Demand, construction, facility supply and transaction values describe different things. Inspect each figure’s scope, source date and evidence category.
Source: Berkeley Lab’s 2024 assessment, summarised 15 January 2025. The 2028 values are scenario bounds, not observations. Figures reproduced from the supplied research; no newer forecast substituted.
| Reference year | Measure | TWh |
|---|---|---|
| 2023 | Modelled historical estimate | 176 |
| 2028 | Lower scenario bound | 325 |
| 2028 | Upper scenario bound | 580 |
Historical estimates, scenarios, tracked-market observations and secondary-source reporting are explicitly distinguished.
There is no defensible single dollar total in the evidence reviewed. Electricity consumption, construction expenditure, facility inventory and transaction values measure different activities. The following dashboard deliberately keeps them separate.
| Measure | Figure and reference period | Source date and evidence status | Buyer interpretation |
|---|---|---|---|
| US data centre electricity consumption | 176 TWh in 2023, approximately 4.4% of US electricity use | Berkeley Lab’s 2024 assessment, summarised 15 January 2025; modelled historical estimate | National demand baseline—not a 2026 observation. (newscenter.lbl.gov) |
| US electricity demand scenarios | 325–580 TWh in 2028 | Same assessment; scenario range | Useful for demand sensitivities, not local connection availability. (newscenter.lbl.gov) |
| Implied electricity-demand growth | Approximately 13–27% annually, 2023–2028 | Desk calculation: (2028 scenario / 176)^(1/5) − 1 |
Growth implied by the scenarios, not a separately observed forecast. (newscenter.lbl.gov) |
| Private US data centre construction | $84.95bn seasonally adjusted annual pace in August 2026, versus $49.05bn a year earlier | Census-derived figures reported by Tom’s Hardware, 6 October 2026; secondary-source verification | Roughly 73% year-on-year growth in the annualised spending pace—not $84.95bn spent during August. (tomshardware.com) |
| Primary-market facility supply | 10,903 MW, H1 2026 | CBRE, 27 August 2026; tracked wholesale-market observation | A defined market sample, not the entire US installed base. (cbre.com) |
| Primary-market net absorption | 1,456.2 MW, H1 2026; 11.7% above H1 2025 | CBRE, 27 August 2026 | Occupancy change, not gross lease-signing volume. (cbre.com) |
| Primary-market construction pipeline | 7,481.1 MW, H1 2026; 80.4% preleased | CBRE, 27 August 2026 | Construction does not mean uncommitted supply. (cbre.com) |
| Global expansion outlook—context only | Approximately 100 GW of additions over 2026–2030; 14% capacity CAGR | JLL, 5 January 2026; forecast | Global context; do not label it a US market forecast. (jll.com) |
Census includes construction and building services such as mechanical and electrical installations. Its definitions explicitly exclude racks and servers; consequently, construction spending is not total AI infrastructure expenditure. (census.gov)
The Census release dated 1 October 2026 confirms August as the reporting month and describes current-month estimates as preliminary. However, the detailed data-centre spreadsheet could not be independently extracted during this research pass. The $84.95bn figure is therefore labelled secondary-source reported, rather than presented as a directly reconciled Census table entry. (census.gov)
This report does not validate the supplied planning estimates for US wholesale-colocation revenue or the standalone high-density cooling market. It also does not add construction expenditure, electricity bills, financing commitments and multiyear lease revenue into an aggregate addressable market.
For an investment committee, the more useful sizing question is: how much suitably specified capacity can the project realistically sell or procure within its delivery window? That requires a local, dated competitive set rather than a national revenue estimate.
Search the supplied transaction evidence. Announcement, execution and completion are not interchangeable.
Source: Which recent deals and milestones matter to buyers? · supplied research snapshot.
The evidence supports strong infrastructure demand, but not the assumption that announced capacity is available capacity. CBRE reports that primary-market supply increased 33.7% year on year in H1 2026 while vacancy stood at 1.4%. For a buyer, the important question remains whether a particular block meets its technical requirements and activation date. ( cbre.com )
The report uses the following evidence labels:
There is no defensible single dollar total in the evidence reviewed. Electricity consumption, construction expenditure, facility inventory and transaction values measure different activities. The following dashboard deliberately keeps them separate.
Regional data is useful for prioritising enquiries, not proving that a particular site can receive power. The following observations are deliberately narrower than a “best states for data centres” ranking.
Public data supports benchmarks, not a universal high-density colocation price. Geography, commitment size, delivery date and contractual scope must remain visible.
Keep facility construction and tenant technology expenditure separate. JLL’s 5 January 2026 outlook forecasts a global average construction cost of $11.3m/MW in 2026 , up from $10.7m/MW in 2025 , and describes its chart’s scope as shell and core. It separately notes that AI technology fit-out can cost as much as $25m/MW . These are global benchmarks, not US site-specific bids. ( jll.com )
State electricity averages are screening indicators, not data-centre tariffs. EIA’s latest monthly table available at this cut-off covers July 2026 , released 24 September 2026 . It identifies the figures as preliminary estimates and notes that customer-sector classification can depend on utility practice. ( eia.gov )
The following is a selected transaction register, not an exhaustive market-volume database. Values retain their original economic meaning: enterprise value, financing capacity, projected lease revenue or generation investment.
A useful model separates reserved capacity from actual electricity use. The following is a desk illustration dated 16 October 2026 , not a supplier quote, forecast or complete operating budget.
Use the market evidence to sharpen a commitment checklist—not to replace site diligence.
Recommended monitoring priorities are:
URLs are listed for auditability. Dates below are publication dates unless identified as a reporting period or review date.