Run separate delay cases for utility service, facility integration and customer ramp. Do not apply one generic “cost per month of delay” to all three.
Illustrative capacity-rent exposure—not a market quote
Assume a buyer contracts for 10,000 kW of critical IT capacity at $175/kW/month. These are illustrative assumptions, not observed pricing or a statement of available capacity.
| Assumed billing outcome during three full months before usable compute | Capacity rent paid during that period |
|---|---|
| Rent commencement is deferred until acceptance | $0 |
| Full contracted rent has already commenced | $5.25 million |
The second calculation is 10,000 × $175 × 3. Monthly rent is $1.75 million. This isolates one contract cash-flow item; it is neither a universal delay loss nor necessarily incremental to the entire lease term.
For the actual project, build four separate schedules:
- Recurring cash: capacity rent, applicable utility charges, staffing and other contractual payments.
- Incremental delay cash: storage, remobilisation, extra financing and buyer-confirmed penalties.
- Liquidity commitments: deposits, letters of credit and collateral, distinguishing balances from fees or expenses.
- Commercial impact: deferred contribution and demonstrably lost business, without treating every delayed sale as permanently lost.
Apply demand floors and ratchets according to the actual tariff; do not add a “minimum bill” again when it has already replaced the relevant billing quantity. The need for component-specific treatment is illustrated by Dominion’s separate transmission/distribution and generation floors. (sustainability.dominionenergy.com)