| Date | Event or milestone | How to use it |
|---|---|---|
| 12 October 2026 — passed | Response deadline for ERCOT’s specified State and Community Impact RFI | Check submission evidence and unresolved questions; do not assume a late response has been accepted. (ercot.com) |
| 19 October 2026 | TCEQ update due to the governor under the September directive | Request the update and implementation position; this is not an automatic permit-restart date. (gov.texas.gov) |
| 16 November 2026 — upcoming | Scheduled effective date of EPA’s partial carbon-standard repeal | Recheck applicability and any intervening legal action before reliance. (govinfo.gov) |
| 10 December 2026 — expected | ERCOT’s stated target for its State and Community Impact report | Treat as an expected report milestone, not project clearance. (ercot.com) |
| 1 January 2027 — upcoming | Dominion contract-date trigger for specified new-customer obligations | Confirm execution-date and customer applicability before signing. (scc.virginia.gov) |
| February 2027 — anticipated | Loudoun Phase 2 Planning Commission consideration | Monitor the schedule and draft changes; do not assume adoption. (loudoun.gov) |
NERC adoption and approval, the North Carolina retail settlement and regional FERC implementation should remain event-triggered monitoring items until their relevant orders and implementation dates are verified.
Sources & research context
Research snapshot: 2026-10-19. Sources and limitations are retained as supplied.
Read the complete report and source register →