Compare monthly cash obligations under the same deployment scenarios, not headline electricity prices.
Ohio’s regulator identifies collateral, minimum demand charges, long contracts and exit fees as elements of its data-centre service arrangements. Ohio Power’s published minimum-demand calculation includes a historical-demand test and a contract-capacity formula; it should not be reduced to a blanket statement that every customer pays for 85% of annual energy. (puco.ohio.gov)
What belongs in the cost model?
| Cost category | Required inputs | Presentation |
|---|---|---|
| Capacity reservation or colocation | Contracted kW, phase commencement, escalation and included services | Monthly recurring payment |
| Electricity | Supply arrangement, tariff, riders, metered energy, peak demand and billing rules | Reproducible monthly bill |
| Infrastructure contributions | Customer-funded works, cancellation exposure and payment milestones | Separate capital schedule |
| Deposits and collateral | Amount, acceptable instrument, release terms and funding cost | Separate liquidity schedule |
| Integration and operations | Cooling integration, network deployment, maintenance and service scope | One-off and recurring costs separated |
| Delay and exit | Storage, financing, alternative capacity, contract remedies and termination terms | Scenario-specific exposure |
For a simple grid-supplied energy estimate, average IT MW × period hours × period-specific PUE can estimate facility MWh if the measurement boundaries are consistent. Use the actual supply and metering arrangement where on-site generation or other loads are involved; calculate billing demand separately under the applicable tariff. DOE defines PUE using total facility and IT energy consumption. (energy.gov)
Do not double-count electricity already included in a colocation charge. Do not treat refundable collateral as a consumed operating expense. Show its liquidity requirement and funding cost separately.
Which scenarios should finance approve?
At minimum, construct buyer-selected cases for:
- Expected delivery and ramp.
- Delayed facility availability, with realistic treatment of when each payment starts.
- On-time availability but slower customer utilisation.
- Reduced usable capacity or constrained operation, where relevant to technical or curtailment terms.
For each, show cumulative cash outflow, peak funding requirement, minimum committed payments and the capacity actually available for deployment.
Keep direct cash costs, deferred contribution and demonstrably lost sales separate. Do not label all delayed revenue as permanent loss, or add foregone revenue to foregone contribution as though they were independent costs.
Which dated tariff issue deserves attention?
Virginia’s SCC states that new large-load customers contracting for service on or after 1 January 2027 face a minimum 14-year service obligation. Its published material also addresses minimum transmission/distribution charges and credit-related collateral. That date is still in the future as of this report; obtain advice on the applicable customer classification and transition provisions before modelling a particular contract. (scc.virginia.gov)
Specialist trigger: use an energy procurement adviser and regulatory counsel when tariff interpretation, pass-throughs, collateral or ramp obligations could change the ranking of offers. Ask for a traceable workbook and applicability opinion, not merely a blended cents-per-kWh estimate.