Market data and deal flow The complete report.

Every substantive section, table, FAQ and source. Commissioning credits removed.

Download full research

Research cut-off: 16 October 2026
Prepared for Load & Date Research’s doja research desk
Buyer focus: independent developers assessing 20–100 MW phased projects and AI operators seeking 5–30 MW of high-density colocation. These are research qualification bands, not available inventory.

What should buyers take from the market now?

The evidence supports strong infrastructure demand, but not the assumption that announced capacity is available capacity. CBRE reports that primary-market supply increased 33.7% year on year in H1 2026 while vacancy stood at 1.4%. For a buyer, the important question remains whether a particular block meets its technical requirements and activation date. (cbre.com)

Three recent developments sharpen that distinction:

  • Contracts are filtering speculative power requests. AEP Ohio’s February 2026 update separates initial enquiries, paid studies and binding service contracts rather than treating them as equivalent demand. (aepohio.com)
  • Lease value and delivery risk can rise together. Cipher’s September 2026 Barber Lake amendment increased contracted revenue while revising delivery phasing and allocating additional construction costs. (globenewswire.com)
  • Actual delivery deserves its own category. Applied Digital announced additional ready-for-service capacity in October 2026 at a campus that was already fully leased. Delivery therefore did not create an equivalent amount of open-market availability. (ir.applieddigital.com)

Desk recommendation: organise market intelligence around three separate records: capacity and delivery evidence; recurring and upfront costs; and transaction status. Do not combine them into a single market-growth score.

How should this report’s figures be read?

The report uses the following evidence labels:

Label Meaning in this report Appropriate use
Reported observation A dated statistic published by a regulator, statistical agency, adviser or company Establishing market conditions within the publisher’s coverage
Forecast or scenario A forward-looking estimate from the named source Sensitivity analysis, not a delivery commitment
Company-reported transaction An announcement or filing describing a contract, financing, acquisition or milestone Identifying counterparties and diligence questions
Desk calculation Reproducible arithmetic using disclosed inputs Normalisation and scenario comparison
Not established Evidence sufficient for the stated conclusion was not obtained An explicit diligence gap—not proof of unavailability

For procurement, this desk recommends recording utility service MW, critical IT MW, generation MW and campus potential separately. Applied Digital’s June 2026 disclosure illustrates the importance: it reported approximately 1.4 GW of contracted critical IT load alongside approximately 2.15 GW of gross grid-connected utility power. Those figures describe different things. (ir.applieddigital.com)

Unless otherwise stated, monetary figures are US dollars. Asking rents are not executed lease prices. Company announcements establish what was disclosed, not independent certification of readiness.

How large is the US data centre infrastructure market?

There is no defensible single dollar total in the evidence reviewed. Electricity consumption, construction expenditure, facility inventory and transaction values measure different activities. The following dashboard deliberately keeps them separate.

Measure Figure and reference period Source date and evidence status Buyer interpretation
US data centre electricity consumption 176 TWh in 2023, approximately 4.4% of US electricity use Berkeley Lab’s 2024 assessment, summarised 15 January 2025; modelled historical estimate National demand baseline—not a 2026 observation. (newscenter.lbl.gov)
US electricity demand scenarios 325–580 TWh in 2028 Same assessment; scenario range Useful for demand sensitivities, not local connection availability. (newscenter.lbl.gov)
Implied electricity-demand growth Approximately 13–27% annually, 2023–2028 Desk calculation: (2028 scenario / 176)^(1/5) − 1 Growth implied by the scenarios, not a separately observed forecast. (newscenter.lbl.gov)
Private US data centre construction $84.95bn seasonally adjusted annual pace in August 2026, versus $49.05bn a year earlier Census-derived figures reported by Tom’s Hardware, 6 October 2026; secondary-source verification Roughly 73% year-on-year growth in the annualised spending pace—not $84.95bn spent during August. (tomshardware.com)
Primary-market facility supply 10,903 MW, H1 2026 CBRE, 27 August 2026; tracked wholesale-market observation A defined market sample, not the entire US installed base. (cbre.com)
Primary-market net absorption 1,456.2 MW, H1 2026; 11.7% above H1 2025 CBRE, 27 August 2026 Occupancy change, not gross lease-signing volume. (cbre.com)
Primary-market construction pipeline 7,481.1 MW, H1 2026; 80.4% preleased CBRE, 27 August 2026 Construction does not mean uncommitted supply. (cbre.com)
Global expansion outlook—context only Approximately 100 GW of additions over 2026–2030; 14% capacity CAGR JLL, 5 January 2026; forecast Global context; do not label it a US market forecast. (jll.com)

What does the construction figure include?

