Video and podcast roundups · Research 2026-10-16

Hear the industry.
Inspect the evidence.

Thirteen published recordings and webinar companions, organised around the evidence you need. Publisher context and research limits stay with each item.

Data-centre campus and power infrastructure at dusk
INDUSTRY CONVERSATIONSListen with a decision in mind.

Research cut-off: 16 October 2026. Source-based roundup; not every recording was watched or heard in full. Some publishers require registration. Embedded playback is offered only for supplied direct video links.

Land & permissions01RECORDING

What data centers are getting wrong about grid readiness

Why watch or listen: The published programme directly addresses developer mistakes when approaching utilities, the capital risks behind proposed connection shortcuts, bridge-power strategies and differences in how utilities and developers define readiness. It also examines the utility–developer interface rather than treating power as a generic regional attribute. Published scope. (latitudemedia.com)

Evidence basis programme and replay listing, not a retrieved transcript. Event details .

Who and when: Latitude Media’s Maeve Allsup with Chelle Izzi, identified as PG&E’s chief commercial officer; 11 March 2026. Format: YouTube recording linked from the publisher’s replay page. Evidence: programme and replay listing, not a retrieved transcript. Event details.

Listening notes, buyer application and evidence limits

Title: What data centers are getting wrong about grid readiness

Who and when: Latitude Media’s Maeve Allsup with Chelle Izzi, identified as PG&E’s chief commercial officer; 11 March 2026. Format: YouTube recording linked from the publisher’s replay page. Evidence: programme and replay listing, not a retrieved transcript. Event details.

Why it earns a place: The published programme directly addresses developer mistakes when approaching utilities, the capital risks behind proposed connection shortcuts, bridge-power strategies and differences in how utilities and developers define readiness. It also examines the utility–developer interface rather than treating power as a generic regional attribute. Published scope. (latitudemedia.com)

Our buyer application: Before the next land payment, ask the utility to identify the applicable load, service conditions, outstanding studies, network works, decision owners and dates. Keep the seller’s wording beside the utility’s wording.

Limit: This is a PG&E-focused conversation, not evidence of service at your parcel or a process that can be transferred unchanged to another territory.

Land & permissions02PODCAST

Data Centers: Site Selection to Approval

Evidence basis publisher description. Episode source .

Who and when: Diana O’Lare interviews Flypower CEO Navdeep Martin for ACEC’s The Market Edge; 17 July 2026. Format: video podcast, with YouTube and Podbean links on the episode page. Evidence: publisher description. Episode source.

Listening notes, buyer application and evidence limits

Title: Data Centers: Site Selection to Approval

Who and when: Diana O’Lare interviews Flypower CEO Navdeep Martin for ACEC’s The Market Edge; 17 July 2026. Format: video podcast, with YouTube and Podbean links on the episode page. Evidence: publisher description. Episode source.

Key takeaways from the description: The discussion connects site selection with permitting, stakeholder concerns, local sentiment and political dynamics. Its useful distinction is between identifying land and identifying a credible approval route; AI-assisted site intelligence is presented as one input to that assessment. Publisher description. (engineeringinc.acec.org)

Our buyer application: Add a separate approval-path worksheet to the data center site selection checklist. Record the decision-making bodies, required hearings, unresolved studies, likely objections and the evidence needed before the next commitment.

Limit: The guest sells site-selection intelligence. The description does not independently validate that software’s predictive accuracy, and the episode should not be treated as a substitute for local planning advice.

Land & permissions03PODCAST

What comes after the data center backlash?

Evidence basis published transcript. Episode and transcript .

Who and when: Catalyst host Shayle Kann with Brian Janous, identified as Cloverleaf Infrastructure’s co-founder and chief commercial officer; 3 September 2026. Format: podcast. Evidence: published transcript. Episode and transcript.

Listening notes, buyer application and evidence limits

Title: What comes after the data center backlash?

Who and when: Catalyst host Shayle Kann with Brian Janous, identified as Cloverleaf Infrastructure’s co-founder and chief commercial officer; 3 September 2026. Format: podcast. Evidence: published transcript. Episode and transcript.

Key takeaways: The conversation separates negotiable project impacts—such as noise, water use, infrastructure costs and electricity bills—from broader opposition to AI and its developers. It also considers the potential and limitations of bringing generation to a project, moving off-grid and using smaller distributed facilities. Transcript. (latitudemedia.com)

Our buyer application: Classify objections before commissioning mitigation work. Distinguish an engineering change, a commercial commitment, a disclosure problem and an objection that may persist despite redesign. Give each an owner and a decision date.

Limit: This is a developer-side discussion. Do not assume the speakers’ interpretation represents local residents, regulators or every affected community.

