Skip to content
Open buying file ↗
Do-it-yourself game plans · 2026-10-16

What does the complete DIY process look like?

Run parallel workstreams, but keep separate approval gates. The indicative review windows below are proposed internal planning allowances once usable information is available—not measured market timelines or promises that an external party will respond within them.

Stage Buyer-controlled work Suggested internal allowance Main deliverable Stop or escalation condition
1. Define the requirement Fix load, hardware, phases, date and next commitment 3–5 working days Requirements brief No agreed capacity boundary or deadline
2. Organise evidence Appoint owners; establish secure document control First week, then continuous Evidence register and responsibility matrix Material claims cannot be traced
3. Screen alternatives Compare territories, parcels or facilities 1–3 weeks Shortlist and rejection log No credible route through a blocking condition
4. Establish service conditions Submit complete utility enquiry; examine existing arrangements 1–2 weeks to prepare; external process separate Power evidence pack No identifiable service path or unresolved authority
5. Resolve site and permit risks Commission appropriate legal, environmental and physical checks 3–8 weeks for the initial review cycle; investigations may extend it Site and permit register Acquisition would precede necessary risk resolution
6. Validate technical fit Reconcile power, cooling, structure, fibre and operating scope 2–6 weeks for review and clarification Compatibility matrix and design exceptions Offered capacity cannot support the specified deployment
7. Model and negotiate Build monthly economics and responsibility schedules 2–4 weeks initially; negotiations may extend it Cost workbook and contract issues list Downside exceeds approved limits
8. Authorise commitment Revalidate evidence and approve a bounded expenditure 1–2 weeks Commitment memo A blocker is concealed by an overall score
9. Deliver and accept Track works, equipment, integration and testing Project-specific Accepted capacity and operational handover Energisation is mistaken for acceptance
10. Monitor changes Reconcile progress, obligations and actual performance Weekly during critical delivery Change memo and updated forecast Approval assumptions become stale

Do not add these review windows together to produce a promised activation date. Activities overlap, while utility works, permitting, equipment and construction have their own dependencies.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

    Read the complete report and source register →

    Put the evidence to work.

    Keep your requirements, open questions and commitment conditions together.