and phase Next commitment
01 Mandate & utility evidence02 Rights, permissions & works03 Service & technical fit04 Integration & economics05 Commitment & change control
1. Have you defined the load, deadline and decision you are actually buying for? A · 0 — We have an AI infrastructure opportunity, but no agreed load or activation date.B · 1 — We have a headline MW target and approximate delivery window.C · 2 — We have phase-specific critical IT MW, rack-density assumptions, a monthly ramp and required activation dates.D · 3 — C, plus an approved budget, named decision owner, next commitment date and agreed tolerances for delay, reduced capacity and alternative locations.Evidence to attach and source context Score your requirements brief—not the ambition of the project.
Evidence to attach: A dated, approved load-and-date brief. For a speculative development, use the approved tenant design envelope and identify which assumptions remain uncontracted.
Next action if below 2: Define the requirement before asking suppliers to compete against it. This is the desk’s recommended starting discipline, not an industry certification requirement.
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
2. Can you distinguish utility service MW from critical IT MW and campus potential? A · 0 — We use the advertised campus MW as our deployable IT capacity.B · 1 — We recognise the distinction but have no reconciled capacity schedule.C · 2 — Utility service, facility overhead, critical IT capacity, redundancy assumptions and phase allocations are shown separately.D · 3 — C, plus engineering and commercial reviewers have reconciled the figures to the same boundary, operating conditions and delivery phase.Evidence to attach and source context Score the capacity that your intended deployment can use.
Evidence to attach: A capacity reconciliation and electrical single-line diagram, with reserved, commissioned and future capacity clearly labelled.
Why this matters: Core Scientific’s 2025 Form 10-K separately defines gross utility capacity and non-redundant customer IT capacity. DOE defines PUE using facility energy divided by IT energy; this quiz therefore does not accept an annual PUE calculation alone as proof of peak deliverable IT capacity. (sec.gov )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
3. What does your utility evidence actually establish? A · 0 — Our evidence is a broker statement, nearby substation, energy PPA or regional power map.B · 1 — We have preliminary utility correspondence or a will-serve letter, but its conditions are unresolved.C · 2 — We have site-specific studies or a service plan identifying capacity, timing assumptions, works and outstanding obligations.D · 3 — C, plus the arrangements required for this commitment are executed or otherwise formally confirmed, and qualified reviewers have documented remaining conditions and date limitations.Evidence to attach and source context Score the substance of the documents, not the phrase “power secured”.
Evidence to attach: The complete correspondence, studies, agreements and amendments—not a presentation extract.
Why this matters: Dominion offers preliminary power plans and will-serve letters during site selection. Separately, AEP Ohio describes its service-agreement energisation date as a good-faith estimate. Treating either document’s title as an unconditional delivery guarantee is not justified by those descriptions. (dominionenergy.com )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
4. Do your land or occupancy rights support the delivery plan? A · 0 — We do not control the parcel or capacity, or the relevant right has expired.B · 1 — We have an option, reservation or draft lease, but expiry, assignment or access conditions remain unclear.C · 2 — Relevant rights and deadlines are documented, including access for utility, fibre and construction work.D · 3 — C, plus counsel has reviewed the rights needed for this phase and decision, including extensions, conditions precedent and consequences of delay.Evidence to attach and source context Score enforceable control and necessary access—not exclusivity in a sales conversation.
Evidence to attach: The executed option, lease or acquisition agreement; a rights-and-expiry schedule; and relevant easement information.
Why this matters: AEP Ohio’s published load-study process requires property control through ownership, a lease or an option. That is a territory-specific example, not a national rule. (aepohio.com )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
5. Have you checked the actual planning and permitting pathway? A · 0 — We assume existing zoning or the operator’s assurances are sufficient.B · 1 — We have a general permit list without authorities, application references or conditions.C · 2 — A jurisdiction-specific register covers land use, construction and relevant environmental permissions, with owners and dependencies.D · 3 — C, plus permissions required before this commitment are verified, and remaining approvals have reviewed schedules, conditions and escalation triggers.Evidence to attach and source context Score a parcel-specific permissions register, not the description “industrial land”.
Evidence to attach: Official decisions, application references and an adviser-reviewed permissions register. Include water, discharge, noise and generation matters where relevant.
Why this matters: On 18 March 2025, Loudoun County approved changes requiring special-exception approval for data centres in specified zoning districts, alongside grandfathering provisions. The county explicitly says project circumstances and controlling documents determine the outcome. (loudoun.gov )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
6. Are the utility network works and their dependencies visible? A · 0 — We only have a date and a MW figure.B · 1 — We know an upgrade is needed, but scope, responsibility or approvals are unclear.C · 2 — Required lines, substations, rights of way, studies and approvals have named owners and milestones.D · 3 — C, plus the responsible parties have confirmed the current programme, funding responsibilities and critical dependencies, with changes escalated before payments.Evidence to attach and source context Score the route to service, not just the target energisation date.
Evidence to attach: The utility work scope, dependency schedule, milestone confirmations and responsibility matrix.
