Expert Q&A · 2026-10-16

Which unresolved site dependency should stop the next capital commitment?

Ask: Chris Brown, the development lead and local permitting counsel.

Why it matters: The buyer needs an explicit stopping condition, not an average readiness score. Uptime’s building-characteristics review separates factory testing, installation checks, equipment start-up and integrated testing—useful evidence that readiness requires more than a completed building. (ats.uptimeinstitute.com)

A good answer should cover: Apply six separate gates:

  1. Land control: rights, access, easements and option deadlines.
  2. Planning and permits: applicable permissions, conditions and outstanding proceedings.
  3. Utility arrangements: agreed service and customer obligations.
  4. Network works: scope, approvals, construction and energisation dependencies.
  5. Equipment and facility systems: electrical, cooling, water and connectivity readiness.
  6. Commissioning: test scope, acceptance authority and unresolved defects.

For each gate, ask what is established, what remains conditional and what must be completed before the next payment.

Sharp follow-up: If every other workstream were on time, which single unresolved item could still prevent operation?

Evidence to request: A permit register and dependency schedule linking each condition to its source, owner and required completion date. For Texas air permitting, use the current TCEQ search route: the agency announced a transition to its Permit Search Portal beginning 31 August 2026. (tceq.texas.gov)

Expert quote: [Awaiting interview, attribution and publication approval.]

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.