Power & obligations04PODCAST

Powering the cloud while protecting communities

Evidence basis published transcript. An exact publication date was not established from the retrieved text. Episode source .

Who: CoBank’s Power Plays, hosted by Teri Viswanath and Tamra Reynolds, incorporating contributions from the Data Center Coalition’s Lucas Fykes, NRECA’s Allison Hamilton and Rural Electric Convenience Cooperative’s Sean Middleton. Format: podcast. Evidence: published transcript. An exact publication date was not established from the retrieved text. Episode source.

Listening notes, buyer application and evidence limits

Title: Powering the cloud while protecting communities

Who: CoBank’s Power Plays, hosted by Teri Viswanath and Tamra Reynolds, incorporating contributions from the Data Center Coalition’s Lucas Fykes, NRECA’s Allison Hamilton and Rural Electric Convenience Cooperative’s Sean Middleton. Format: podcast. Evidence: published transcript. An exact publication date was not established from the retrieved text. Episode source.

Key takeaways: The closing discussion identifies dedicated facility charges, allocation of upstream upgrades, minimum bills, demand charges, upfront security and exit provisions as mechanisms used to protect existing customers. It links development acceptance to enforceable commitments rather than general promises of economic benefit. Transcript. (cobank.com)

Our buyer application: Use these categories to interrogate a power proposal. Separate recurring charges, refundable security, non-refundable contributions and termination exposure; then test the contractual payments against a slower load ramp.

Limit: The cooperative-utility perspective is valuable, but the episode supplies no universal tariff or model bill for your project.

Power & obligations05WEBINAR

From interconnection to tariffs: how large loads are reshaping energy policy

Evidence basis programme and replay availability. Event source .

Who and when: Wood Mackenzie’s Caitlin Connelly with Chelle Izzi of PG&E, Parag Soni of Prologis, Doug Scott of the Illinois Commerce Commission and Craig Glazer of PJM; 22 September 2026. Format: one-hour on-demand webinar companion, accessed through the publisher’s form. Evidence: programme and replay availability. Event source.

Listening notes, buyer application and evidence limits

Title: From interconnection to tariffs: how large loads are reshaping energy policy

Who and when: Wood Mackenzie’s Caitlin Connelly with Chelle Izzi of PG&E, Parag Soni of Prologis, Doug Scott of the Illinois Commerce Commission and Craig Glazer of PJM; 22 September 2026. Format: one-hour on-demand webinar companion, accessed through the publisher’s form. Evidence: programme and replay availability. Event source.

Published scope: The panel covers large-load rate structures, cost allocation, protections against customer bill increases and differences in interconnection regulation across markets. Its attraction is the combination of utility, developer, commission and grid-operator perspectives. No panel conclusions are inferred from the agenda. Programme. (woodmac.com)

Our buyer application: Assign responsibility for checking each layer separately: the local service arrangement, applicable electricity tariff, transmission process and project-specific conditions. Ask advisers which document controls each obligation.

Limit: A discussion of regulatory options does not establish that an option has been approved—or applies to your load.

Power & obligations06PODCAST

Powering Progress Episode 4 – The Power Supply Challenge: Delivering Energy for AI Growth

Who and when: Vinson & Elkins’ Aubrey Bishai with energy and infrastructure projects partner Mark Brasher; 18 May 2026. Format: podcast with timestamped transcript. Episode source.

Listening notes, buyer application and evidence limits

Title: Powering Progress Episode 4 – The Power Supply Challenge: Delivering Energy for AI Growth

Who and when: Vinson & Elkins’ Aubrey Bishai with energy and infrastructure projects partner Mark Brasher; 18 May 2026. Format: podcast with timestamped transcript. Episode source.

Key takeaways: Brasher explains how power structures allocate fuel-supply and regulatory risk, why multiple equipment and construction contracts leave interface risks, and how payment commencement may be negotiated around the supplier’s completed obligations even when a separate fuel or power dependency remains unresolved. Transcript. (velaw.com)

Useful starting points: 04:58 for supply structures; 07:34 for construction risk; 10:11 for interconnection and commencement exposure. These are publisher transcript timestamps.

Our buyer application: Ask counsel to map every payment trigger against fuel availability, electrical service, equipment performance and end-user acceptance. Identify who carries the cost when one party finishes but the complete system cannot operate.

Limit: This is issue-spotting, not a project-specific legal opinion.

Power & obligations07PODCAST

Making data centers flexible so they can serve the grid rather than stress it out

Who and when: Volts host David Roberts with Emerald AI CEO Varun Sivaram; 26 August 2026. Format: podcast with transcript and chapters. Episode source.

