Define capacity by its boundary, operating conditions and delivery date before comparing locations or prices.
Use the following definitions in your own brief and require suppliers to reconcile their terminology to them:
| Your comparison field | Required meaning in the procurement |
|---|---|
| Utility service capacity | The permitted or contracted electrical import at the stated delivery point, with relevant demand, operating and curtailment conditions |
| Critical IT capacity | The power available to the computing, storage and network equipment within the agreed facility operating configuration |
| Reserved capacity | The quantity for which the buyer has a contractual reservation or payment obligation; separately establish when it becomes usable |
| Campus potential | Future development capacity, excluded from the current deliverable-capacity total unless independently evidenced |
| Compute-ready date | The date the agreed facility, hardware, network and operational acceptance requirements are satisfied |
Power usage effectiveness, or PUE, measures total facility energy relative to IT energy. DOE describes it on an annual energy basis; it is not, by itself, a certification of instantaneous electrical headroom or rack-level capacity. (energy.gov)
Recommended rule: do not convert advertised utility MW into guaranteed critical IT MW by dividing by a marketing PUE. Require the engineer to reconcile electrical capacity, auxiliary loads, cooling capacity and the intended maintenance or failure configuration.
Likewise, distinguish electricity procurement from connection rights. A virtual PPA can settle financially while the buyer continues receiving electricity from its local utility. It does not establish physical service at the proposed parcel. (betterbuildingssolutioncenter.energy.gov)