Why this matters: Dominion’s published connection process includes design, rights of way, permitting, materials, possible regulatory filings and construction. It also explains that projects of similar size can have different delivery times. (dominionenergy.com )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
7. Have you tested service restrictions and any bridge-power assumptions? A · 0 — We assume all advertised power is continuously usable; bridge generation is an untested fallback.B · 1 — We know some restrictions exist but have not mapped them to workloads or contracts.C · 2 — Firmness, curtailment, ramp limits and applicable technical obligations are documented; any bridge solution has a scoped approval, fuel and operating plan.D · 3 — C, plus technical, environmental and commercial reviewers have accepted the intended operating mode and transition plan—or documented that bridge power is unnecessary.Evidence to attach and source context Score the operating conditions behind the MW claim.
Evidence to attach: Service conditions, workload response assumptions and, where applicable, generation authorisations and fuel arrangements.
Why this matters: TCEQ’s electric-generating-unit guidance requires assessment against the relevant authorisation criteria. FERC’s June 2026 large-load proceedings also address different transmission-service arrangements; they are not evidence that a particular site has unrestricted service. (tceq.texas.gov )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
8. Is the electrical and physical deployment plan supported by procurement evidence? A · 0 — We assume the building’s MW rating means our racks will fit and run.B · 1 — We have preliminary equipment specifications or quotations, with delivery and installation unresolved.C · 2 — The phase has an equipment schedule, rack layout, electrical design, structural checks and installation responsibilities.D · 3 — C, plus critical orders or existing assets, delivery milestones, access routes and acceptance requirements are verified to the standard needed for the next commitment.Evidence to attach and source context Score equipment and installation readiness—not a generic equipment lead-time estimate.
Evidence to attach: The long-lead register, supplier confirmations, relevant design reviews and installation plan.
Why this matters: NVIDIA’s DGX H100 data-centre design guide addresses electrical provisioning, rack installation and load-bearing paths from the loading dock to the equipment location. Apply the documentation for your actual hardware—not H100 specifications by default. (docs.nvidia.com )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
9. Does “liquid-ready” mean compatible with your exact deployment? A · 0 — “Liquid-ready” is the extent of our evidence.B · 1 — We have a rack-density claim or CDU rating, but no equipment-specific interface review.C · 2 — The matrix covers coolant, temperatures, flow, pressure, materials, heat rejection, residual air cooling and responsibility boundaries.D · 3 — C, plus the hardware supplier, facility designer and operator have reviewed compatibility, testing, monitoring and remaining integration work.Evidence to attach and source context Score an approved cooling interface, not a marketing label.
Evidence to attach: The cooling compatibility matrix, design conditions and agreed commissioning scope.
Why this matters: Schneider Electric explains that CDU performance depends on specified flow, pressure, temperature and rating conditions, including filtration. NVIDIA’s DGX GB200 reference architecture uses both direct liquid and air cooling; that example should not be generalised to every AI system. (blog.se.com )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
10. Is connectivity part of the activation plan? A · 0 — We assume network connectivity will be arranged after power is ready.B · 1 — Providers are identified, but serviceability, installation or internal networking remains unconfirmed.C · 2 — External services, building entry, cross-connects, internal fabric and storage networking have a documented design and delivery sequence.D · 3 — C, plus orders or existing services, required diversity, performance criteria, testing and accountable owners support the activation date.Evidence to attach and source context Score end-to-end connectivity, not proximity to a fibre route.
Evidence to attach: Carrier confirmations, network design and acceptance criteria; request physical-path evidence where diversity is a requirement.
Why this matters: NVIDIA’s DGX SuperPOD architecture includes networking, management nodes and storage alongside the compute systems. This quiz therefore treats the complete deployment—not GPU installation alone—as the unit of readiness. (docs.nvidia.com )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
11. Does your programme reach accepted compute, rather than just energisation? A · 0 — Our programme ends at utility energisation or building handover.B · 1 — Installation and testing are listed, but durations or responsibilities are assumed.C · 2 — The dependency schedule connects power, cooling, connectivity, rack installation, configuration, testing and operational handover.D · 3 — C, plus responsible parties have confirmed durations, float, acceptance criteria and defect ownership; tests due before this commitment have passed.Evidence to attach and source context Score the complete delivery sequence and its hand-offs.
Evidence to attach: The integrated schedule, commissioning plan, acceptance protocol and relevant test results.
Why this matters: AWS’s commissioning role explicitly covers factory, functional and integrated-system testing. NVIDIA separately describes delivery, installation, testing and operational handover within SuperPOD deployment engagements. (amazon.jobs )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
12. Have you modelled the full electricity bill through the load ramp? A · 0 — We only have an energy price.B · 1 — We added some charges, but minimum demand, ratchets, riders or ramp assumptions remain incomplete.C · 2 — A monthly model separates energy, demand, applicable minimums, riders, taxes, deposits and infrastructure contributions.D · 3 — C, plus the applicable tariff and contract versions are checked, a reviewer has tested the calculations, and slower-ramp cases are included.Evidence to attach and source context Score the monthly obligation—not the quoted cents per kWh.
