| Date or period | Published milestone | What the buyer should verify |
|---|---|---|
| 22 October 2026 | PJM consultation identified in its motion | Whether proposed changes affect costs or obligations. (pjm.com) |
| By 29 October 2026 | PJM’s planned revised backstop filing | Whether it was filed and what changed; filing is not approval. (pjm.com) |
| November 2026 | PJM said it would explain final load adjustments for the 2027 forecast | Whether assumptions relevant to the project have changed. (insidelines.pjm.com) |
| By 10 December 2026 | ERCOT’s expected community-impact report | Findings and any subsequent project-specific requests. (ercot.com) |
| 1 January 2027 | Dominion’s stated GS-5 effective date | Actual tariff and contract applicability. (sustainability.dominionenergy.com) |
The quarter-end test: Can another reviewer trace every material MW, date and payment assumption to a current document, identify its conditions and name the person responsible for the next unresolved action?
Reply prompt: Which assumption would stop your next approval if it changed tomorrow? Make that the first item in the Investment Committee Change Radar.
Sources
Primary sources support the technical and regulatory items. Company announcements are attributed to their issuers; market research, recruitment materials and podcasts are used within their stated limits. All sources were reviewed for this 16 October 2026 research cut-off.
- DOE — Order 202-26-50 overview, issued 12 October 2026: `https://www.energy.gov/ceser/federal-power-act-section-202c-pjm-interconnection-llc-pjm-order-no-202-26-50
- PJM — Providing Reliable Electricity in a New Reality, 15 October 2026: `https://insidelines.pjm.com/providing-reliable-electricity-in-a-new-reality/
- PJM — Motion for Abeyance, 12 October 2026: `https://www.pjm.com/-/media/DotCom/documents/other-fed-state/20261012-el26-108-000.pdf
- FERC — Commissioner Rosner’s concurrence, ER26-3515-000, 9 October 2026: `https://www.ferc.gov/news-events/news/commissioner-rosners-concurrence-pjm-interconnection-llc-er26-3515-000
- ERCOT — Medium-load RFI clarification, 24 September 2026: `https://www.ercot.com/services/comm/mkt_notices/M-B091426-02
- ERCOT — State and Community Impact RFI notice, 14 September 2026: `https://www.ercot.com/services/comm/mkt_notices/M-B091426-01
- ERCOT — Batch/CTP workshop agenda, 15 October 2026: `https://www.ercot.com/calendar/10152026-Batch_CTP-Workshop-3a_Batch-Scope
- Duke Energy — North Carolina large-load settlement announcement, 7 October 2026: `https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs
- PJM — Annual large-load review, 29 September 2026: `https://insidelines.pjm.com/pjm-kicks-off-annual-process-of-vetting-large-load-requests/
- NVIDIA — DSX Ready launch, 21 September 2026: `https://blogs.nvidia.com/blog/dsx-ready-ai-factories-power-cooling/
- PJM — Backstop procurement update, 30 September 2026: `https://insidelines.pjm.com/ferc-accepts-pjm-reliability-backstop-proposal/
- CBRE — North America Data Center Trends H1 2026, 27 August 2026: `https://www.cbre.com/insights/books/21435420725
- NVIDIA — DSX Facilities Infrastructure Reference Design Overview, referencing the 19 August 2026 design guide: `https://docs.nvidia.com/dsx/facilities-infra/reference-design-overview
- DOE — Best Practices Guide for Energy-Efficient Data Center Design, 2024: `https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf
- Fleet Data Centers — Commissioning Senior Manager, Electrical, recruitment page accessed 16 October 2026: `https://job-boards.greenhouse.io/fleet/jobs/4336702009
- CBRE — Under Pressure: Can data centers keep up with AI?, podcast and transcript, 23 June 2026: `https://www.cbre.com/insights/podcasts/2026-ep26-can-data-centers-keep-up-with-ai
- Virginia SCC — Data Center Initiatives and related rate explanations, accessed 16 October 2026: `https://www.scc.virginia.gov/about-the-scc/scc-facts/
- Dominion Energy — GS-5 Large-Load Rate Class Report, accessed 16 October 2026: `https://sustainability.dominionenergy.com/GS-5%20Large%20Load%20Rate%20Class%20Report.pdf
- FERC — Backstop procurement order, ER26-3380-000, 29 September 2026, hosted by PJM: `https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9154/20260929-er26-3380-000.pdf
- TCEQ — Types of Authorization for Turbines, last modified 23 January 2026: `https://www.tceq.texas.gov/permitting/air/guidance/newsourcereview/turbines/nsrauth_turb.html
- Strategic Mission Critical — Mechanical Commissioning Advisor, recruitment page accessed 16 October 2026: `https://job-boards.greenhouse.io/strategicmissioncritical/jobs/4361711009
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.