Use separate commitment gates. Do not average a blocking dependency into a favourable overall score.
The proposed gatecard below is a decision framework. The required evidence should match the commitment: commissioning need not be complete before acquiring development land, but its scope, funding and dependencies should not be omitted from the development case.
| Gate | Evidence to request | Reason to hold or condition the next commitment |
|---|---|---|
| 1. Land control | Title and survey review, option terms, access, easements and assignment rights | Essential land or access cannot be secured on acceptable terms |
| 2. Planning and permits | Parcel-specific permission register, authority correspondence and conditions | Proposed use or essential infrastructure lacks a credible approval route |
| 3. Utility arrangements | Service studies, applicable agreements, deposits and phase commitments | The required load, date or customer is not covered |
| 4. Network works | Scope, responsible party, rights-of-way, procurement and construction milestones | An essential upstream dependency has no accountable delivery plan |
| 5. Equipment and facility systems | Electrical, cooling, water and fibre designs; procurement evidence | The proposed configuration cannot meet the brief without unresolved work |
| 6. Commissioning and acceptance | Test scope, acceptance criteria, responsibility matrix and issue closure process | No agreed method exists to establish readiness for the intended deployment |
For the planning gate, investigate power, water, broadband and land use together. Pennsylvania’s official planning toolkit addresses these as interconnected development considerations; TCEQ separately provides processes for air construction and operating authorisations, application status and permit records. Neither source establishes approval for a particular parcel. (dced.pa.gov)
What should the pre-payment checklist ask?
- [ ] Does each essential dependency have an owner and an evidence-backed next milestone?
- [ ] Does the land-control period accommodate unresolved development decisions?
- [ ] Can expenditure be staged while a consequential uncertainty is resolved?
- [ ] Is there a funded alternative if the first phase slips?
- [ ] Has the investment committee explicitly accepted any speculative exposure?
Does behind-the-meter generation remove these gates?
Treat it as a separate delivery route requiring its own diligence, not an automatic exemption. Request the generation design, fuel arrangements, operating permissions, equipment commitments, maintenance strategy and any grid-interface requirements.
A Texas project application illustrates why operating purpose matters: the Longhorn Data Center filing distinguishes emergency diesel engines from gas turbines intended for primary power, with the primary generation addressed through a different authorisation route. That is a project example, not a universal permit prescription. (records.tceq.texas.gov)
Specialist trigger: appoint local land-use and environmental advisers before relying on a permitting assumption, and generation specialists before treating bridge power as the funded fallback.