A 15-question buyer assessment for US data centre developers and AI infrastructure operators.
Load & Date Research. Research reviewed 16 October 2026.
What does this readiness quiz tell you?
This quiz tests whether your evidence supports your next financial commitment—not whether a site sounds promising. Use it before acquiring land, releasing a utility deposit, signing high-density colocation capacity, approving construction expenditure or committing GPU deliveries.
You will receive:
- An evidence-readiness score out of 45.
- Separate results for six delivery gates.
- An override identifying blockers that a high score cannot cancel.
- A practical next step and prioritised evidence request.
The intended buyers are independent developers evaluating 20–100 MW phased projects and AI operators seeking 5–30 MW high-density colocation. These are this desk’s target requirement bands, not claims about available inventory.
Important: The questions, points and score bands are an original editorial framework. They have not been statistically validated against project outcomes. A score is not an engineering certification, legal opinion, credit assessment, probability of delivery or authorisation to invest.
How should you take the quiz?
Assess one site or facility, one phase and one decision at a time. Do not combine evidence from different parcels, buildings or proposed phases.
Record this decision brief first:
| Field | Your answer |
|---|---|
| Site, building and phase | |
| Buyer role and decision owner | |
| Required critical IT MW | |
| Required usable-compute date | |
| Next commitment and payment date | |
| Amount becoming non-refundable or otherwise exposed | |
| Assessment date |
Then follow these rules:
- Choose one answer per question. A = 0 points; B = 1; C = 2; D = 3.
- Score what you can substantiate today. If your position falls between answers, choose the lower one.
- Unknown means 0, not “probably fine”. Missing evidence means not established, not necessarily unavailable.
- Outsourced does not mean verified. Colocation buyers should request operator evidence or an appropriately scoped independent review; they do not need to own the underlying utility agreement themselves.
- Match evidence to the commitment stage. Before land acquisition, an approved design envelope and controlled conditions may be appropriate. Before GPU installation, required physical systems and permissions need to be ready. Before customer activation, acceptance evidence must exist.
- Do not award automatic points for “not applicable”. Document why an item is unnecessary and how the underlying requirement is satisfied. For example, a grid-only deployment can score fully on Question 7 without buying bridge generation.
For every answer worth 2 or 3 points, record a document reference, document date, reviewer and unresolved conditions.
Which 15 questions should you answer?
1. Have you defined the load, deadline and decision you are actually buying for?
Score your requirements brief—not the ambition of the project.
- A — 0: We have an AI infrastructure opportunity, but no agreed load or activation date.
- B — 1: We have a headline MW target and approximate delivery window.
- C — 2: We have phase-specific critical IT MW, rack-density assumptions, a monthly ramp and required activation dates.
- D — 3: C, plus an approved budget, named decision owner, next commitment date and agreed tolerances for delay, reduced capacity and alternative locations.
Evidence to attach: A dated, approved load-and-date brief. For a speculative development, use the approved tenant design envelope and identify which assumptions remain uncontracted.
Next action if below 2: Define the requirement before asking suppliers to compete against it. This is the desk’s recommended starting discipline, not an industry certification requirement.
2. Can you distinguish utility service MW from critical IT MW and campus potential?
Score the capacity that your intended deployment can use.
- A — 0: We use the advertised campus MW as our deployable IT capacity.
- B — 1: We recognise the distinction but have no reconciled capacity schedule.
- C — 2: Utility service, facility overhead, critical IT capacity, redundancy assumptions and phase allocations are shown separately.
- D — 3: C, plus engineering and commercial reviewers have reconciled the figures to the same boundary, operating conditions and delivery phase.
Evidence to attach: A capacity reconciliation and electrical single-line diagram, with reserved, commissioned and future capacity clearly labelled.
Why this matters: Core Scientific’s 2025 Form 10-K separately defines gross utility capacity and non-redundant customer IT capacity. DOE defines PUE using facility energy divided by IT energy; this quiz therefore does not accept an annual PUE calculation alone as proof of peak deliverable IT capacity. (sec.gov)
3. What does your utility evidence actually establish?
Score the substance of the documents, not the phrase “power secured”.
- A — 0: Our evidence is a broker statement, nearby substation, energy PPA or regional power map.
- B — 1: We have preliminary utility correspondence or a will-serve letter, but its conditions are unresolved.
