Complete source research · 2026-10-16

Scorecard The complete report.

Every substantive section, table, FAQ and source. Commissioning credits removed.

Download full research

Which supplier or plan deserves the next commitment?

Choose the option that can substantiate the required critical IT capacity, operating conditions, full payment obligations and activation date—not the option with the largest advertised campus or lowest headline electricity price.

This scorecard combines six non-negotiable commitment gates with a 100-point weighted comparison. The gates determine whether an option can proceed to a particular decision. The weighted score helps compare options that survive those gates. A high score never overrides a blocker.

Load & Date Research.
Research cut-off: 16 October 2026.
Intended buyers: independent developers evaluating 20–100 MW phased projects and AI operators procuring 5–30 MW of high-density colocation. These are assessment scopes, not claims about available inventory.

Methodology status: The weights, scoring anchors, evidence caps and decision thresholds below are proposed desk methodology. They are not an industry standard, statistically calibrated default model, engineering certification or investment recommendation. No actual supplier is rated here, and no site-specific availability has been verified.

What should the finished assessment say?

For [named phase and workload], [supplier/site] scores [X/100] for [specified commitment]. Gate status is [clear/conditional/blocked/not established]. The principal unresolved dependency is [item]. Do not release [payment or hardware commitment] until [evidence or condition] is satisfied.

Use this for a complete site or facility delivery package. Do not compare a utility, a cooling manufacturer and a colocation operator as though they sell the same outcome. For a component supplier, assess its work package separately and retain the unresolved interfaces on the overall project scorecard.

1. What exactly are you buying?

Freeze the requirement before opening supplier scores. Otherwise, an offer can appear superior merely because it assumes a smaller load, later date or weaker operating obligation.

Complete this buyer brief:

Required field What to record
Decision under review Option extension, land acquisition, utility commitment, construction release, colocation contract or GPU shipment
Financial exposure Payment due now; refundable amount; cancellation exposure; later obligations triggered
Capacity Required critical IT MW by phase; maximum simultaneous load; other IT and facility loads
Hardware Exact rack/system configuration, rack count, electrical interfaces and cooling requirements
Dates Site access, energisation, facility acceptance, hardware installation and customer activation
Service conditions Permitted curtailment, maintenance interruptions, power caps and recovery requirements
Connectivity Carriers, route requirements, bandwidth, latency and installation responsibilities
Commercial limits Monthly cash ceiling, upfront funding limit, collateral capacity and acceptable downside
Accountability Buyer decision owner, technical approver, energy lead and legal reviewer

How should utility service MW and critical IT MW be normalised?

Use separate fields rather than one ambiguous “power available” number:

  • Utility service MW: the import capacity and conditions supported by the service arrangement at the specified delivery point.
  • Critical IT MW: the capacity available to the buyer’s IT equipment at the agreed electrical boundary and operating configuration.
  • Buyer-allocable MW: the portion assigned to this buyer after other contractual allocations and shared infrastructure constraints are reconciled.
  • Campus potential: expansion ambition; exclude it from committed capacity unless the relevant phase passes its own checks.

Record these as the scorecard’s working definitions and reconcile them with the actual contracts.

DOE defines power usage effectiveness, or PUE, as facility energy divided by IT energy and distinguishes infrastructure efficiency from overall computing efficiency. Consequently, this methodology does not accept annual PUE as sufficient proof of firm IT capacity or peak electrical capability. Require an engineer’s capacity reconciliation at the required operating conditions instead. (energy.gov)

For each phase, request a capacity bridge showing utility imports, any dependable on-site supply, facility auxiliaries, electrical losses, reserve arrangements, cooling limits and existing customer allocations. Do not add redundant equipment ratings together as if all of that capacity were simultaneously sellable.

2. Which conditions must pass before the weighted score matters?

Assess six gates separately. Never publish their average as a readiness percentage.

The table is a proposed evidence checklist, not a national permitting pathway.

