What should a high-density colocation comparison contain?

Compare the same deployable requirement before comparing price. For a buyer seeking 10 MW of critical IT capacity, the desk recommends the following return schedule; 10 MW is an illustrative requirement, not identified inventory.

Comparison field What to request from every bidder
Capacity boundary Utility service MW, facility allocation and critical IT MW stated separately
Rack configuration Supported rack count, density, electrical topology and the specified hardware generation
Cooling scope CDU responsibility, facility-water conditions, technical-loop requirements, heat rejection and residual air cooling
Dates Facility access, energisation, cooling completion, network availability and operational acceptance
Commercial commencement Which event starts rent, power minimums and other commitments
Exclusions and remedies Buyer-funded integration, acceptance tests, unresolved conditions and contractual responses to delay

NVIDIA’s published DSX reference design illustrates why cooling needs this level of specificity: it distinguishes facility water, a separate technical cooling loop and air cooling for the data halls. Those are features of that reference architecture, not universal specifications for every AI deployment. (docs.nvidia.com)

Do not use annual PUE as a shortcut to a guaranteed peak IT allocation. DOE defines PUE using total annual facility energy divided by annual IT energy. Our inference: a claimed annual efficiency ratio is insufficient evidence of the electrical and cooling capacity available to a particular rack configuration at peak conditions. (energy.gov)

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.