Refresh the evidence behind your power and activation dates before releasing the next land payment, utility deposit or hardware commitment. This week’s practical priorities are operational readiness in PJM, submission evidence in Texas and a clean distinction between proposed rules and approved arrangements.
1. Did PJM require data centres to switch to backup generation?
Not according to PJM’s 15 October update. DOE issued Order 202-26-50 on 12 October, effective 13–16 October, authorising PJM to direct backup resources to operate as a last resort before or during an Energy Emergency Alert 3. PJM subsequently said it had not used that authority; it did activate demand response on 13 and 14 October. Do not turn emergency authorisation into a claim that data centres were actually disconnected or transferred to generators. (energy.gov)
Buyer action: Ask your operator who receives utility instructions, who authorises a transfer, which workloads remain supported and where the tested operating procedure is recorded. Request the applicable contract and operating instructions rather than assuming every facility has the same obligation.
2. Has PJM’s backstop procurement timetable become dependable?
No new procurement start date is established by this week’s filing. On 12 October, PJM requested that FERC pause the backstop paper-hearing proceedings while it prepares a revised filing. PJM identified 22 October for stakeholder consultation and planned to file by 29 October, addressing cost allocation, transmission-owner exit responsibilities and load-serving-entity collateral. Those are procedural milestones, not commitments to deliver generation to a particular project. (pjm.com)
Important carry-forward from 9 October: In a separate proceeding, Commissioner Rosner’s concurrence confirms that FERC rejected the bulk of PJM’s proposed Interim Resource Adequacy Service filing. Do not copy the earlier IRAS proposal into a current investment memorandum as though the proposed framework had been adopted intact. (ferc.gov)
Buyer action: Give the backstop procurement and IRAS separate rows in your regulatory tracker, each with its docket, latest decision and affected underwriting assumption.
3. Can your Texas team prove its RFI was submitted?
The published State and Community Impact RFI deadline was 12 October—not a future task. ERCOT’s September notices required responses from identified recipients and clarified the treatment of certain 25 MW-to-below-75 MW data centres. Its 24 September notice distinguished mandatory responses for previously identified customers from a voluntary route for newly substantiated medium loads. (ercot.com)
Buyer action: Obtain the submission confirmation from the transmission or distribution service provider, the submitted version and any subsequent clarification request. Record the status separately from the Batch Zero Eligibility RFI: ERCOT explicitly describes these as separate requests. (ercot.com)
4. Did ERCOT’s 15 October workshop create a new connection entitlement?
The published agenda does not establish that. The workshop covered the pre-batch portal process, large-load reporting and transparency, and BYOG/PCLR enhancements. An agenda demonstrates that subjects were scheduled for discussion; it is not an adopted rule or a site-specific approval. (ercot.com)
Buyer action: If a seller cites the workshop as evidence of a faster connection route, request the resulting rule text, its implementation status and written confirmation that the project qualifies.
5. Which North Carolina costs need refreshing?
Carry-forward from 7 October: Duke’s announced settlement proposes non-refundable upfront funding for dedicated connection facilities, alongside deposits and security for shared grid upgrades. Duke described applicability, if approved, to customers of at least 50 MW with an 80% load factor signing an electric service agreement after 1 June 2026. The announcement itself is not an approval order. (news.duke-energy.com)
Buyer action: Ask for the proposed terms, any subsequent approval and a reconciliation against your existing service agreement. Separate non-refundable expenditure, refundable security and recurring charges.