- C — 2: We have site-specific studies or a service plan identifying capacity, timing assumptions, works and outstanding obligations.
- D — 3: C, plus the arrangements required for this commitment are executed or otherwise formally confirmed, and qualified reviewers have documented remaining conditions and date limitations.
Evidence to attach: The complete correspondence, studies, agreements and amendments—not a presentation extract.
Why this matters: Dominion offers preliminary power plans and will-serve letters during site selection. Separately, AEP Ohio describes its service-agreement energisation date as a good-faith estimate. Treating either document’s title as an unconditional delivery guarantee is not justified by those descriptions. (dominionenergy.com)
4. Do your land or occupancy rights support the delivery plan?
Score enforceable control and necessary access—not exclusivity in a sales conversation.
- A — 0: We do not control the parcel or capacity, or the relevant right has expired.
- B — 1: We have an option, reservation or draft lease, but expiry, assignment or access conditions remain unclear.
- C — 2: Relevant rights and deadlines are documented, including access for utility, fibre and construction work.
- D — 3: C, plus counsel has reviewed the rights needed for this phase and decision, including extensions, conditions precedent and consequences of delay.
Evidence to attach: The executed option, lease or acquisition agreement; a rights-and-expiry schedule; and relevant easement information.
Why this matters: AEP Ohio’s published load-study process requires property control through ownership, a lease or an option. That is a territory-specific example, not a national rule. (aepohio.com)
5. Have you checked the actual planning and permitting pathway?
Score a parcel-specific permissions register, not the description “industrial land”.
- A — 0: We assume existing zoning or the operator’s assurances are sufficient.
- B — 1: We have a general permit list without authorities, application references or conditions.
- C — 2: A jurisdiction-specific register covers land use, construction and relevant environmental permissions, with owners and dependencies.
- D — 3: C, plus permissions required before this commitment are verified, and remaining approvals have reviewed schedules, conditions and escalation triggers.
Evidence to attach: Official decisions, application references and an adviser-reviewed permissions register. Include water, discharge, noise and generation matters where relevant.
Why this matters: On 18 March 2025, Loudoun County approved changes requiring special-exception approval for data centres in specified zoning districts, alongside grandfathering provisions. The county explicitly says project circumstances and controlling documents determine the outcome. (loudoun.gov)
6. Are the utility network works and their dependencies visible?
Score the route to service, not just the target energisation date.
- A — 0: We only have a date and a MW figure.
- B — 1: We know an upgrade is needed, but scope, responsibility or approvals are unclear.
- C — 2: Required lines, substations, rights of way, studies and approvals have named owners and milestones.
- D — 3: C, plus the responsible parties have confirmed the current programme, funding responsibilities and critical dependencies, with changes escalated before payments.
Evidence to attach: The utility work scope, dependency schedule, milestone confirmations and responsibility matrix.
Why this matters: Dominion’s published connection process includes design, rights of way, permitting, materials, possible regulatory filings and construction. It also explains that projects of similar size can have different delivery times. (dominionenergy.com)
7. Have you tested service restrictions and any bridge-power assumptions?
Score the operating conditions behind the MW claim.
- A — 0: We assume all advertised power is continuously usable; bridge generation is an untested fallback.
- B — 1: We know some restrictions exist but have not mapped them to workloads or contracts.
- C — 2: Firmness, curtailment, ramp limits and applicable technical obligations are documented; any bridge solution has a scoped approval, fuel and operating plan.
- D — 3: C, plus technical, environmental and commercial reviewers have accepted the intended operating mode and transition plan—or documented that bridge power is unnecessary.
Evidence to attach: Service conditions, workload response assumptions and, where applicable, generation authorisations and fuel arrangements.
Why this matters: TCEQ’s electric-generating-unit guidance requires assessment against the relevant authorisation criteria. FERC’s June 2026 large-load proceedings also address different transmission-service arrangements; they are not evidence that a particular site has unrestricted service. (tceq.texas.gov)
8. Is the electrical and physical deployment plan supported by procurement evidence?
Score equipment and installation readiness—not a generic equipment lead-time estimate.
- A — 0: We assume the building’s MW rating means our racks will fit and run.
- B — 1: We have preliminary equipment specifications or quotations, with delivery and installation unresolved.
