Response deadline for ERCOT’s specified State and Community Impact RFI
Buyer action / applicability checkCheck submission evidence and unresolved questions; do not assume a late response has been accepted. (ercot.com)
Track the change, establish its applicability and identify the buyer action. Dates and status below belong to the supplied 19 October research snapshot.
Check submission evidence and unresolved questions; do not assume a late response has been accepted. (ercot.com)
Request the update and implementation position; this is not an automatic permit-restart date. (gov.texas.gov)
Recheck applicability and any intervening legal action before reliance. (govinfo.gov)
Treat as an expected report milestone, not project clearance. (ercot.com)
Confirm execution-date and customer applicability before signing. (scc.virginia.gov)
Monitor the schedule and draft changes; do not assume adoption. (loudoun.gov)
NERC adoption and approval, the North Carolina retail settlement and regional FERC implementation remain event-triggered items until relevant orders and implementation dates are verified.
Source: What dates belong in the investment committee’s change register? · supplied research snapshot.
Revalidate Texas approvals, Virginia generator specifications and large-load payment obligations before releasing the next material payment. Texas’s September permitting directive, Virginia’s July generator-permit requirements and Dominion’s approaching January 2027 contract provisions create distinct diligence questions; none should be reduced to a generic assessment of whether a state welcomes data centres. ( gov.texas.gov )
This report separates enacted requirements, adopted rules, procedural orders, proposed tariffs and published standards . A settlement announcement is not treated as a commission approval; a standards ballot is not treated as an effective reliability obligation; and a future reporting date is not treated as an energisation date.
Do not rely on an earlier Texas development timetable without written reconfirmation of the audit and permitting conditions applicable to the project. Three separate developments matter: the governor’s audit direction, ERCOT’s information requests and the adopted large-load interconnection standards. ( gov.texas.gov )
No universal, immediately available connection entitlement was established by the material reviewed. On 18 June 2026 , FERC issued tailored section 206 show-cause orders to PJM, MISO, SPP, CAISO, ISO New England and NYISO. The orders required the operators and transmission owners to justify existing arrangements or propose changes, with initial 30-day information-report and 60-day tariff-response requirements. Those initial response periods are already past. ( ferc.gov )
SPP offers approved large-load processes, but conditional transmission must not be marketed as equivalent to firm service. On 14 January 2026 , FERC accepted SPP’s High Impact Large Load and associated High Impact Large Load Generation Assessment processes, including an approach for generation serving qualifying nearby large loads. ( ferc.gov )
Qualifying customers need a revised minimum-payment and credit model, not just an updated energy price. The Virginia SCC’s 24 February 2026 factsheet explains its large-load provisions in Case PUR-2025-00058 :
They are different regulatory instruments at different jurisdictional levels. Duke announced a North Carolina large-load settlement on 7 October 2026 , involving Duke Energy Carolinas, Duke Energy Progress, Public Staff and other parties. On 14 October 2026 , the North Carolina Department of Justice still described the retail arrangement as a proposal before the Utilities Commission. A final state approval was not established in this research. ( news.duke-energy.com )
The standards-development process reached a major milestone; universal enforceability was not established. NERC announced on 15 October 2026 that its Computational Loads Reliability Standards and implementation plans passed final ballot under Project 2026-02 . The announcement says the standards would next go to the Board of Trustees for adoption and then to FERC for US regulatory approval. ( nerc.com )
Some federal requirements are changing, but the sources do not support treating on-site generation as permit-free. Separate turbine standards, greenhouse-gas rules and emergency-engine operating permissions.
The permit-application date now matters directly to generator specifications. Virginia Code §10.1-1322.6 , added in 2026, provides that for data-centre permit applications submitted on or after 1 July 2026 , DEQ may not issue the relevant permit unless each generator set’s permitted emissions are no higher than those achieved by a Tier 4-equivalent set. The provision includes coverage under a general permit. ( law.lis.virginia.gov )
Use the current edition deliberately, but do not confuse publication with local legal adoption. ASHRAE lists Standard 90.4-2025, Energy Standard for Data Centers , as published and superseding the 2022 edition. Its scope covers new facilities, additions and modifications to relevant systems and equipment. The publisher listing reviewed did not establish an exact publication day. ( ashrae.org )
Separate the already-adopted special-exception requirement from the next package of proposed standards. Loudoun adopted Phase 1 on 18 March 2025 , requiring special-exception approval for data centres in the specified Industrial Park, General Industry and Mineral Resources–Heavy Industry districts. Its grandfathering resolution provides a route for certain applications accepted before 12 February 2025 ; it is not an automatic exemption for every previously discussed project. ( loudoun.gov )
NERC adoption and approval, the North Carolina retail settlement and regional FERC implementation should remain event-triggered monitoring items until their relevant orders and implementation dates are verified.
Use a short regulatory change pack that maps directly to the commitment being requested. The following is the desk’s recommended operating method.
Primary authorities and official publications used below. URLs are provided for the underlying evidence; the inline citations identify the propositions they support.