Separate the cost of obtaining a decision from the much larger commitments that decision may release. There is no adequately supported universal fee for the entire multidisciplinary scope in this guide.

Which public cost references are actually useful?

Reference What it establishes Important limitation
AEP Ohio load-study fee Its published fee is $50,000 for requests from 50,000 kW to below 100,000 kW. Territory-specific study fee, not the cost of obtaining service or completing diligence. (aepohio.com)
Texas adopted large-load rule text, published 2 October 2026 The intermediate-stage financial-security provision specifies $50,000 per MW; the later agreement’s security can be the greater of that amount or allocated system-upgrade costs. Have counsel confirm effective provisions, applicability and transitional treatment. Security is not interchangeable with a non-refundable fee. (sos.state.tx.us)
JLL 2026 outlook Forecast global average construction cost of $11.3 million/MW, with a stated shell-and-core methodology excluding land and active IT equipment. A global benchmark, not a quote for a particular US liquid-cooled deployment. (jll.com)
Cushman & Wakefield 2026 guide Its public summary reports average greenfield costs of $17.6 million/MW for modern facilities. Do not average it with JLL’s figure: reconcile scope and capacity definitions before using either in underwriting. (cushmanwakefield.com)

For perspective, applying the Texas rule’s $50,000/MW intermediate-security figure to an illustrative qualifying 80 MW request gives $4 million. That arithmetic describes potential security scale—not total project cost, a payment quote or a conclusion that the provision applies to a particular buyer. (sos.state.tx.us)

How should a lean buyer budget the diligence effort?

Use explicit hours and third-party scopes rather than a guessed percentage of project value.

Constructed budgeting example—not observed market rates or a complete engagement quote:

Work package Assumed effort and rate Illustrative amount
Internal integration lead 240 hours × $150 loaded hourly cost $36,000
Technical and commercial specialist review 160 hours × $250 $40,000
Legal review 80 hours × $400 $32,000
Illustrative review subtotal 480 hours $108,000

This excludes surveys, environmental fieldwork, geotechnical investigations, utility fees, detailed design, travel, taxes, procurement deposits, construction and commissioning. It also excludes repeating work when the preferred site or hardware configuration changes.

Obtain separate written scopes for those exclusions. Require each proposal to specify deliverables, assumptions, site visits, reliance rights, turnaround conditions and what triggers additional fees.

The hidden DIY cost is coordination. Make it visible in the work plan: collecting documents, resolving contradictions, updating models, arranging specialist reviews and preparing an approval pack are allocated tasks, not free by-products of appointing advisers.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. www.aepohio.com
  2. www.sos.state.tx.us
  3. www.jll.com
  4. www.cushmanwakefield.com
Read the complete report and source register →

Put the evidence to work.

Keep your requirements, open questions and commitment conditions together.