Market data and deal flow · Research 2026-10-16

Read the market.
Keep the context.

Demand, construction, facility supply and transaction values describe different things. Inspect each figure’s scope, source date and evidence category.

US data-centre electricity demand / TWh

A national demand scenario.
Not a local power offer.

2023 · modelled historical estimate176 TWh
2028 · lower scenario325 TWh
2028 · upper scenario580 TWh

Source: Berkeley Lab’s 2024 assessment, summarised 15 January 2025. The 2028 values are scenario bounds, not observations. Figures reproduced from the supplied research; no newer forecast substituted.

Accessible chart data
Reference yearMeasureTWh
2023Modelled historical estimate176
2028Lower scenario bound325
2028Upper scenario bound580

The market evidence register.

Historical estimates, scenarios, tracked-market observations and secondary-source reporting are explicitly distinguished.

There is no defensible single dollar total in the evidence reviewed. Electricity consumption, construction expenditure, facility inventory and transaction values measure different activities. The following dashboard deliberately keeps them separate.

Measure Figure and reference period Source date and evidence status Buyer interpretation
US data centre electricity consumption 176 TWh in 2023, approximately 4.4% of US electricity use Berkeley Lab’s 2024 assessment, summarised 15 January 2025; modelled historical estimate National demand baseline—not a 2026 observation. (newscenter.lbl.gov)
US electricity demand scenarios 325–580 TWh in 2028 Same assessment; scenario range Useful for demand sensitivities, not local connection availability. (newscenter.lbl.gov)
Implied electricity-demand growth Approximately 13–27% annually, 2023–2028 Desk calculation: (2028 scenario / 176)^(1/5) − 1 Growth implied by the scenarios, not a separately observed forecast. (newscenter.lbl.gov)
Private US data centre construction $84.95bn seasonally adjusted annual pace in August 2026, versus $49.05bn a year earlier Census-derived figures reported by Tom’s Hardware, 6 October 2026; secondary-source verification Roughly 73% year-on-year growth in the annualised spending pace—not $84.95bn spent during August. (tomshardware.com)
Primary-market facility supply 10,903 MW, H1 2026 CBRE, 27 August 2026; tracked wholesale-market observation A defined market sample, not the entire US installed base. (cbre.com)
Primary-market net absorption 1,456.2 MW, H1 2026; 11.7% above H1 2025 CBRE, 27 August 2026 Occupancy change, not gross lease-signing volume. (cbre.com)
Primary-market construction pipeline 7,481.1 MW, H1 2026; 80.4% preleased CBRE, 27 August 2026 Construction does not mean uncommitted supply. (cbre.com)
Global expansion outlook—context only Approximately 100 GW of additions over 2026–2030; 14% capacity CAGR JLL, 5 January 2026; forecast Global context; do not label it a US market forecast. (jll.com)

What does the construction figure include?

Census includes construction and building services such as mechanical and electrical installations. Its definitions explicitly exclude racks and servers; consequently, construction spending is not total AI infrastructure expenditure. (census.gov)

The Census release dated 1 October 2026 confirms August as the reporting month and describes current-month estimates as preliminary. However, the detailed data-centre spreadsheet could not be independently extracted during this research pass. The $84.95bn figure is therefore labelled secondary-source reported, rather than presented as a directly reconciled Census table entry. (census.gov)

Which market-size estimates should not be carried forward?

This report does not validate the supplied planning estimates for US wholesale-colocation revenue or the standalone high-density cooling market. It also does not add construction expenditure, electricity bills, financing commitments and multiyear lease revenue into an aggregate addressable market.

For an investment committee, the more useful sizing question is: how much suitably specified capacity can the project realistically sell or procure within its delivery window? That requires a local, dated competitive set rather than a national revenue estimate.

Deal and milestone register.

Search the supplied transaction evidence. Announcement, execution and completion are not interchangeable.

Event and announcement date
Google–Constellation, 6 October 2026
Generation / supplyAnnounced agreements
Disclosed value and volume
890 MW of incremental nuclear capacity supported by a 20-year PPA; a separate 2,700 MW, 15-year supply agreement; more than $4.3bn of Constellation investment
Evidenced status and timing
Announced agreements; first nuclear uprate expected by 2028. Investment is not the disclosed PPA purchase price. (constellationenergy.com)
Buyer significance
Separate new generation from contracted existing supply. Neither headline establishes service at an unrelated development site.
Event and announcement date
Applied Digital, Polaris Forge 1, 2 October 2026
Delivery milestoneReady for service
Disclosed value and volume
Additional 75 MW critical IT load; campus operational total 250 MW
Evidenced status and timing
Company-reported ready-for-service milestone achieved 1 October 2026, confirmed in results dated 7 October; campus fully leased. (ir.applieddigital.com)
Buyer significance
A delivered-capacity observation, not a listing of 75 MW available to new customers.
Event and announcement date
Cipher Digital, Barber Lake, 25 September 2026
LeasingLease amended
Disclosed value and volume
Additional approximately $5.2bn contracted revenue; total above $9bn over 20 years
Evidenced status and timing
Existing Fluidstack lease amended, coupled with a binding subsequent 10-year AI-lab commitment. Hall deliveries expected Q4 2026–Q1 2027. (globenewswire.com)
Buyer significance
More contracted revenue does not remove change-order or delivery risk.
Event and announcement date
Vantage, 14 September 2026
FinancingFinancing closed
Disclosed value and volume
$2bn financing facility
Evidenced status and timing
Closed; five-year revolving platform including extension options, initially collateralised by three development assets; North American scope. (vantage-dc.com)
Buyer significance
Evidence of development financing—not proof the full amount has been drawn or spent on US construction.
Event and announcement date
Aligned acquisition, 21 July 2026
AcquisitionAcquisition completed
Disclosed value and volume
Approximately $40bn enterprise value; 51 campuses, more than 6.4 GW operational and planned capacity
Evidenced status and timing
Acquisition of 100% of equity completed by AIP, MGX and BlackRock’s GIP consortium. Portfolio spans US and Latin American activities. (aligneddc.com)
Buyer significance
A platform acquisition, not a construction-cost or operating-MW valuation comparable.
Event and announcement date
TeraWulf–Anthropic, 6 July 2026
LeasingLease signed
Disclosed value and volume
Approximately 401 MW critical IT, 20-year lease, approximately $19bn expected contracted revenue
Evidenced status and timing
Signed lease at Hawesville, Kentucky; capacity delivery expected at signing from late 2027 to early 2028. Rent follows delivery of the relevant premises. (investors.terawulf.com)
Buyer significance
Useful evidence of long-duration demand, but delivery and credit-support conditions still require diligence.
Event and announcement date
Applied Digital, Delta Forge 2, 8 June 2026
LeasingLease signed
Disclosed value and volume
210 MW critical IT, 15-year take-or-pay lease; approximately $5.2bn base-term revenue
Evidenced status and timing
Signed with an unnamed US investment-grade hyperscaler; initial operations forecast for Q1 2028 at announcement. Lease reiterated in 7 October 2026 results. (ir.applieddigital.com)
Buyer significance
Signed future demand, not operating inventory; do not identify the unnamed tenant by inference.

Source: Which recent deals and milestones matter to buyers? · supplied research snapshot.