Census includes construction and building services such as mechanical and electrical installations. Its definitions explicitly exclude racks and servers; consequently, construction spending is not total AI infrastructure expenditure. (census.gov)

The Census release dated 1 October 2026 confirms August as the reporting month and describes current-month estimates as preliminary. However, the detailed data-centre spreadsheet could not be independently extracted during this research pass. The $84.95bn figure is therefore labelled secondary-source reported, rather than presented as a directly reconciled Census table entry. (census.gov)

Which market-size estimates should not be carried forward?

This report does not validate the supplied planning estimates for US wholesale-colocation revenue or the standalone high-density cooling market. It also does not add construction expenditure, electricity bills, financing commitments and multiyear lease revenue into an aggregate addressable market.

For an investment committee, the more useful sizing question is: how much suitably specified capacity can the project realistically sell or procure within its delivery window? That requires a local, dated competitive set rather than a national revenue estimate.

Where is capacity tight—and what does that mean for a shortlist?

Regional data is useful for prioritising enquiries, not proving that a particular site can receive power. The following observations are deliberately narrower than a “best states for data centres” ranking.

Market Dated evidence Recommended buyer response
Northern Virginia CBRE’s H1 2026 chapter says capacity delivering during 2026 was committed and that contiguous 5–10 MW requirements were difficult to accommodate. Published with the 27 August 2026 report. (cbre.com) Require a named building, phase and contractual availability date. Revalidate any offer described simply as available in Northern Virginia.
Dallas–Fort Worth 95% of more than 765 MW under construction was preleased; an additional 3.7 GW was planned but not under construction, H1 2026. (cbre.com) Separate leased construction from speculative greenfield potential. A search for “10 MW AI colocation capacity available Dallas” needs building-level evidence.
Atlanta CBRE reports turnkey facilities preleasing approximately 12 months before completion and build-to-suit projects approximately 2.5 years ahead, H1 2026. (cbre.com) Compare contractual reservations and delivery conditions, not just the size of the construction pipeline.
Silicon Valley 509.2 MW inventory, 4.2% vacancy and 144 MW under construction, H1 2026; release dated 1 September 2026. (cbre.com) Do not infer that the reported vacancy forms one contiguous, high-density deployment block. Request configuration and cooling evidence.

These recommendations are analyst interpretations, not assertions that suitable inventory is impossible to obtain.

How much of a utility enquiry pipeline becomes a binding commitment?

AEP Ohio provides a useful disclosed example. Its 13 February 2026 update reported the following progression for the requests being filtered through its new data-centre process. (aepohio.com)

Evidence stage Disclosed volume
Initial requests before tariff approval Approximately 30,000 MW
Requests that paid for formal studies 13,022.7 MW
Binding contracts under the new tariff, as of 12 February 2026 5,642 MW

The utility separately reported 12,219 MW contracted before the tariff, producing 17,861 MW of total contracted projects scheduled progressively through 2035. The older contracts must not be confused with the new-tariff conversion cohort. (aepohio.com)

Desk inference: an enquiry pipeline is a weak substitute for bankable demand. For a developer’s competitive analysis, distinguish requests, paid studies, executed agreements, energised service and accepted IT capacity.

What are current colocation prices—and which comparisons are defensible?

Public data supports benchmarks, not a universal high-density colocation price. Geography, commitment size, delivery date and contractual scope must remain visible.

Benchmark Price or movement Date and limitations
Northern Virginia, requirements above 10 MW $160–$185/kW/month asking-rent benchmark H1 2026, CBRE report published 27 August 2026. Not an executable offer or a guarantee of liquid-cooling compatibility. (cbre.com)
Silicon Valley $200–$275/kW/month asking rents H1 2026; CBRE release 1 September 2026. The release does not specify a matching 10-plus-MW tier, so this is not a like-for-like comparison with Northern Virginia. (cbre.com)
Primary markets, 3–10 MW requirements 8.3% increase during H1 2026 CBRE, 27 August 2026; asking-rate movement. (cbre.com)
Primary markets, requirements above 10 MW 6.7% increase during H1 2026 Same report and basis. (cbre.com)

Can disclosed lease values reveal a useful price range?