Evidence to attach: The tariff, riders, service terms and inspectable monthly workbook.
Why this matters: AEP Ohio’s published DCT information includes minimum billing-demand formulas, collateral and exit provisions. A demand minimum is not interchangeable with a minimum purchase of energy. DOE’s PUE definition is energy-based, so peak billing demand needs its own defensible input. (aepohio.com )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
13. Are offers comparable, and do contracts allocate delivery risk clearly? A · 0 — We rank offers by headline $/kW/month or total advertised MW.B · 1 — Capacity and pricing are partly normalised, but commencement, exclusions or remedies remain unclear.C · 2 — Offers use the same critical IT basis and show electricity, integration, escalators, minimum commitments, acceptance and payment triggers separately.D · 3 — C, plus legal and commercial reviewers have assessed delay provisions, termination, liability limits, counterparty obligations and unpriced exclusions.Evidence to attach and source context Score a reconciled commercial scope and a reviewed obligations schedule.
Evidence to attach: A like-for-like comparison and contract-issues schedule. For self-build, use the construction and supply package comparison instead.
Why this matters: CoreWeave’s 2025 Form 10-K describes multi-year, fixed-capacity data-centre leases and the exposure from leasing more capacity than customers use. Your own documents must establish when that exposure begins. (sec.gov )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
14. Can the project withstand a delay or slower customer ramp? A · 0 — We have not modelled downside cases.B · 1 — We apply one generic monthly loss figure or treat all delayed revenue as permanently lost.C · 2 — Buyer-confirmed scenarios separate incremental cash expenditure, financing cash flows, deferred contribution and potentially unrecoverable losses.D · 3 — C, plus finance has reviewed liquidity, covenant implications, customer remedies and executable alternatives, with escalation thresholds approved.Evidence to attach and source context Score a decision-ready downside model—not a universal “cost of delay” estimate.
Evidence to attach: Base, delay and slower-ramp cases, plus a fallback decision tree.
Modelling discipline: Identify costs already included in the base case before adding delay exposure. Keep debt principal, interest, depreciation and operating expenditure distinct; do not count the same obligation twice. These are this quiz’s proposed modelling controls, not a forecast of losses.
Source context: CoreWeave discloses both capacity-mismatch exposure and development-delay risks, supporting the need for buyer-specific scenarios rather than a single industry loss figure. (sec.gov )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
15. Will the evidence still be valid when you sign or pay? A · 0 — Evidence sits in emails; nobody owns revalidation.B · 1 — We have a data room but no consistent dates, conditions or refresh triggers.C · 2 — Material claims have sources, dates, owners and statuses: document-supported, conditional, conflicting or not established.D · 3 — C, plus a named reviewer reconfirms decision-critical evidence before commitment and escalates changes to dates, capacity, tariffs, approvals or counterparties.Evidence to attach and source context Score change control and accountability.
Evidence to attach: The evidence register and latest change memo. Record adviser scope and any supplier or referral remuneration separately.
Why this matters: ERCOT’s 8 July 2026 notice ended further reviews and approvals under its then-existing LLIS process after 10 July 2026 as it moved into Batch Zero. An older process description is therefore not enough to establish a project’s current position. (ercot.com )
Add evidence reference (required for 2–3 points) Document reference Document date Reviewer Unresolved conditions (or none)
Six separate delivery gates.
Gate indications are derived from your answers; they are not independent verification. Keep mandate, economics, contracts and governance controls separate.
Find a chapter 8 chapters
01 What does this readiness quiz tell you? This quiz tests whether your evidence supports your next financial commitment—not whether a site sounds promising. Use it before acquiring land, releasing a utility deposit, signing high-density colocation capacity, approving construction expenditure or committing GPU deliveries.
↗ 02 How should you take the quiz? Assess one site or facility, one phase and one decision at a time. Do not combine evidence from different parcels, buildings or proposed phases.
↗ 03 Which 15 questions should you answer? Score your requirements brief—not the ambition of the project.
↗ 04 What does your score mean? Add the 15 answers. Maximum: 45 points. Apply the overrides below before acting on the band.
↗ 05 When must a blocker override a high score? Always preserve the distinction between a known blocker and missing proof. Under this framework, either can prevent support for the next irreversible commitment, but they require different responses.
↗ 06 What should you do with your weakest answers? Commission the smallest piece of work that can resolve the decision-critical uncertainty. These are suggested deliverables, not claims that a live automated tool has verified your project.
↗ 07 What are the limits of this assessment? Public utility guidance and technical documentation can establish what to investigate; they cannot confirm private capacity allocations, parcel rights, confidential service conditions or supplier delivery commitments. This document makes no site-availability claim and offers no universal connection timeline or cost-of-delay estimate.
↗ 08 Sources URLs below identify the public evidence used. Dated examples are illustrative; check the controlling documents applicable to your project before commitment.
↗ Show all chapters No matching chapters.