Compare two delivery packages against the same requirement. Evidence quality caps every rating; mandatory gates and buyer constraints remain separate.
Choose the option that can substantiate the required critical IT capacity, operating conditions, full payment obligations and activation date—not the option with the largest advertised campus or lowest headline electricity price.
Freeze the requirement before opening supplier scores. Otherwise, an offer can appear superior merely because it assumes a smaller load, later date or weaker operating obligation.
Assess six gates separately. Never publish their average as a readiness percentage.
Use the development profile for site and build decisions; use the AI operator profile for near-term high-density colocation procurement. Both total 100 points.
Score the evidenced position, not the supplier’s confidence. Use integer ratings from zero to five, then cap them by evidence quality.
The following anchors are desk-designed scoring rules. Apply them at the project’s actual stage.
Trace the claim from the named delivery point to the named phase, then identify every condition between that evidence and operation.
Score the monthly payment obligation under the buyer’s ramp—not the advertised cents per kWh. Berkeley Lab’s August 2026 research examines large-load tariff structures and service agreements as mechanisms for managing operational and financial risks, including underutilised investment. It provides context, not a substitute for the tariff and contract applicable to a particular site. ( eta.lbl.gov )
Require a configuration-specific compatibility matrix, not a cooling label. NVIDIA’s DGX GB200 SuperPOD architecture explicitly combines liquid and air cooling. A facility assessment for that configuration must therefore address both heat-removal paths. This example should not be generalised into specifications for every AI rack. ( docs.nvidia.com )
Build the schedule backwards from customer-usable compute, then verify every predecessor and hand-off.
Yes. The gates are deliberately stronger than the weighted average.
Revalidate the project’s applicable process, not merely the date on the last presentation. These are dated developments, not a complete national regulatory update.
Submit a decision sheet backed by an inspectable evidence register—not an unexplained number.
Primary sources below support the factual examples and distinctions. The scoring system and decision rules are the desk’s proposed methodology.