How should hiring evidence change a site commitment decision?

Keep the six delivery gates separate. Add people and accountability to each gate, rather than creating a blended “hiring readiness score”. The following is a recommended buyer workpaper, not a claim that every project requires the same organisational structure.

Commitment gate People or capability to identify Documentary question before the next commitment
Land control Development lead and transaction counsel Who owns the parcel decision, diligence exceptions and option deadline?
Planning and permits Permitting lead and relevant specialists Which approvals remain unresolved, and who is accountable for each?
Utility arrangements Utility negotiator, energy lead and counsel Who can explain the service conditions, capacity basis and commercial obligations?
Network works Utility/EPC interface, protection engineering and procurement Who owns the substation, connection works, equipment schedule and acceptance interfaces?
Equipment and facility systems Electrical/mechanical engineering, cooling integration and controls Who demonstrates compatibility with the proposed customer configuration?
Commissioning and activation Commissioning lead, deployment lead and operations owner Who has authority to accept the system, resolve defects and authorise operational handover?

What should trigger an immediate clarification request?

Recommended triggers include:

  • A critical role is still being recruited, but the delivery schedule assumes its work is already underway.
  • An advertised position is portfolio-wide, while the buyer assumes dedicated on-site coverage.
  • Supplier installation or testing resources are described as available but are not booked against the project.
  • The operator cannot identify who owns an interface between facility, cooling, controls and customer equipment.
  • The staffing plan starts at facility opening but does not show commissioning or training coverage beforehand.
  • A vacant position is treated as a delivery blocker without checking whether an incumbent, contractor or shared team covers the responsibility.

Missing recruitment evidence means “not established”, not “unstaffed”. The next action is to verify responsibility and coverage, not to infer failure from a careers page.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.