Direct questions · Research 2026-10-16

Your questions.
Evidence-led answers.

Get a direct answer first. Then inspect the documents, conditions and boundaries that make it useful.

Server racks in a data-centre hall
POWER / CAPACITY / COMMITMENTTest the claim. Read the evidence.
Jump to the selected answer ↓
Choose a questionRead →
Power & capacity01 / 24

How do I verify power availability for a data center site?

The short answer

Verify a site-specific service proposition, not a regional capacity claim. Start with the exact parcel, serving utility, requested load and phase dates, then identify what remains conditional between the application and energisation.

What remains uncertain

Whether the claimed capacity applies to this parcel, phase and operating configuration.

Evidence to request

A dated utility response, applicable studies and agreements, outstanding conditions and a usable-capacity reconciliation.

Explore the evidence

Open an item to see what needs establishing.

01Broker statement or campus presentation
What to recordExact claim, author and date
What to ask nextWhich utility document supports it?
02Utility correspondence
What to recordSite, customer entity, load and qualifications
What to ask nextIs this preliminary feasibility, an offer or an obligation?
03Completed study
What to recordStudied configuration, assumptions and identified works
What to ask nextWhat has changed since the study?
04Executed arrangements
What to recordCapacity, service conditions, payment obligations and remedies
What to ask nextWhich conditions precedent remain unsatisfied?
05Delivery programme
What to recordNetwork works, equipment, permits and accountable owners
What to ask nextWhich dependency controls the first usable phase?
06Energisation and acceptance evidence
What to recordActual service limit and completed tests
What to ask nextWhat critical IT load can operate under the agreed resilience conditions?
Research, examples and source context

Dominion’s data-centre enquiry process asks buyers to establish that the site is within its service territory and provide its address or coordinates and requested MW. That is a useful starting point, but it is an enquiry route—not a public reservation of deliverable capacity. (dominionenergy.com)

Use this proposed evidence ladder:

Evidence presented What to record What to ask next
Broker statement or campus presentation Exact claim, author and date Which utility document supports it?
Utility correspondence Site, customer entity, load and qualifications Is this preliminary feasibility, an offer or an obligation?
Completed study Studied configuration, assumptions and identified works What has changed since the study?
Executed arrangements Capacity, service conditions, payment obligations and remedies Which conditions precedent remain unsatisfied?
Delivery programme Network works, equipment, permits and accountable owners Which dependency controls the first usable phase?
Energisation and acceptance evidence Actual service limit and completed tests What critical IT load can operate under the agreed resilience conditions?

For each phase, create one line containing:

Parcel → utility → service MW → critical IT MW → operating conditions → required works → target date → evidence date → unresolved conditions

Ask the utility to confirm whether the studied configuration still applies. Ask the facility engineer separately to reconcile utility capacity with the electrical and cooling design.

Commitment rule: do not promote an unsupported statement to “power secured” merely because several parties repeat it. Label it not established until the relevant evidence is obtained; that is different from concluding that power is unavailable.

Extract from the desk’s supplied research. Source links and limitations stay with the answer.