Gate Evidence to request What a satisfactory position looks like What should stop or condition the commitment
G1. Land and access Title/lease/option documents; permitted use; access, utility and fibre easements; relevant assignments Rights cover the intended phase, delivery routes and commitment period Expiring control, missing rights or a proposed assignment that has not been accepted
G2. Planning and permits Jurisdiction-specific permission register; approval documents; conditions; appeal status; water, air, noise and fire requirements where applicable Required permissions for the next activity are established; later approvals have identified owners and credible paths A required approval is refused, incompatible with the design, or unsupported at the commitment stage
G3. Utility arrangements Site-specific correspondence, studies, agreements, delivery point, capacity schedule, service conditions and payment requirements The buyer can distinguish requested, studied, contracted and energised capacity A marketing claim, preliminary letter or supply contract is being substituted for the required service evidence
G4. Network works Utility/network scope; dependencies; rights of way; funding; procurement; construction and energisation milestones Every material upstream work package has a responsible party, evidenced status and dated dependency Unresolved transmission works, equipment allocation or approval assumptions underpin the promised date
G5. Equipment and facility systems Electrical and cooling design; equipment orders; allocation records; water and fibre arrangements; interface matrix The specified racks can be supported at the required density and resilience, with delivery responsibilities assigned Unsupported “liquid-ready” claims, unavailable components or an unowned integration task
G6. Commissioning and acceptance Test strategy, scripts, resource bookings, witness rights, acceptance criteria and eventual results The next-stage commitment is supported by an executable acceptance plan; activation is supported by completed tests Energisation or building completion is being treated as proof of usable compute

Assign one of four statuses to each gate:

  • Clear for this decision: evidence meets the requirement for the specific release of money or equipment.
  • Conditional: a defined cure remains; specify its owner, deadline, cost and contractual hold point.
  • Blocked: evidence identifies an incompatibility or dependency that defeats the requirement without a material change.
  • Not established: evidence is missing, stale or contradictory. This means insufficient proof—not necessarily unavailable capacity.

How should the gates change with project stage?

A development plan should not fail merely because it has not yet been built. Equally, a construction plan cannot substantiate a claim that capacity is ready to operate.

Commitment stage Recommended gate standard
Bounded feasibility or option expenditure Identified uncertainties, access to investigate them, capped exposure and a credible route to resolve them
Irreversible land, utility, construction or lease commitment Stage-relevant rights and agreements established; future conditions explicitly allocated, funded and protected by hold points or accepted risk limits
Hardware mobilisation or operational activation Required physical capacity, permissions, integration and tests completed for that release; documented acceptance of any limited residual items

A future commissioning plan may therefore be satisfactory for a construction decision, but it is not a substitute for commissioning results at activation.

Additional vetoes: failure to meet a mandatory capacity, deadline, resilience, security or funding constraint overrides the total score. Put buyer-specific non-negotiables on the cover sheet before scoring.

3. What weights should buyers use?

Use the development profile for site and build decisions; use the AI operator profile for near-term high-density colocation procurement. Both total 100 points.

Criterion Developer weight AI operator weight Primary accountable reviewer
1. Utility service and capacity entitlement 20 18 Energy lead and counsel
2. Network works and energisation deliverability 16 12 Utility interface lead and electrical engineer
3. Land, permissions and site constraints 12 5 Development lead and local specialists
4. Electrical, cooling and connectivity compatibility 10 18 Infrastructure engineering lead
5. Equipment delivery and time to compute 12 15 Integrated programme owner
6. Full costs and ramp economics 14 14 Energy procurement and finance
7. Contractual allocation of delivery risk 7 8 Commercial lead and counsel
8. Commissioning and operational readiness 5 6 Commissioning authority and operations
9. Counterparty execution and financial capacity 3 3 Procurement and finance
10. Evidence governance and change control 1 1 Diligence owner
Total 100 100

These weights reflect the desk’s proposed priorities, not measured failure frequencies. Commissioning and permissions remain mandatory gates even where their comparative weight is modest.

