Ask: Ari Peskoe, followed by the serving utility’s authorised representative.
Why it matters: The interview should establish the difference between an encouraging statement and an enforceable delivery obligation. AEP Ohio’s published process, for example, describes an electric service agreement containing a good-faith energisation estimate, with the contract term beginning at actual energisation. (aepohio.com)
A good answer should cover:
- The document’s parties, site identifier, load definition, phase dates and expiry.
- Whether it records an enquiry, completed study, service offer or executed agreement.
- Unfinished network works, approvals, customer contributions and third-party dependencies.
- Which dates are estimates, obligations or conditions—and what remedies apply if they move.
- Whether ownership, tenant, load-profile or design changes require consent or restudy.
Sharp follow-up: Which exact sentence would you refuse to let a seller paraphrase as power secured?
Evidence to request: Redacted correspondence, the service study, executed agreements and a utility-confirmed schedule of unresolved conditions.
Buyer use: Attach the assessment to the next land or infrastructure payment request. Mark absent proof as not established, rather than assuming either availability or unavailability.
Expert quote: [Awaiting interview, attribution and publication approval.]
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.
Read the complete report and source register →