- C — 2: The phase has an equipment schedule, rack layout, electrical design, structural checks and installation responsibilities.
- D — 3: C, plus critical orders or existing assets, delivery milestones, access routes and acceptance requirements are verified to the standard needed for the next commitment.
Evidence to attach: The long-lead register, supplier confirmations, relevant design reviews and installation plan.
Why this matters: NVIDIA’s DGX H100 data-centre design guide addresses electrical provisioning, rack installation and load-bearing paths from the loading dock to the equipment location. Apply the documentation for your actual hardware—not H100 specifications by default. (docs.nvidia.com)
9. Does “liquid-ready” mean compatible with your exact deployment?
Score an approved cooling interface, not a marketing label.
- A — 0: “Liquid-ready” is the extent of our evidence.
- B — 1: We have a rack-density claim or CDU rating, but no equipment-specific interface review.
- C — 2: The matrix covers coolant, temperatures, flow, pressure, materials, heat rejection, residual air cooling and responsibility boundaries.
- D — 3: C, plus the hardware supplier, facility designer and operator have reviewed compatibility, testing, monitoring and remaining integration work.
Evidence to attach: The cooling compatibility matrix, design conditions and agreed commissioning scope.
Why this matters: Schneider Electric explains that CDU performance depends on specified flow, pressure, temperature and rating conditions, including filtration. NVIDIA’s DGX GB200 reference architecture uses both direct liquid and air cooling; that example should not be generalised to every AI system. (blog.se.com)
10. Is connectivity part of the activation plan?
Score end-to-end connectivity, not proximity to a fibre route.
- A — 0: We assume network connectivity will be arranged after power is ready.
- B — 1: Providers are identified, but serviceability, installation or internal networking remains unconfirmed.
- C — 2: External services, building entry, cross-connects, internal fabric and storage networking have a documented design and delivery sequence.
- D — 3: C, plus orders or existing services, required diversity, performance criteria, testing and accountable owners support the activation date.
Evidence to attach: Carrier confirmations, network design and acceptance criteria; request physical-path evidence where diversity is a requirement.
Why this matters: NVIDIA’s DGX SuperPOD architecture includes networking, management nodes and storage alongside the compute systems. This quiz therefore treats the complete deployment—not GPU installation alone—as the unit of readiness. (docs.nvidia.com)
11. Does your programme reach accepted compute, rather than just energisation?
Score the complete delivery sequence and its hand-offs.
- A — 0: Our programme ends at utility energisation or building handover.
- B — 1: Installation and testing are listed, but durations or responsibilities are assumed.
- C — 2: The dependency schedule connects power, cooling, connectivity, rack installation, configuration, testing and operational handover.
- D — 3: C, plus responsible parties have confirmed durations, float, acceptance criteria and defect ownership; tests due before this commitment have passed.
Evidence to attach: The integrated schedule, commissioning plan, acceptance protocol and relevant test results.
Why this matters: AWS’s commissioning role explicitly covers factory, functional and integrated-system testing. NVIDIA separately describes delivery, installation, testing and operational handover within SuperPOD deployment engagements. (amazon.jobs)
12. Have you modelled the full electricity bill through the load ramp?
Score the monthly obligation—not the quoted cents per kWh.
- A — 0: We only have an energy price.
- B — 1: We added some charges, but minimum demand, ratchets, riders or ramp assumptions remain incomplete.
- C — 2: A monthly model separates energy, demand, applicable minimums, riders, taxes, deposits and infrastructure contributions.
- D — 3: C, plus the applicable tariff and contract versions are checked, a reviewer has tested the calculations, and slower-ramp cases are included.
Evidence to attach: The tariff, riders, service terms and inspectable monthly workbook.
Why this matters: AEP Ohio’s published DCT information includes minimum billing-demand formulas, collateral and exit provisions. A demand minimum is not interchangeable with a minimum purchase of energy. DOE’s PUE definition is energy-based, so peak billing demand needs its own defensible input. (aepohio.com)
13. Are offers comparable, and do contracts allocate delivery risk clearly?
Score a reconciled commercial scope and a reviewed obligations schedule.
- A — 0: We rank offers by headline $/kW/month or total advertised MW.
- B — 1: Capacity and pricing are partly normalised, but commencement, exclusions or remedies remain unclear.
- C — 2: Offers use the same critical IT basis and show electricity, integration, escalators, minimum commitments, acceptance and payment triggers separately.
