Does the location support our workload and network architecture, or only our power requirement?

Ask: Chris Sharp and the buyer’s network and workload architects.

Why it matters: Power is one input to a functioning cluster. NVIDIA’s DGX SuperPOD architecture distinguishes compute, storage and management fabrics; the required connectivity cannot be reduced to a statement that fibre is nearby. (docs.nvidia.com)

A good answer should cover: Start with the actual workload: training, batch inference, interactive inference or a mixture. Require buyer-defined limits for latency, data movement, storage performance, recovery and geographical placement.

Then distinguish:

  • Inside the deployment: compute fabric, storage fabric, management connectivity and performance validation.
  • Outside the deployment: carrier access, physical route diversity, service activation, customer connectivity and contractual service levels.

Sharp follow-up: What measured workload result would cause you to reject an otherwise attractive power location?

Evidence to request: Network designs, route and service confirmations, relevant performance tests and the cost of maintaining any alternative location.

Buyer use: Ask the expert to compare a cheaper-power site with a closer or better-connected alternative using buyer-supplied workload economics. Require the trade-off to be explicit rather than assuming all AI activity has the same location flexibility.

Expert quote: [Awaiting interview, attribution and publication approval.]

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.