Yes—but only as an arithmetic lifetime average. Applied Digital’s 2026 filed presentation discloses the following base-term values, excluding pass-through power. The presentation was reviewed on 16 October 2026; its exact publication day was not established in this pass. (ir.applieddigital.com)

Campus Disclosed inputs Desk calculation
Polaris Forge 1 Approximately $11bn, 400 MW, approximately 15 years Approximately $153/kW/month
Delta Forge 1 Approximately $7.5bn, 300 MW, approximately 15 years Approximately $139/kW/month

Calculation: base-term revenue ÷ contracted IT kW ÷ base-term months. These are undiscounted averages, not opening rents. They do not reconstruct escalators, phasing, concessions, landlord obligations or the timing of revenue recognition. They should not be used to claim that a smaller near-term procurement should clear at the same price. (ir.applieddigital.com)

For offer normalisation, request:

  • Critical IT capacity available at acceptance—not campus potential.
  • Reserved capacity and billing commencement by phase.
  • Electricity, demand charges and losses: included, passed through or marked up.
  • Rack density and cooling scope priced into the offer.
  • Escalators, minimum commitments, deposits and termination exposure.
  • Responsibility for tenant fit-out, network integration and acceptance testing.

This is a recommended comparison format, not a statement that every supplier uses the same commercial structure.

What should developers budget for construction and AI fit-out?

Keep facility construction and tenant technology expenditure separate. JLL’s 5 January 2026 outlook forecasts a global average construction cost of $11.3m/MW in 2026, up from $10.7m/MW in 2025, and describes its chart’s scope as shell and core. It separately notes that AI technology fit-out can cost as much as $25m/MW. These are global benchmarks, not US site-specific bids. (jll.com)

As a clearly labelled screening calculation, applying $11.3m/MW to a hypothetical 50 MW project produces $565m. That is an order-of-magnitude reference, not a complete development budget. Do not add the fit-out upper figure automatically: the actual technical scope must first be reconciled.

A construction comparison should ask each estimator to identify whether its number includes:

Cost category Question to resolve before comparison
Land and development Acquisition, site preparation, professional fees and permitting included?
Grid connection Utility contributions, off-site works and substation scope included?
Electrical infrastructure Resilience configuration and equipment procurement basis aligned?
Cooling Heat rejection, distribution, CDUs and residual air cooling assigned to which party?
Tenant infrastructure Networking, racks, servers and installation included or excluded?
Delivery risk Contingency, escalation, financing and commissioning treated consistently?

The checklist is this desk’s recommended budget-reconciliation method. Public benchmarks do not establish a universal liquid-cooling retrofit cost or a universal US cost per commissioned AI MW.

What do electricity prices tell a buyer—and what do they leave out?

State electricity averages are screening indicators, not data-centre tariffs. EIA’s latest monthly table available at this cut-off covers July 2026, released 24 September 2026. It identifies the figures as preliminary estimates and notes that customer-sector classification can depend on utility practice. (eia.gov)

Geography Industrial average, July 2026 Commercial average, July 2026
Texas 7.07¢/kWh 8.47¢/kWh
North Dakota 8.21¢/kWh 8.22¢/kWh
Arizona 9.35¢/kWh 13.12¢/kWh
Georgia 10.03¢/kWh 12.54¢/kWh
Virginia 10.07¢/kWh 11.68¢/kWh
United States 9.77¢/kWh 14.53¢/kWh

Source for every table entry: EIA Electric Power Monthly, Table 5.6.A, 24 September 2026. These are sector-wide averages, not energy-only quotes or prices offered to a particular facility. (eia.gov)

Which large-load tariff conditions materially change ramp economics?

The applicable minimum-demand formula matters more than a headline percentage.

AEP Ohio: its public tariff explainer, reviewed 16 October 2026, describes study fees of $10,000–$100,000, a contract lasting the ramp period plus eight years, and a ramp of no more than four years. Its minimum-demand calculation is tiered and also includes a historical-demand test. (aepohio.com)

For example, the published contract-capacity formula gives a 50 MW customer a 36.25 MW minimum: 15 MW + 85% × (50 − 25) MW, before any higher historical-demand requirement or applicable ramp provisions. It is therefore inaccurate to apply a flat 85% formula to every customer. This is a demand calculation—not a requirement to buy that percentage of unused energy. (aepohio.com)

Dominion Virginia: the SCC describes minimum service obligations of 14 years for new qualifying large-load customers contracting on or after 1 January 2027. It also describes minimum transmission and distribution charges and potential collateral of up to 60% of minimum contract charges for customers without sufficient credit, subject to applicability rules. These provisions should not be treated as already effective for every customer in October 2026. (scc.virginia.gov)

Practical limitation: this pass reviewed public utility and regulator explanations, not a complete customer-specific reconstruction of operative tariff sheets, riders and executed agreements. Obtain specialist confirmation before making a payment or signing service terms.

