The useful distinction is between evidence of an intention to build and evidence supporting a deployable configuration. September brought new scrutiny of proposed loads, a power-and-cooling qualification programme and a reminder that an accepted regulatory filing can still leave a procurement delayed. The desk’s recommendation is to organise the shortlist around critical IT MW, operating conditions, full costs and acceptance dates.
1. What does PJM’s load review establish—and what does it not?
PJM is testing forecast credibility, not offering a public list of available sites. Its 29 September update described an annual review using contract information, checks for duplicate connection requests and an independent assessment of data-centre demand. PJM said it did not have a load interconnection queue and relied on load-serving entities to submit forecast adjustments. Near-term requests were expected to demonstrate firmer commitments than longer-term projects. (insidelines.pjm.com)
Procurement implication: Ask a developer which utility submitted the load, what commitment supports it and whether the same demand appears elsewhere. Treat inclusion in a forecast as a planning input—not proof that a particular service date has been secured.
2. Why did Texas diligence expand beyond electrical studies?
ERCOT’s 14 September RFI sought project information extending into water, cooling and community impacts. Its specified recipients included conditionally classified Batch Zero projects and certain substantiated data centres requesting at least 25 MW but below 75 MW, subject to the notice’s energisation conditions. The request was separate from the Batch Zero Eligibility RFI. (ercot.com)
Procurement implication: Reconcile the cooling design, water assumptions, ownership information and load request before submitting them through different workstreams. For a phased development, ask your service provider how the project and its additions are classified; do not assume an individual phase determines the applicable treatment.
3. Does NVIDIA DSX Ready mean a facility is ready?
No: the programme qualifies specified products against relevant requirements, not an entire deployment. NVIDIA launched DSX Ready on 21 September with battery energy storage systems and cooling distribution units as its initial categories. NVIDIA explicitly says BESS qualification does not replace site engineering or establish site-level stability; a qualified CDU still requires assessment against the planned facility. (blogs.nvidia.com)
Procurement implication: Request the exact product, qualification scope, configuration and interfaces. Replace “NVIDIA-compatible cooling” in the proposal with a responsibility matrix covering the equipment supplier, facility operator and GPU integrator.
4. Why did PJM’s backstop procurement not launch on 30 September?
Acceptance came with a suspension. PJM’s 30 September notice said FERC had accepted the backstop proposal but suspended it for five months, with an effective date of 28 February 2027, subject to refund and further proceedings. PJM therefore did not start the procurement on its previously announced date and said the timetable would be reviewed. (insidelines.pjm.com)
Post-month correction: FERC’s separate 9 October decision rejected the bulk of the IRAS filing. Keep September descriptions of proposed market arrangements clearly labelled as historical proposals. (ferc.gov)
5. What does the market benchmark say about negotiating leverage?
Earlier context—not a September movement: CBRE’s H1 2026 report, dated 27 August, recorded 1.4% vacancy across its primary markets and 80.4% preleasing of capacity under construction. These are market-level observations, not evidence of a contiguous, technically suitable block available for your start date. (cbre.com)
Procurement implication: Use the figures to frame negotiations, not to skip diligence. Ask each bidder to identify the specific hall, phase, capacity reservation and remaining delivery conditions behind its offer.