Listening notes, buyer application and evidence limits

Title: Making data centers flexible so they can serve the grid rather than stress it out

Who and when: Volts host David Roberts with Emerald AI CEO Varun Sivaram; 26 August 2026. Format: podcast with transcript and chapters. Episode source.

Key takeaways: The discussion distinguishes changing when computation runs, moving it between locations and coordinating local resources. It examines workload eligibility, liability for slower jobs, contractual counterparties, enforcement and failures encountered during demonstrations. Those are more useful procurement topics than a general assertion that AI demand can flex. Transcript and chapters. (volts.wtf)

Useful chapters: 08:35 on workload classification; 10:55 on liability; 18:02 on enforcing the commitment.

Our buyer application: Request a curtailment specification covering permitted workloads, response time, event duration, telemetry, restoration and customer remedies. Test it against actual customer service commitments.

Limit: Sivaram is describing his company’s approach. Demonstration results and commercial claims are not proof of compatibility with your workloads or acceptance by your utility.

AI facility readiness08RECORDING

800Vdc MGX Acclerated Computing Rack & Energy Storage for Improved GPU Power Utilization

Evidence basis official video description and OCP programme. Video source .

Who and when: NVIDIA’s Jared Huntington and Mike Tu, published by the Open Compute Project; 22 October 2025. The title above preserves the publisher’s spelling. Format: direct YouTube video. Evidence: official video description and OCP programme. Video source.

Listening notes, buyer application and evidence limits

Title: 800Vdc MGX Acclerated Computing Rack & Energy Storage for Improved GPU Power Utilization

Who and when: NVIDIA’s Jared Huntington and Mike Tu, published by the Open Compute Project; 22 October 2025. The title above preserves the publisher’s spelling. Format: direct YouTube video. Evidence: official video description and OCP programme. Video source.

Key takeaways from the description: The presentation addresses synchronous input-current swings associated with GPU clusters and the use of capacitors, supercapacitors or batteries to moderate them. Its focus is better use of available electrical infrastructure through storage and improved rack input-current behaviour. Official description. (youtube.com)

Our buyer application: Add dynamic power behaviour to the high-density colocation RFI. Request the intended hardware’s load profile, the facility’s accepted operating envelope and the design evidence connecting them—not simply a rack-kW figure.

Limit: This is architecture guidance from a hardware supplier. It does not prove that a particular facility supports an 800 VDC design, or that storage resolves every grid constraint.

AI facility readiness09WEBINAR

OCP Educational Webinar: A Chemical Perspective on Liquid Cooled Data Centers

Evidence basis programme and recording link. Organiser page .

Who and when: The speaker list includes Tom Corrigan of PFX Group, James Kelly of OCP and Alex Cordovil of Dell’Oro Group; 13 November 2025. Format: one-hour recorded webinar companion; OCP explicitly states that viewing is free but registration is required. Evidence: programme and recording link. Organiser page.

Listening notes, buyer application and evidence limits

Title: OCP Educational Webinar: A Chemical Perspective on Liquid Cooled Data Centers

Who and when: The speaker list includes Tom Corrigan of PFX Group, James Kelly of OCP and Alex Cordovil of Dell’Oro Group; 13 November 2025. Format: one-hour recorded webinar companion; OCP explicitly states that viewing is free but registration is required. Evidence: programme and recording link. Organiser page.

Published scope: Coolant choices, fluid chemistry, preparation through flushing and commissioning, operating-health monitoring and responses to fluid ageing. The programme makes this a useful preparation session for specifying responsibilities that extend beyond equipment installation. Programme. (opencompute.org)

Our buyer application: Ask for the approved fluid, compatibility evidence, cleaning acceptance criteria, sampling regime and responsibility for remediation. Put those deliverables into the handover checklist.

Limit: The webinar is educational content involving a fluid supplier, not a project certification or a substitute for hardware-specific requirements.

AI facility readiness10PODCAST

Episode 5: Castrol’s Nick Barrett on Liquid Cooling at Scale

Evidence basis detailed publisher recap. Episode source .

Who and when: The Data Centre Podcast host Ben Craske with Nick Barrett, identified as Castrol’s Data Centre OEM Liaison; 10 July 2026. Format: video podcast; the page links to YouTube and Spotify. Evidence: detailed publisher recap. Episode source.

Listening notes, buyer application and evidence limits

Title: Episode 5: Castrol’s Nick Barrett on Liquid Cooling at Scale

Who and when: The Data Centre Podcast host Ben Craske with Nick Barrett, identified as Castrol’s Data Centre OEM Liaison; 10 July 2026. Format: video podcast; the page links to YouTube and Spotify. Evidence: detailed publisher recap. Episode source.