- D — 3: C, plus legal and commercial reviewers have assessed delay provisions, termination, liability limits, counterparty obligations and unpriced exclusions.
Evidence to attach: A like-for-like comparison and contract-issues schedule. For self-build, use the construction and supply package comparison instead.
Why this matters: CoreWeave’s 2025 Form 10-K describes multi-year, fixed-capacity data-centre leases and the exposure from leasing more capacity than customers use. Your own documents must establish when that exposure begins. (sec.gov)
14. Can the project withstand a delay or slower customer ramp?
Score a decision-ready downside model—not a universal “cost of delay” estimate.
- A — 0: We have not modelled downside cases.
- B — 1: We apply one generic monthly loss figure or treat all delayed revenue as permanently lost.
- C — 2: Buyer-confirmed scenarios separate incremental cash expenditure, financing cash flows, deferred contribution and potentially unrecoverable losses.
- D — 3: C, plus finance has reviewed liquidity, covenant implications, customer remedies and executable alternatives, with escalation thresholds approved.
Evidence to attach: Base, delay and slower-ramp cases, plus a fallback decision tree.
Modelling discipline: Identify costs already included in the base case before adding delay exposure. Keep debt principal, interest, depreciation and operating expenditure distinct; do not count the same obligation twice. These are this quiz’s proposed modelling controls, not a forecast of losses.
Source context: CoreWeave discloses both capacity-mismatch exposure and development-delay risks, supporting the need for buyer-specific scenarios rather than a single industry loss figure. (sec.gov)
15. Will the evidence still be valid when you sign or pay?
Score change control and accountability.
- A — 0: Evidence sits in emails; nobody owns revalidation.
- B — 1: We have a data room but no consistent dates, conditions or refresh triggers.
- C — 2: Material claims have sources, dates, owners and statuses: document-supported, conditional, conflicting or not established.
- D — 3: C, plus a named reviewer reconfirms decision-critical evidence before commitment and escalates changes to dates, capacity, tariffs, approvals or counterparties.
Evidence to attach: The evidence register and latest change memo. Record adviser scope and any supplier or referral remuneration separately.
Why this matters: ERCOT’s 8 July 2026 notice ended further reviews and approvals under its then-existing LLIS process after 10 July 2026 as it moved into Batch Zero. An older process description is therefore not enough to establish a project’s current position. (ercot.com)
What does your score mean?
Add the 15 answers. Maximum: 45 points. Apply the overrides below before acting on the band.
| Score | Evidence-readiness band | What it means | Recommended next step |
|---|---|---|---|
| 0–14 | Define before committing | The requirement or supporting evidence is too incomplete for this framework to support an irreversible commitment. | Produce the load-and-date brief and identify the serving utility or operator. Limit activity to explicitly authorised investigation. |
| 15–26 | Build the evidence pack | There is a plausible proposition, but material questions remain unanswered or supported mainly by preliminary documents. | Issue a targeted request for information. Prioritise power, rights, permissions and the delivery sequence before broad market comparisons. |
| 27–35 | Resolve dependencies | Much of the decision is documented, but unresolved interfaces, commercial terms or downside assumptions still need review. | Hold a cross-functional dependency review and assign closure evidence, owners and deadlines. Use conditional commitments only after professional review. |
| 36–45 | Prepare for final commitment review | The evidence pack is comparatively mature under this quiz—not a guarantee of feasibility or delivery. | Revalidate critical documents, resolve overrides and present the residual-risk decision to the authorised committee. |
The bands are deliberately not percentages of construction completion. A well-documented early-stage project and an operating facility are at different physical stages even if both have evidence appropriate to their next decision.
When must a blocker override a high score?
Always preserve the distinction between a known blocker and missing proof. Under this framework, either can prevent support for the next irreversible commitment, but they require different responses.
Apply these rules in order:
- Known blocker: An expired necessary right, refusal of an essential permission, incompatible technical requirement, or evidenced delivery date beyond an immovable deadline takes precedence over the score. Mark “Hold—known blocker” until resolved or the decision is changed.
- Critical evidence gap: Any answer of 0 or 1 on Questions 2–14 produces “Hold—critical evidence incomplete” for an irreversible commitment dependent on that issue.