What changed recently in Texas large-load diligence?

ERCOT’s 14 September 2026 notice required specified unenergised data-centre projects to provide state and community impact information, including water information. The scope included relevant Batch Zero projects and certain substantiated 25–75 MW projects; the stated response deadline was 12 October 2026. (ercot.com)

That deadline has passed as of this report. For an affected site, request evidence of submission and its subsequent status. Do not assume that reaching the deadline meant audit clearance or permission to energise. This report does not establish project-specific clearance or a blanket release of affected projects.

Which recent deals and milestones matter to buyers?

The following is a selected transaction register, not an exhaustive market-volume database. Values retain their original economic meaning: enterprise value, financing capacity, projected lease revenue or generation investment.

Event and announcement date Disclosed value and volume Evidenced status and timing Buyer significance
Google–Constellation, 6 October 2026 890 MW of incremental nuclear capacity supported by a 20-year PPA; a separate 2,700 MW, 15-year supply agreement; more than $4.3bn of Constellation investment Announced agreements; first nuclear uprate expected by 2028. Investment is not the disclosed PPA purchase price. (constellationenergy.com) Separate new generation from contracted existing supply. Neither headline establishes service at an unrelated development site.
Applied Digital, Polaris Forge 1, 2 October 2026 Additional 75 MW critical IT load; campus operational total 250 MW Company-reported ready-for-service milestone achieved 1 October 2026, confirmed in results dated 7 October; campus fully leased. (ir.applieddigital.com) A delivered-capacity observation, not a listing of 75 MW available to new customers.
Cipher Digital, Barber Lake, 25 September 2026 Additional approximately $5.2bn contracted revenue; total above $9bn over 20 years Existing Fluidstack lease amended, coupled with a binding subsequent 10-year AI-lab commitment. Hall deliveries expected Q4 2026–Q1 2027. (globenewswire.com) More contracted revenue does not remove change-order or delivery risk.
Vantage, 14 September 2026 $2bn financing facility Closed; five-year revolving platform including extension options, initially collateralised by three development assets; North American scope. (vantage-dc.com) Evidence of development financing—not proof the full amount has been drawn or spent on US construction.
Aligned acquisition, 21 July 2026 Approximately $40bn enterprise value; 51 campuses, more than 6.4 GW operational and planned capacity Acquisition of 100% of equity completed by AIP, MGX and BlackRock’s GIP consortium. Portfolio spans US and Latin American activities. (aligneddc.com) A platform acquisition, not a construction-cost or operating-MW valuation comparable.
TeraWulf–Anthropic, 6 July 2026 Approximately 401 MW critical IT, 20-year lease, approximately $19bn expected contracted revenue Signed lease at Hawesville, Kentucky; capacity delivery expected at signing from late 2027 to early 2028. Rent follows delivery of the relevant premises. (investors.terawulf.com) Useful evidence of long-duration demand, but delivery and credit-support conditions still require diligence.
Applied Digital, Delta Forge 2, 8 June 2026 210 MW critical IT, 15-year take-or-pay lease; approximately $5.2bn base-term revenue Signed with an unnamed US investment-grade hyperscaler; initial operations forecast for Q1 2028 at announcement. Lease reiterated in 7 October 2026 results. (ir.applieddigital.com) Signed future demand, not operating inventory; do not identify the unnamed tenant by inference.

Which deal deserves particular underwriting attention?

Barber Lake is a useful reminder to track amendments, not only initial announcements. Cipher disclosed that it would bear the first $359.3m of costs above the initial budget under the amended arrangement. It also established a reimbursement framework for part of the excess above that amount. Those disclosures sit alongside the increased lease value and revised phasing. (globenewswire.com)

The recommended diligence response is to obtain a change log showing:

  1. Original versus revised delivery milestones.
  2. Additional scope and its technical cause.
  3. Responsibility for cost overruns.
  4. Timing and security of reimbursement.
  5. Rent commencement and customer acceptance by hall.