Key takeaways: Barrett emphasises early fluid planning, commissioning, flushing, monitoring and end-of-life management. The recap also stresses shared understanding across designers, contractors and operating teams, alongside collaborative validation and material-compatibility testing. Publisher recap. (datacentremagazine.com)

Our buyer application: Build a responsibility matrix covering the operator, cooling integrator, hardware manufacturer and fluid supplier. Ask who approves the first fill, who monitors conditions, and who authorises corrective work.

Limit: Castrol has a commercial interest in fluid and lifecycle services. Use the episode to improve questions, not to infer that one supplier or coolant is suitable for every deployment.

AI facility readiness11PODCAST

Episode 103 – Networking at hyperscale with Pradeep Vincent, Oracle Cloud Infrastructure

Evidence basis publisher description. Episode source .

Who and when: DCD’s Georgia Butler with Pradeep Vincent, identified as Oracle’s executive vice president and chief technical architect of OCI; 14 May 2026. Format: Zero Downtime podcast. Evidence: publisher description. Episode source.

Listening notes, buyer application and evidence limits

Title: Episode 103 – Networking at hyperscale with Pradeep Vincent, Oracle Cloud Infrastructure

Who and when: DCD’s Georgia Butler with Pradeep Vincent, identified as Oracle’s executive vice president and chief technical architect of OCI; 14 May 2026. Format: Zero Downtime podcast. Evidence: publisher description. Episode source.

Key takeaways from the description: The episode considers power and networking together for large AI training clusters, including the challenges of moving towards multiple buildings and potentially multiple campuses. Its relevance is the system boundary: the discussion is about a functioning cluster, not GPUs or facility capacity in isolation. Published scope. (datacenterdynamics.com)

Our buyer application: Require a deployment-specific network design alongside the electrical and cooling proposal. Identify physical boundaries, delivery responsibilities and acceptance tests for the intended cluster.

Limit: The short description does not establish recommended topology, bandwidth, latency or procurement specifications. Do not invent those from the episode title.

AI facility readiness12PODCAST

Bringing Data Centers Projects to Life

Evidence basis publisher transcript excerpt and episode description. Publisher page ; podcast listing .

Who and when: Paul Turner and David Tain with commissioning leaders Rodrigo Otárola and Stephen Hedley. The podcast listing dates Episode 64 to 7 October 2026; the publisher’s transcript page is dated 12 October 2026. Format: ICxA podcast/panel. Evidence: publisher transcript excerpt and episode description. Publisher page; podcast listing.

Listening notes, buyer application and evidence limits

Title: Bringing Data Centers Projects to Life

Who and when: Paul Turner and David Tain with commissioning leaders Rodrigo Otárola and Stephen Hedley. The podcast listing dates Episode 64 to 7 October 2026; the publisher’s transcript page is dated 12 October 2026. Format: ICxA podcast/panel. Evidence: publisher transcript excerpt and episode description. Publisher page; podcast listing.

Key takeaways supported by those sources: The discussion centres on commissioning, systems integration and the transition into live operations. The transcript introduction also highlights fragmented knowledge across geographies and the need to bring those perspectives together. Episode description; transcript excerpt. (icxa.net)

Our buyer application: Define separate milestones for construction completion, facility acceptance, IT installation, integrated testing and customer activation. Request the evidence and signatory required at each transition.

Limit: This is a global discussion, not a US project acceptance specification. No universal commissioning duration should be inferred.

Location strategy13PODCAST

Under Pressure: Can data centers keep up with AI?

Who and when: The Weekly Take host Spencer Levy with Digital Realty’s Andy Power and CBRE’s Pat Lynch; 23 June 2026, 35 minutes. Format: podcast with transcript. Episode source.

Listening notes, buyer application and evidence limits

Title: Under Pressure: Can data centers keep up with AI?

Who and when: The Weekly Take host Spencer Levy with Digital Realty’s Andy Power and CBRE’s Pat Lynch; 23 June 2026, 35 minutes. Format: podcast with transcript. Episode source.

Key takeaways: The speakers discuss advance leasing, power and permitting constraints, and the continuing importance of connectivity and proximity to existing data. Power contrasts the location flexibility of some training deployments with his expectations for enterprise inference and other location-sensitive workloads. Those expectations should be treated as his market judgement, not a universal siting rule. Transcript. (cbre.com)

Our buyer application: Write the workload brief before comparing regions. Specify which applications can move, which connections must remain nearby and whether the procurement concerns future reservation or usable capacity by a fixed date.

Limit: This is an operator-and-adviser perspective. Market commentary and vacancy discussion do not establish availability for your requirement.

9 chapters