Expert Q&A · 2026-10-16

How do we reconcile utility service MW, critical IT MW and advertised campus potential?

Ask: Chris Brown, with the project’s electrical and mechanical designers.

Why it matters: A buyer needs a capacity definition that survives technical review. Schneider Electric’s power-sizing guidance explicitly includes IT equipment, cooling, lighting and backup-related requirements when assessing total facility power. (se.com)

A good answer should cover: A phase-by-phase reconciliation from the utility delivery point to usable rack power. Ask the expert to identify electrical losses, cooling and auxiliary demand, operating reserves, maintenance configurations and the limiting equipment path.

Request the following comparison rather than one headline MW figure:

Capacity statement Required clarification
Utility service Delivery point, voltage, import limit, operating conditions and date
Facility electrical capacity Installed versus planned equipment; normal and maintenance configurations
Critical IT capacity Power boundary, rack allocation and supported operating conditions
Campus potential Remaining land, approvals, utility and construction dependencies

Sharp follow-up: Could the facility support the contracted IT load on the design hot day with the specified equipment unavailable for maintenance? Show the calculation and assumptions.

Evidence to request: Signed capacity reconciliation, electrical single-line diagram, equipment ratings and thermal design basis. Ask the expert to explain why any PUE-based shortcut is—or is not—appropriate for the capacity claim.

Expert quote: [Awaiting interview, attribution and publication approval.]

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.