| Decision owner | Recommended evidence request | Decision it supports |
|---|---|---|
| Development lead | Current utility milestone letter, unresolved conditions and next payment | Whether to extend the option or fund works |
| AI infrastructure COO | Energisation, cooling, network and acceptance dates with named owners | Whether to release or redirect hardware |
| Energy procurement | Applicable tariff version, contract start and security schedule | Whether the proposed ramp remains affordable |
| Investment committee | One-page change log against the last approval pack | Whether approval assumptions remain supportable |
This week’s discipline: Mark each material claim document-supported, conditional, conflicting or not established. Do not let an old approval pack stand in for a current answer.
Reply prompt: Which milestone determines your next commitment: land control, utility service, facility acceptance or customer activation?
Draft 2 — Monthly digest
Subject: September’s capacity test: what can actually run your GPUs?
Preview: Load verification, component qualification and suspended procurement—not another ranking of advertised campus megawatts.
Coverage: 1–30 September 2026; prepared 16 October 2026. Earlier context and post-month developments are labelled explicitly.
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.