- Undefined mandate: A score below 2 on Question 1 produces “Define the decision first”, even if a supplier has a strong evidence pack.
- Weak change control: A score below 2 on Question 15 prevents the top-band label from being treated as current at signing. Revalidate first.
- No override: Use the numerical band to prioritise the next review; final approval remains with the buyer’s authorised decision-makers and advisers.
A hold does not mean abandon the project. A bounded study payment, refundable reservation or negotiated option extension may be a different decision from a land acquisition or non-cancellable capacity contract. Assess that revised decision explicitly rather than silently waiving the gap.
How should the six delivery gates be displayed?
Use four statuses: Supported for this decision; Conditional; Not established; Blocked. Do not average them.
| Delivery gate | Main questions | Evidence focus |
|---|---|---|
| Land control | 4 | Rights, expiry, access and relevant easements |
| Planning and permits | 5, 7 | Applicable permissions and operating authorisations |
| Utility arrangements | 2, 3, 7 | Capacity, service terms, restrictions and obligations |
| Network works | 6 | Infrastructure scope, owners and dependencies |
| Equipment and facility systems | 8, 9, 10 | Electrical, physical, cooling and connectivity compatibility |
| Commissioning | 11 | Integrated testing, acceptance and operational handover |
Keep Questions 1 and 12–15 visible as separate mandate, economics, contract and governance controls.
Illustrative result: Fourteen answers worth 3 points and a 0 on utility evidence produce 42/45. The correct output is “42/45; utility arrangements not established; hold the dependent irreversible commitment”—not “ready to proceed”.
What should you do with your weakest answers?
Commission the smallest piece of work that can resolve the decision-critical uncertainty. These are suggested deliverables, not claims that a live automated tool has verified your project.
| Weakest area | Suggested follow-up deliverable | Appropriate lead |
|---|---|---|
| Questions 2–3 | Power Claim Reality Check: claim-to-document comparison and utility questions | Development and energy leads |
| Questions 4–6 | Site Commitment Gatecard: rights, permissions and network dependencies | Development, counsel and engineers |
| Question 7 | Service-condition and bridge-power review | Energy, environmental and technical advisers |
| Questions 8–10 | Equipment, Liquid-Ready and Connectivity Evidence Audit | Infrastructure and facilities leads |
| Question 11 | GPU-to-Power Deadline Test: dependencies, float and acceptance ownership | Programme manager and commissioning lead |
| Questions 12–13 | True Cost of Power model and Critical IT MW Offer Normaliser | Energy procurement, finance and counsel |
| Question 14 | Delay, slow-ramp and fallback scenarios | Finance and commercial leadership |
| Question 15 | Investment Committee Change Memo | Decision owner and diligence coordinator |
What should your result sheet contain?
Copy this structure into the approval pack:
- Decision being assessed:
- Site, building and phase:
- Required critical IT MW and usable-compute date:
- Evidence score and band:
- Override status:
- Six separate gate statuses:
- Three most consequential unresolved items:
- Closure document, owner and deadline for each:
- Exposure if the next payment is made before closure:
- Evidence revalidation date:
- Authorised next action:
For a focused research review, start with the decision brief and a redacted document index. Agree confidentiality, permitted use and handling arrangements before sharing commercially sensitive agreements.
The useful outcome is not a higher score. It is a clearer answer to one question: what evidence must change before this particular commitment becomes supportable?
What are the limits of this assessment?
Public utility guidance and technical documentation can establish what to investigate; they cannot confirm private capacity allocations, parcel rights, confidential service conditions or supplier delivery commitments. This document makes no site-availability claim and offers no universal connection timeline or cost-of-delay estimate.
The research process included utility and regulator material, manufacturer documentation, operator filings, industry coverage, recruitment evidence, YouTube and podcasts. Supplier media were used for context, not as proof of capacity: for example, Schneider Electric’s June 2026 podcast discusses coordinated power-and-cooling planning, while its October 2025 video describes its cooling portfolio. Neither establishes readiness at a buyer’s site. (blog.se.com)
Sources
URLs below identify the public evidence used. Dated examples are illustrative; check the controlling documents applicable to your project before commitment.
