Verify a site-specific service proposition, not a regional capacity claim. Start with the exact parcel, serving utility, requested load and phase dates, then identify what remains conditional between the application and energisation.
Dominion’s data-centre enquiry process asks buyers to establish that the site is within its service territory and provide its address or coordinates and requested MW. That is a useful starting point, but it is an enquiry route—not a public reservation of deliverable capacity. (dominionenergy.com)
Use this proposed evidence ladder:
| Evidence presented | What to record | What to ask next |
|---|---|---|
| Broker statement or campus presentation | Exact claim, author and date | Which utility document supports it? |
| Utility correspondence | Site, customer entity, load and qualifications | Is this preliminary feasibility, an offer or an obligation? |
| Completed study | Studied configuration, assumptions and identified works | What has changed since the study? |
| Executed arrangements | Capacity, service conditions, payment obligations and remedies | Which conditions precedent remain unsatisfied? |
| Delivery programme | Network works, equipment, permits and accountable owners | Which dependency controls the first usable phase? |
| Energisation and acceptance evidence | Actual service limit and completed tests | What critical IT load can operate under the agreed resilience conditions? |
For each phase, create one line containing:
Parcel → utility → service MW → critical IT MW → operating conditions → required works → target date → evidence date → unresolved conditions
Ask the utility to confirm whether the studied configuration still applies. Ask the facility engineer separately to reconcile utility capacity with the electrical and cooling design.
Commitment rule: do not promote an unsupported statement to “power secured” merely because several parties repeat it. Label it not established until the relevant evidence is obtained; that is different from concluding that power is unavailable.