Freeze weights before evaluating offers. If the buyer changes the brief, rescore every option. Do not remove difficult criteria or redistribute missing-evidence weights to improve an option’s total.

4. How should each criterion be scored?

Score the evidenced position, not the supplier’s confidence. Use integer ratings from zero to five, then cap them by evidence quality.

Performance rating

Rating Meaning
0 Demonstrated failure, or no usable evidence. Label these differently: F for failed and NE for not established.
1 Material weakness; predominantly an assertion or an unowned dependency
2 Partial solution; important scope, funding, timing or acceptance gaps remain
3 Credible solution with identified, costed conditions and accountable owners
4 Meets the stage-specific requirement with executable evidence and limited residual issues
5 Meets the requirement and has been independently challenged against relevant downside conditions, with acceptable controls and contingency

Award the highest anchor whose material requirements are all satisfied. Do not average away a failed critical subtest inside a criterion. Record non-critical exceptions separately.

Evidence cap

Evidence grade Maximum rating Required support
E0 0 No usable evidence, or a material contradiction remains unresolved
E1 1 Marketing, verbal assurance or an unverified supplier representation
E2 3 Traceable, site-specific study, design or conditional document; material execution conditions remain
E3 4 Applicable executed agreement, issued approval, acknowledged order or stage-appropriate acceptance record
E4 5 E3-quality evidence plus independent reconciliation, current confirmation and relevant downside validation

Apply the cap to the material claim, not merely to the document’s title. An executed agreement may prove an obligation while leaving the delivery date conditional. A test report for another hall does not prove this hall’s readiness.

Calculation

Effective rating = minimum(performance rating, evidence cap)

Weighted points = criterion weight × effective rating ÷ 5

Total score = sum of weighted points

Also report evidence coverage: the sum of weights supported by E3 or E4 evidence. This is a documentation measure, not a probability of completion or a readiness percentage.

Suggested decision thresholds

Result Recommended action
80–100, all relevant gates clear, and criteria 1–6 each at least 3 Eligible for approval of the specified next commitment, subject to the buyer’s authorised reviewers
65–79, without a blocker Conditional shortlist; close gaps, renegotiate or authorise only bounded further diligence
Below 65 Hold, redesign or seek alternatives
Any blocked/not-established mandatory gate, regardless of score Hold the affected commitment; define the evidence or redesign needed

These thresholds are governance recommendations. They do not establish financeability, creditworthiness or guaranteed delivery.

5. What do good and bad look like for each criterion?

The following anchors are desk-designed scoring rules. Apply them at the project’s actual stage.

