Translate the diligence findings into contract schedules, approval conditions and accountable obligations. A risk register without a contractual or funded response is not closure.
A publicly filed Digi Power X–Cerebras agreement dated 4 May 2026 illustrates the importance of detail: it distinguishes early access from ready-for-service, conditions its second phase on financing, and includes inspection and deemed-acceptance provisions. Its technical exhibits are omitted and commercial terms are partly redacted, so it is a useful issue checklist—not a pricing benchmark or proof of facility readiness. (sec.gov)
What should counsel and the commercial team reconcile?
- [ ] Capacity, phase, technical scope and measurement boundaries.
- [ ] Acceptance evidence and objection deadlines.
- [ ] Billing triggers and buyer-caused delay provisions.
- [ ] Outside dates, termination rights and remedy limitations.
- [ ] Included services, exclusions and change-in-cost provisions.
- [ ] Financing conditions, assignment and counterparty security.
Have the relevant lawyer review enforceability and interaction with the complete agreement; these are negotiation questions, not assumed rights. (sec.gov)
What should the investment committee receive?
Produce one short commitment memo with appendices:
- Decision requested: amount, deadline and what becomes irreversible.
- Capacity supported: phase, critical IT MW, delivery conditions and evidence date.
- Open blockers: owner, resolution route and latest acceptable decision date.
- Downside funding: delayed-delivery and slow-ramp cases.
- Alternatives: rephase, extend, change facility or stop.
- Approval conditions: evidence required before each subsequent release.
Exit test: legal, technical and commercial assumptions agree. Unresolved risk must be expressly accepted by the authorised buyer—not silently inherited from a supplier presentation.