- Dominion Energy — Data Center Requests: preliminary power plans, will-serve letters and connection dependencies. `https://www.dominionenergy.com/virginia/large-business-services/data-center-requests
- AEP Ohio — Data Center Tariff: property control, service agreements, estimated energisation, billing demand and commercial obligations. `https://www.aepohio.com/company/about/rates/data-center-tariff/
- US Department of Energy — Best Practices Guide for Energy-Efficient Data Center Design, July 2024: PUE definition and measurement basis. `https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf
- Core Scientific — Form 10-K for the year ended 31 December 2025: separate utility and customer IT capacity definitions. `https://www.sec.gov/Archives/edgar/data/1839341/000162828026013305/core-20251231.htm
- Loudoun County — Data Center Standards and Locations, Phase 1: March 2025 amendments and grandfathering. `https://www.loudoun.gov/6221/Phase-1-Project-Plan-for-Data-Center-Sta
- TCEQ — Air Quality Standard Permit for Electric Generating Units: authorisation screening and conditions. `https://www.tceq.texas.gov/permitting/air/newsourcereview/combustion/egu_sp.html
- FERC — Commissioner Chang’s concurrence, 18 June 2026: scope of regional large-load proceedings and service questions. `https://ferc.gov/news-events/news/e-11-commissioner-changs-concurrence-iso-new-england-inc-docket-no-el26-72-000
- NVIDIA — DGX SuperPOD Data Center Design, DGX H100: electrical provisioning, physical deployment and coordination. `https://docs.nvidia.com/nvidia-dgx-superpod-data-center-design-dgx-h100.pdf
- Schneider Electric — CDU rating conditions and filtration, 16 December 2025: cooling-interface and rating considerations. `https://blog.se.com/datacenter/2025/12/16/account-for-filtering-too-beware-of-how-cdu-rating-capacity-is-specified/
- NVIDIA — DGX GB200 SuperPOD reference architecture: hybrid cooling, networking and storage scope. `https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html
- Amazon Jobs — Commissioning Engineer, Job ID 10575904: first-party description of factory, functional and integrated testing responsibilities. `https://amazon.jobs/en/jobs/10575904/commissioning-engineer
- NVIDIA — DGX SuperPOD FAQ: delivery, installation, testing and operational handover. `https://docs.nvidia.com/dgx-superpod/faq/latest/dgx-superpod.html
- CoreWeave — Form 10-K for the year ended 31 December 2025: fixed-capacity leases, capacity mismatch and development risks. `https://www.sec.gov/Archives/edgar/data/1769628/000176962826000104/crwv-20251231.htm
- ERCOT — Market notice M-B062326-04, 8 July 2026: transition from the prior LLIS process to Batch Zero. `https://www.ercot.com/services/comm/mkt_notices/M-B062326-04
- US EPA — Physical PPA: physical delivery arrangements, used in the FAQ. `https://www.epa.gov/green-power-markets/physical-ppa
- US EPA — Financial PPA: distinction from physical electricity delivery, used in the FAQ. `https://www.epa.gov/green-power-markets/financial-ppa?trk=article-ssr-frontend-pulse_little-text-block
- Schneider Electric — AI Factories: Power, Cooling & Token Economics, 15 June 2026: podcast context; not site evidence. `https://blog.se.com/digital-transformation/artificial-intelligence/2026/06/15/podcast-chris-sharp-steven-carlini-ai-factories-power-cooling-token-economics/
- Schneider Electric — Liquid Cooling Solutions for AI Data Centers, 10 October 2025: official YouTube portfolio overview; not site evidence. `https://www.youtube.com/watch?v=aanhsxw1trA
FAQs
What is a data center power readiness assessment?
In this framework, it is an evidence-based review of whether a particular site, phase and delivery plan support the buyer’s next commitment. It examines six delivery gates alongside requirements, electricity economics, contracts, downside exposure and evidence freshness.
What does a utility will-serve letter guarantee?
Do not infer a guarantee from the document’s title: review its actual capacity, timing, conditions and obligations with the utility and counsel. Dominion describes will-serve letters within its preliminary site-selection assistance, while its connection guidance identifies further infrastructure and approval steps. (dominionenergy.com)
Does a power purchase agreement prove that a site has deliverable power?
Not by itself: EPA distinguishes physical PPAs, which involve physical delivery, from financial PPAs, which do not. The assessment should separately establish the site’s connection, service capacity, operating conditions and required infrastructure. (epa.gov)
What is the difference between utility service MW and critical IT MW?