Why is there no combined deal-flow dollar total?

A combined figure would obscure rather than clarify activity. The register contains a platform enterprise value, a revolving financing commitment, multiyear lease receipts, generation investment and a physical delivery milestone. Adding them would not measure annual spending, annual revenue or newly available capacity.

For the next research pass, maintain separate transaction series:

  • Acquisitions: consideration, enterprise value, acquired stake and completion date.
  • Financing: committed amount, drawn amount, maturity and collateral.
  • Leasing: new critical IT MW, term, commencement and disclosed base-term revenue.
  • Generation: incremental MW versus existing contracted supply.
  • Delivery: accepted IT MW, commissioning milestone and remaining availability.

These are proposed database fields, not additional market estimates.

What does a 10 MW deployment cost under a slower ramp?

A useful model separates reserved capacity from actual electricity use. The following is a desk illustration dated 16 October 2026, not a supplier quote, forecast or complete operating budget.

Explicit assumptions

  • Reserved critical IT capacity: 10 MW.
  • Capacity charge: $175/kW/month, chosen solely for illustration.
  • Billing applies to the full reservation throughout the year.
  • Actual average IT draw: either 10 MW or 5 MW.
  • Assumed total-facility-to-IT energy ratio: 1.20 in both cases.
  • Assumed energy-only price: $80/MWh.
  • Annual hours: 8,760.
  • Excluded: demand charges, minimum utility bills, taxes, deposits, fit-out, hardware, staffing, financing and network costs.
Calculated item Full average IT draw Half average IT draw
Average IT load 10 MW 5 MW
Assumed average metered load 12 MW 6 MW
Annual metered energy 105,120 MWh 52,560 MWh
Annual reserved-capacity rent $21.00m $21.00m
Annual energy component $8.41m $4.20m
Rent plus energy subtotal $29.41m $25.20m
Subtotal per average utilised IT kW/month $245.08 $420.08

All outputs are desk calculations from the stated hypothetical assumptions. The constant 1.20 energy ratio is a simplifying assumption, not a prediction of part-load facility performance.

The result illustrates the commercial issue: halving utilisation does not halve a fixed capacity reservation. Actual tariff minimums could change the electricity component further; those must be modelled from the applicable documents rather than inferred from this example.

What does delayed activation expose?

Under the same hypothetical reservation, three months of rent is $5.25m if billing has commenced. That is a cash obligation, not automatically an incremental loss: the counterfactual and contract terms determine how much is avoidable.

For a buyer-specific delay model, show separately:

  • Rent and utility obligations that start before usable deployment.
  • Additional storage, handling and financing costs.
  • Customer penalties supported by actual contracts.
  • Deferred contribution from delayed service.
  • Revenue genuinely lost rather than shifted to a later period.

Do not publish a universal dollar cost of delay or treat all delayed revenue as permanently lost.

What evidence should precede the next land, utility or hardware commitment?

Use the market evidence to sharpen a commitment checklist—not to replace site diligence.

Decision Minimum evidence this desk recommends requesting
Extend a land option Parcel-specific service correspondence; planning status; dependencies; expiry dates; next non-refundable payment
Fund utility works Executed service terms; study scope; network works; target-date conditions; collateral and cancellation exposure
Reserve colocation Phase-specific critical IT MW; technical configuration; acceptance criteria; billing start; delay remedies
Release GPU orders Integrated facility, cooling, network, installation and acceptance sequence with named owners
Approve financing Contracted versus operational capacity; remaining cost to complete; tenant support; slower-ramp and delay sensitivities

For each capacity claim, record: what it measures, its source date, its conditions, who confirms it and what must happen next. Use separate statuses such as document-supported, conditional, conflicting and not established.

What should the desk monitor between now and signing?

Recommended monitoring priorities are:

  1. Delivery changes: compare actual accepted capacity with previously announced milestones.
  2. Lease amendments: track scope changes, tenant substitutions, rent commencement and cost reallocations.
  3. Utility evidence: refresh studies, service agreements, network dependencies and applicable tariff terms.
  4. Financing conditions: distinguish facility availability from funding at the project entity.
  5. Technical scope: reconfirm that cooling and electrical acceptance match the chosen hardware.
  6. Comparable offers: refresh price, phase and availability together; a rent observation without a delivery window is incomplete.

