Start with the next irreversible decision, then investigate the assumptions that could change it. Do not commission a nationwide market study when the immediate question is whether to release a utility deposit or reserve a specific hall.
| Your immediate decision | First action | Required output before proceeding |
|---|---|---|
| Extend an option or acquire land | Reconcile the seller’s power claim with utility evidence and local development permissions | Phase-specific Site Commitment Gatecard |
| Reserve high-density colocation | Compare the same critical IT capacity, technical scope and payment commencement | Critical IT MW Offer Normaliser |
| Commit or ship GPUs | Work backwards from customer activation through integration and testing | GPU-to-Power Deadline Test |
| Sign electricity arrangements | Model the actual tariff and contract against the monthly load ramp | True Cost of Power workbook |
| Obtain investment approval | Identify unresolved dependencies, downside funding and conditions on expenditure | Commitment memo with named risk owners |
Use four decision outcomes:
- Proceed: evidence supports the next commitment and its remaining risks are accepted.
- Proceed conditionally: expenditure is bounded, with explicit conditions and an approval owner.
- Rephase or switch: a smaller deployment, different facility or different date better meets the requirement.
- Hold: a consequential assumption remains unsupported or contradictory.
Missing evidence means “not established”, not automatically “unavailable”.
Sources & research context
Research snapshot: 2026-10-19. Sources and limitations are retained as supplied.