Use separate commitment gates rather than a blended readiness score. The following is the desk’s proposed checklist, to be tailored with the buyer’s legal, utility and engineering advisers.
| Gate | Evidence to request | Suggested reason to pause the next commitment |
|---|---|---|
| Land control | Executable control documents, access rights and relevant easements | Required rights remain unresolved |
| Planning and permits | Permission register, operating conditions and outstanding decisions | A necessary permission lacks a supportable path |
| Utility arrangements | Applicable agreement, load definition, service conditions and payment schedule | The commercial claim exceeds the supplied document |
| Network works | Defined scope, responsible party, funding and dated milestones | The activation case assumes unfinished works away |
| Equipment and facility systems | Confirmed configuration, delivery records, cooling interfaces and network scope | A critical interface or delivery remains unowned |
| Commissioning and acceptance | Test plan, witnessed results, defect closure and acceptance responsibility | A building-completion date substitutes for tested operation |
This emphasis on documented tests and turnover is consistent with the activities described in Fleet’s commissioning role and Strategic Mission Critical’s mechanical commissioning role, including functional tests, integrated systems testing and deficiency resolution. The postings substantiate the work involved, not readiness at any named facility. (job-boards.greenhouse.io)