Stage 2: How do you verify power availability for a data center site?

Ask what the documents establish for the named project—not whether the seller describes the site as powered.

Dominion explicitly describes preliminary power planning and will-serve letters within its site-selection support. Its published connection process separately includes infrastructure design, rights-of-way, permitting, materials and construction. Treat those as distinct evidence questions rather than one assurance. (dominionenergy.com)

What should the power evidence register contain?

For every material claim, record:

  • The issuing organisation, document date and project reference.
  • The customer entity, parcel, phase, MW and delivery boundary covered.
  • The exact claim and supporting passage.
  • Outstanding conditions, expiry provisions and required payments.
  • The person authorised to confirm the interpretation.
  • The assessment date and next revalidation trigger.

Use this documentary classification:

Status Meaning Buyer response
Document-supported Evidence expressly supports the defined claim Check scope, conditions and whether it remains current
Conditional Delivery depends on identified outstanding actions Assign owners, dates, funding and consequences
Conflicting Documents or counterparties give inconsistent answers Reconcile before relying on the claim
Not established Adequate supporting evidence has not been provided Request evidence or exclude the claim from the base case

Which questions should go directly to the utility?

  1. Which phase and customer does the service plan cover?
  2. What can be delivered initially, and what requires further works?
  3. Which approvals, rights-of-way and equipment remain outstanding?
  4. Who pays, and which payments become non-refundable?
  5. What would change the delivery date or require another study?

Also establish whether the date is an estimate or an enforceable commitment. Ohio Power’s published process expressly warns that dates involving regional transmission upgrades can be high-level estimates dependent on factors outside its control. (aepohio.com)

Do not accept a PPA as a substitute for this exercise. EPA distinguishes financial PPAs, which do not physically deliver electricity to the customer, from physical PPAs. For either structure, separately establish the site’s connection and delivery arrangements. (epa.gov)

Specialist trigger: before a deposit, acquisition or financing decision relies on ambiguous utility wording, bring in utility counsel and a power-system engineer with relevant territory experience.

Sources & research context

Research snapshot: 2026-10-19. Sources and limitations are retained as supplied.

  1. www.dominionenergy.com
  2. www.aepohio.com
  3. www.epa.gov
Read the complete report and source register →