The wider channel review included industry reporting, the 23 June 2026 CBRE/Digital Realty podcast and current recruitment listings. The podcast discusses power, permitting and advance leasing; these are useful qualitative signals, not an alternative statistical inventory. (cbre.com)

Job-board searches located operational-readiness roles, but did not establish a reliable hiring-volume series. The linked primary job page was not retrievable, so no recruitment count or labour-market price estimate is used here.

Bottom line: buy-side advantage comes from comparing the same capacity basis, complete payment obligations and evidenced delivery conditions. Large market totals and large contracts can help identify where to investigate; they cannot substitute for a site-specific commitment decision.

Sources

URLs are listed for auditability. Dates below are publication dates unless identified as a reporting period or review date.

  1. Berkeley Lab — electricity-demand assessment summary, 15 January 2025. `https://newscenter.lbl.gov/2025/01/15/berkeley-lab-report-evaluates-increase-in-electricity-demand-from-data-centers/
  2. CBRE — North America Data Center Trends H1 2026, 27 August 2026. `https://www.cbre.com/insights/books/21435420725
  3. JLL — 2026 Global Data Center Market Outlook, 5 January 2026. `https://www.jll.com/en-us/insights/market-outlook/data-center-outlook
  4. Tom’s Hardware — August construction-spending figures, 6 October 2026; secondary reporting of Census detail. `https://www.tomshardware.com/tech-industry/data-centers/spending-on-u-s-data-center-buildings-hits-record-usd85-billion-annual-pace-up-73-percent-in-a-year-and-census-doesnt-count-the-servers-and-racks-inside
  5. US Census Bureau — Monthly Construction Spending, August 2026, released 1 October 2026; rolling release URL. `https://www.census.gov/construction/c30/pdf/release.pdf
  6. US Census Bureau — construction definitions, reviewed 16 October 2026. `https://www.census.gov/construction/c30/definitions.html
  7. CBRE — Northern Virginia, H1 2026. `https://www.cbre.com/insights/books/north-america-data-center-trends-h1-2026/northern-virginia-data-center-market
  8. CBRE — Dallas–Fort Worth, H1 2026. `https://www.cbre.com/insights/books/north-america-data-center-trends-h1-2026/dallas-ft-worth-data-center-market
  9. CBRE — Atlanta, H1 2026. `https://www.cbre.com/insights/books/north-america-data-center-trends-h1-2026/atlanta-data-center-market
  10. CBRE — Silicon Valley market release, 1 September 2026. `https://www.cbre.com/press-releases/silicon-valley-data-center-demand-continues-outpace-supply-causing-vacancy-fall-further-rents-rise
  11. AEP Ohio — contracted-load update, 13 February 2026. `https://www.aepohio.com/company/news/view?releaseID=10753
  12. AEP Ohio — Data Center Tariff explainer, reviewed 16 October 2026. `https://www.aepohio.com/company/about/rates/data-center-tariff/
  13. Virginia SCC — large-load and transmission-cost explanations, reviewed 16 October 2026. `https://www.scc.virginia.gov/about-the-scc/scc-facts/
  14. EIA — Electric Power Monthly, Table 5.6.A, July 2026 data released 24 September 2026; rolling table. `https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=table_5_06_a
  15. ERCOT — State and Community Impact RFI, 14 September 2026. `https://www.ercot.com/services/comm/mkt_notices/M-B091426-01
  16. Applied Digital — 2026 filed investor presentation, reviewed 16 October 2026; exact publication day not established. `https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001144879-26-000036/apld_invxinvestorpresent.htm
  17. Constellation — Google nuclear-uprate and supply agreements, 6 October 2026. `https://www.constellationenergy.com/news/2026/10/google-and-constellation-announce-landmark-agreement-to-bring-890-mw-of-new-nuclear-capacity-to-pjm-grid.html
  18. Applied Digital — additional Polaris Forge 1 capacity, 2 October 2026. `https://ir.applieddigital.com/news-events/press-releases/detail/161/applied-digital-brings-an-additional-75-mw-of-ai
  19. Applied Digital — fiscal Q1 2027 results, 7 October 2026. `https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001144879-26-000057/apldq127earningsrelease.htm
  20. Cipher Digital — Barber Lake amendment and additional commitment, 25 September 2026. `https://www.globenewswire.com/news-release/2026/09/25/3369064/0/en/cipher-digital-expands-barber-lake-lease-term-to-20-years-increasing-revenue-to-over-9-billion.html
  21. Vantage — development financing facility, 14 September 2026. `https://vantage-dc.com/news/vantage-secures-2b-credit-facility-expanding-financing-to-support-growing-demand/
  22. Aligned — acquisition completion, 21 July 2026. `https://aligneddc.com/press-release/aip-mgx-and-blackrocks-gip-close-acquisition-of-aligned-data-centers/
  23. TeraWulf — Form 8-K and transaction release, 6 July 2026. `https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001104659-26-080583/0001104659-26-080583.pdf
  24. Applied Digital — Delta Forge 2 lease, 8 June 2026. `https://ir.applieddigital.com/news-events/press-releases/detail/154/applied-digital-signs-210-mw-lease-at-delta-forge-2
  25. CBRE — Under Pressure: Can data centers keep up with AI?, podcast and transcript, 23 June 2026. `https://www.cbre.com/insights/podcasts/2026-ep26-can-data-centers-keep-up-with-ai

