Newsletter drafts · 2026-10-16

Which territory-specific developments should affect underwriting?

Virginia: what starts changing in 2027?

Dominion says the approved GS-5 class and tariff become effective on 1 January 2027. The SCC explains that new qualifying large-load customers contracting on or after that date face a minimum 14-year service obligation. Its guidance also describes minimum transmission and distribution charges and potential collateral requirements for customers without sufficient credit. (sustainability.dominionenergy.com)

Dominion’s report states demand-charge floors of 85% of contracted demand for transmission and distribution and 60% for generation. These are different billing components—not an 85% minimum on every element of an electricity bill. (sustainability.dominionenergy.com)

Desk recommendation: Commission a contract-specific monthly ramp model. Ask the utility to confirm applicability, exceptions, phase treatment, collateral, reduction rights and exit provisions before comparing sites on an energy-only rate.

North Carolina: which proposed costs belong in the sensitivity case?

Duke’s 7 October announcement describes a settlement, subject to regulatory approval, covering upfront connection expenditure and security for shared upgrades. This review has not established a subsequent approval order. (news.duke-energy.com)

Desk recommendation: Carry proposed obligations as an explicit scenario until applicability is confirmed. Require the approved tariff or order before treating the settlement’s terms as settled contract economics.

Texas: what does the December reporting milestone mean?

ERCOT’s September notice said it expected to publish conclusions from its State and Community Impact RFI by 10 December 2026. That is an expected reporting milestone; the notice does not promise that publication grants an individual project permission to energise. (ercot.com)

Desk recommendation: Keep separate evidence for classification, completed submissions, study results, network works and permission to energise. Where the remaining process is unclear, identify the uncertainty rather than assigning an unsupported connection date.

PJM: what should remain outside the base delivery assumption?

FERC’s 29 September backstop order accepted the filing subject to a five-month suspension, refund and further proceedings. PJM’s 12 October motion then set out plans for a revised filing by 29 October. Neither establishes that a particular buyer will receive new supply by its required date. (pjm.com)

Desk recommendation: Underwrite site delivery against the actual utility, supply and construction arrangements. Record prospective regulatory improvements separately as potential upside, not as completed dependencies.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. sustainability.dominionenergy.com
  2. news.duke-energy.com
  3. www.ercot.com
  4. www.pjm.com
Read the complete report and source register →