Utility service capacity and the capacity available to customer IT equipment use different boundaries; Core Scientific’s reporting explicitly distinguishes them. Require a project-specific reconciliation rather than treating a campus utility figure as deployable IT capacity. (sec.gov)
Can a high readiness score justify proceeding when one delivery gate is unresolved?
No: under this quiz, a known blocker or decision-critical evidence gap overrides the numerical band. A score of 42/45 can still produce a hold if utility arrangements are not established.
How should an AI operator verify that colocation is liquid-ready?
Request an equipment-specific interface review covering coolant, temperatures, flow, pressure, materials, heat rejection, residual air cooling and commissioning ownership. Schneider Electric’s guidance shows why CDU rating conditions matter, while NVIDIA’s GB200 architecture illustrates that liquid-cooled compute can still require air cooling. (blog.se.com)
How should minimum demand charges be treated in a data center electricity cost model?
Model them according to the applicable tariff’s billing-demand formula, separately from metered energy consumption. AEP Ohio’s published DCT information includes both historical-demand and contract-capacity tests, illustrating why a headline energy rate cannot establish the full obligation. (aepohio.com)
Can developers use this quiz before construction or commissioning is complete?
Yes: assess evidence appropriate to the specific commitment, such as land acquisition or a controlled study payment, rather than pretending the facility is operational. A later GPU-installation or customer-activation decision requires a new assessment and the physical completion or acceptance evidence relevant to that stage.
How often should the readiness assessment be refreshed?
This framework recommends revalidation before every material irreversible commitment and whenever a decision-critical assumption changes. Relevant triggers include revised utility milestones, approvals, equipment dates, rack configurations, tariffs, contract terms and customer deadlines.
Sources
- core-20251231
- Data Center Requests | Virginia | Dominion Energy
- Data Center Tariff
- Phase 1: Project Plan for Data Center Standards & Locations | Loudoun County, VA - Official Website
- Air Quality Standard Permit for Electric Generating Units - Texas Commission on Environmental Quality - www.tceq.texas.gov
- https://docs.nvidia.com/nvidia-dgx-superpod-data-center-design-dgx-h100.pdf
- Understand CDU rating capacity and account for filtering too! - Schneider Electric Blog
- DGX SuperPOD Architecture — NVIDIA DGX SuperPOD: Next Generation Scalable Infrastructure for AI Leadership Reference Architecture Featuring NVDIA DGX GB200
- Commissioning Engineer - Job ID: 10575904 | Amazon.jobs
- crwv-20251231
- Market Notice Details
- [Podcast] AI Factories: Power, Cooling & Token Economics - Schneider Electric Blog
- Physical PPA | US EPA
- https://www.dominionenergy.com/virginia/large-business-services/data-center-requests
- https://www.aepohio.com/company/about/rates/data-center-tariff/
- https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf
- https://www.sec.gov/Archives/edgar/data/1839341/000162828026013305/core-20251231.htm
- https://www.loudoun.gov/6221/Phase-1-Project-Plan-for-Data-Center-Sta
- https://www.tceq.texas.gov/permitting/air/newsourcereview/combustion/egu_sp.html
- https://ferc.gov/news-events/news/e-11-commissioner-changs-concurrence-iso-new-england-inc-docket-no-el26-72-000
- https://docs.nvidia.com/nvidia-dgx-superpod-data-center-design-dgx-h100.pdf
- https://blog.se.com/datacenter/2025/12/16/account-for-filtering-too-beware-of-how-cdu-rating-capacity-is-specified/
- https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html
- https://amazon.jobs/en/jobs/10575904/commissioning-engineer
- https://docs.nvidia.com/dgx-superpod/faq/latest/dgx-superpod.html
- https://www.sec.gov/Archives/edgar/data/1769628/000176962826000104/crwv-20251231.htm
- https://www.ercot.com/services/comm/mkt_notices/M-B062326-04
- https://www.epa.gov/green-power-markets/physical-ppa
- https://www.epa.gov/green-power-markets/financial-ppa?trk=article-ssr-frontend-pulse_little-text-block
- https://blog.se.com/digital-transformation/artificial-intelligence/2026/06/15/podcast-chris-sharp-steven-carlini-ai-factories-power-cooling-token-economics/
- https://www.youtube.com/watch?v=aanhsxw1trA