Research limitations: public sources did not establish a complete US revenue market size, an exhaustive transaction-volume series, executable high-density offers or site-specific power availability. The detailed Census construction figure remains secondary-source verified, and customer-specific tariff economics require operative documents and specialist review.

FAQs

How large is the US data centre power market?

Berkeley Lab estimated US data centre electricity consumption at 176 TWh in 2023 and published 2028 scenarios of 325–580 TWh. These measure electricity demand, not market revenue or locally available utility capacity, and the 2023 figure must not be described as a 2026 observation. (newscenter.lbl.gov)

How much does large-block colocation cost in Northern Virginia?

CBRE’s H1 2026 report gives a $160–$185/kW/month asking-rent benchmark for requirements above 10 MW. Treat it as a market reference rather than an executable offer, and separately confirm electricity, technical scope, commencement and availability. (cbre.com)

Does a large construction pipeline mean capacity is available to lease?

No: CBRE reported that 80.4% of primary-market capacity under construction was preleased in H1 2026. Buyers should request the uncommitted capacity in a named phase and its delivery conditions, rather than applying the market’s construction total to their requirement. (cbre.com)

Can state electricity prices be used to budget a data centre?

Use them for initial screening, not as a substitute for the applicable tariff and supply arrangement. EIA’s July 2026 table reports sector-wide averages and notes that commercial and industrial classifications can depend on utility practice. (eia.gov)

Does AEP Ohio always bill data centres for 85% of contracted capacity?

Its published minimum-demand formula is tiered and also includes a historical-demand test, so a blanket 85% calculation is not accurate for every customer. Reconstruct the bill from the operative tariff, ramp provisions and executed agreement; minimum demand is not the same as unused energy consumption. (aepohio.com)

What is the difference between utility service MW and critical IT MW?

They are different capacity measures and should not be substituted for one another in an offer comparison. Applied Digital’s June 2026 disclosure illustrates the distinction by reporting approximately 1.4 GW of contracted critical IT load alongside approximately 2.15 GW of gross grid-connected utility power. (ir.applieddigital.com)

Can announced lease revenue be converted into a colocation price?

Dividing base-term revenue by IT kW and contract months produces an undiscounted lifetime average, not an opening rent. Applied Digital’s disclosed presentation inputs support this calculation, but they do not reconstruct phasing, escalators, concessions or all contractual obligations. (ir.applieddigital.com)

Does the Google–Constellation agreement add 3.59 GW of new generation?

No: the 6 October 2026 announcement separates 890 MW of incremental nuclear capacity from a 2,700 MW agreement supporting existing generation. The first nuclear uprate was expected by 2028, and neither component establishes site-specific utility service for an unrelated buyer. (constellationenergy.com)

Was the approximately $40bn Aligned acquisition completed?

Yes: Aligned announced completion on 21 July 2026 and described approximately $40bn of enterprise value. Its disclosed capacity combined operational and planned assets, so dividing that value by the headline MW would not produce a clean valuation per operating MW. (aligneddc.com)

What should an affected Texas developer check after the October 2026 ERCOT information deadline?

ERCOT’s 14 September notice set 12 October 2026 as the response deadline for specified data-centre projects. Request evidence of submission and the project’s subsequent status; the deadline itself does not establish audit clearance or permission to energise. (ercot.com)