No universal, immediately available connection entitlement was established by the material reviewed. On 18 June 2026, FERC issued tailored section 206 show-cause orders to PJM, MISO, SPP, CAISO, ISO New England and NYISO. The orders required the operators and transmission owners to justify existing arrangements or propose changes, with initial 30-day information-report and 60-day tariff-response requirements. Those initial response periods are already past. (ferc.gov)
The subjects include transmission studies, cost shifting, co-location, flexible-load service and generation serving nearby loads. Buyers must now examine the relevant regional responses and subsequent orders—not continue treating the June announcement as the latest operative tariff. (ferc.gov)
FERC’s 9 October 2026 Duke concurrence also expressly described the broader DOE large-load ANOPR as still pending. It should not be confused with a completed nationwide final rule. (ferc.gov)
Recommended action: identify three separate documents in every power evidence pack:
- The applicable retail service arrangement.
- The transmission service and cost-recovery arrangement.
- The site-specific study and construction conditions.
For co-location, obtain the permitted import configuration, responsibility during a generator outage and the actual transmission product. FERC issued a further PJM co-location rehearing and compliance order on 18 June 2026; relying only on the December 2025 announcement is therefore insufficient. This pass did not fully verify the subsequent operative PJM tariff revisions. (ferc.gov)