Which evidence should release the next tranche of capital?

Use separate commitment gates rather than a blended readiness score. The following is the desk’s proposed checklist, to be tailored with the buyer’s legal, utility and engineering advisers.

Gate Evidence to request Suggested reason to pause the next commitment
Land control Executable control documents, access rights and relevant easements Required rights remain unresolved
Planning and permits Permission register, operating conditions and outstanding decisions A necessary permission lacks a supportable path
Utility arrangements Applicable agreement, load definition, service conditions and payment schedule The commercial claim exceeds the supplied document
Network works Defined scope, responsible party, funding and dated milestones The activation case assumes unfinished works away
Equipment and facility systems Confirmed configuration, delivery records, cooling interfaces and network scope A critical interface or delivery remains unowned
Commissioning and acceptance Test plan, witnessed results, defect closure and acceptance responsibility A building-completion date substitutes for tested operation

This emphasis on documented tests and turnover is consistent with the activities described in Fleet’s commissioning role and Strategic Mission Critical’s mechanical commissioning role, including functional tests, integrated systems testing and deficiency resolution. The postings substantiate the work involved, not readiness at any named facility. (job-boards.greenhouse.io)

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.