Refresh the decision whenever a material assumption changes, and immediately before an irreversible commitment.
Recommended change triggers:
- Utility date, load allocation, study assumption or required upgrade changes.
- Tariff, rider, collateral or supply-contract changes.
- Permission delay, new condition or material challenge.
- Hardware configuration, rack density or cooling requirement changes.
- Equipment manufacturing or delivery milestone changes.
- Operator scope, hall allocation or acceptance date changes.
- Customer ramp, credit support or financing conditions change.
Keep each change memo short:
Previous assumption → new evidence → schedule effect → cash effect → affected gate → action → decision owner
The final standard is simple: can the buyer show what usable capacity is supported, on what conditions, at what full cost, and by which evidenced sequence? If not, the next payment should buy the missing information or preserve optionality—not silently convert uncertainty into an approved fact.
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.