Ask: Andy Lawrence, the buyer’s CFO and a lender’s underwriting representative.
Why it matters: Uptime’s 2026 outlook explicitly identifies uncertainty around the speed and ultimate scale of AI infrastructure build-out. The buyer therefore needs scenarios tied to its own commitments, rather than a generic growth forecast converted into a revenue assumption. (professionalservices.uptimeinstitute.com)
A good answer should cover: Ask finance to maintain four separate schedules:
| Schedule | What to establish |
|---|---|
| Continuing contractual payments | Capacity rent, utility minimums and other obligations payable under the relevant contracts |
| Incremental delay cash costs | Additional storage, insurance, financing, remobilisation or other expenditure relative to the baseline |
| Deferred contribution | The timing change in revenue less associated variable costs—not automatically permanent loss |
| Permanent losses and remedies | Supported cancellation exposure, penalties, unrecoverable costs and realistically collectible recoveries |
Sharp follow-up: Which cost appears twice in the model, and which assumed recovery is unsupported by the contract or counterparty credit?
Evidence to request: Buyer-approved assumptions, contract references and monthly cash-flow scenarios for energisation delay, integration delay, slow utilisation and tenant default.
Buyer use: Show deposits and restricted cash separately from expense. Present uncertainty explicitly; do not manufacture probabilities or promise returns.
Expert quote: [Awaiting interview, attribution and publication approval.]
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.
Read the complete report and source register →