Expert Q&A · 2026-10-16

How should an investment committee model delay without inventing a universal cost per MW?

Ask: Andy Lawrence, the buyer’s CFO and a lender’s underwriting representative.

Why it matters: Uptime’s 2026 outlook explicitly identifies uncertainty around the speed and ultimate scale of AI infrastructure build-out. The buyer therefore needs scenarios tied to its own commitments, rather than a generic growth forecast converted into a revenue assumption. (professionalservices.uptimeinstitute.com)

A good answer should cover: Ask finance to maintain four separate schedules:

Schedule What to establish
Continuing contractual payments Capacity rent, utility minimums and other obligations payable under the relevant contracts
Incremental delay cash costs Additional storage, insurance, financing, remobilisation or other expenditure relative to the baseline
Deferred contribution The timing change in revenue less associated variable costs—not automatically permanent loss
Permanent losses and remedies Supported cancellation exposure, penalties, unrecoverable costs and realistically collectible recoveries

Sharp follow-up: Which cost appears twice in the model, and which assumed recovery is unsupported by the contract or counterparty credit?

Evidence to request: Buyer-approved assumptions, contract references and monthly cash-flow scenarios for energisation delay, integration delay, slow utilisation and tenant default.

Buyer use: Show deposits and restricted cash separately from expense. Present uncertainty explicitly; do not manufacture probabilities or promise returns.

Expert quote: [Awaiting interview, attribution and publication approval.]

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.