Criterion Weak: 0–1 Adequate: 3 Strong: 5 Minimum evidence pack
1. Service and entitlement “Power secured” without the relevant service terms; requested and allocated MW confused Site and phase identified; service scope documented; remaining conditions explicit Applicable rights, capacity allocations and operating restrictions independently reconciled; no material entitlement ambiguity Agreements, studies, load schedule, delivery-point diagram, allocation register
2. Network delivery Date depends on unspecified upstream work or generic equipment lead times Network scope, owners and milestone dependencies identified; some contingencies remain Critical work status confirmed with responsible parties; procurement, rights and approvals evidenced; delay response evaluated Utility schedule, work packages, approvals, order acknowledgements, progress evidence
3. Site and permissions Land rights, intended use or a required permission unsupported Site-specific diligence complete enough to identify approval conditions and mitigation costs Stage-required rights and permissions confirmed; environmental, water and physical constraints independently challenged Rights schedule, permit register, specialist reports, authority correspondence
4. Technical compatibility Campus-average density or “liquid-ready” label substitutes for rack-level proof Engineering design matches the proposed systems, with documented interface exceptions End-to-end compatibility validated at required load and operating conditions, including degraded modes where required Single-lines, rack layout, cooling calculations, interface specifications, network design
5. Time to compute Delivery date ends at shell completion or energisation Integrated dependency schedule includes fit-out, fibre, installation and acceptance Critical path and resource allocations independently challenged; float, recovery options and late-delivery scenarios evidenced Logic-linked schedule, equipment allocations, installer commitments, responsibility matrix
6. Costs and ramp Energy-only rate presented as the full bill; deposits and minimums omitted Monthly base and downside cases include material tariff and contractual obligations Billing logic independently reconciled; slower ramp, delay, curtailment and exit exposures remain within buyer limits Applicable tariff/riders, contract schedules, model, sample bill or utility calculation
7. Contract protection Payment commencement is detached from acceptance; interface failures have no owner Scope, milestones, exclusions and remedies documented, with recognised negotiation gaps Obligations align across contracts; acceptance, change control, security and remedies are executable and commercially acceptable Draft/final contracts, scope matrix, guarantee/security documents, counsel issues list
8. Acceptance and operations Certificate, brand or equipment startup substituted for integrated acceptance Stage-appropriate test plan, staffing and handover scope agreed Relevant acceptance evidence and operational capability independently verified; critical defects closed or explicitly controlled Test scripts/results, defect log, operating procedures, training and maintenance records
9. Counterparty capacity Project depends on uncommitted funding, unnamed subcontractors or unverifiable references Delivery team, funding route and relevant references identified Project-specific resources and funding substantiated; comparable delivery references checked; substitution/failure plan evaluated Financial evidence, project funding, organisation chart, subcontractor and reference checks
10. Evidence governance Dates conflict; no version owner; material changes disclosed informally Controlled document register and regular updates Traceable changes automatically trigger reassessment of affected gates, costs and dates Evidence register, decision log, notification obligations, conflict disclosures

Where should overlapping risks be scored?

Keep the assessment boundaries explicit:

  • Criterion 1 scores service rights and conditions; criterion 2 scores physical network delivery.
  • Criterion 4 scores technical capability; criterion 5 scores delivery sequencing; criterion 8 scores acceptance and operation.
  • Criterion 6 scores economic exposure; criterion 7 scores who contractually bears it.
  • Criterion 10 scores the change-control process, not a second generic penalty for documents already capped elsewhere.

One event can affect several outcomes, but the economic model must not count the same cash exposure twice.

6. How do you verify a data center power availability claim?

Trace the claim from the named delivery point to the named phase, then identify every condition between that evidence and operation.

Dominion’s public data-centre process separates preliminary site evaluation from infrastructure design, rights of way, permitting, material procurement, regulatory filings and construction. Its site-selection assistance can include a will-serve letter. This supports treating that letter as one document in a delivery chain—not as a universal statement that all later dependencies are complete. (dominionenergy.com)

Ask the supplier and serving utility:

  1. Which legal entity holds the service rights, and can the proposed buyer rely on or receive those rights?
  2. What is requested, studied, contracted, currently energised and already allocated elsewhere?
  3. Which date is an estimate, which is a contractual milestone, and what conditions qualify each?
  4. Which upstream works remain, who funds them, and what evidence supports their dates?
  5. What operating limits apply: import cap, curtailment, ramp limits, backup arrangements or phased service?
  6. What changes to hardware, load behaviour or phase size require renewed review?

NERC’s July 2025 large-load white paper identifies issues including load behaviour, ride-through, power quality, stability and observability. The buyer implication is to request the load model and operating assumptions used for the project’s studies, rather than relying solely on a static MW figure. (nerc.com)

Does a PPA establish physical service?

Not by itself. EPA distinguishes physical PPAs, which involve electricity delivery, from financial PPAs, which do not. This scorecard therefore evaluates energy procurement separately from evidence that the specific site, connection and facilities can support the buyer’s load. (epa.gov)

Do not score a credible PPA as worthless. Score it for what it establishes—then request the separate delivery evidence.

Does bridge power remove the grid dependency?

Treat it as an additional delivery plan, not an automatic cure. Require a separate review of fuel, equipment, operating permissions, emissions, maintenance, redundancy, grid interaction and transition to permanent service.

EPA’s data-centre resources distinguish applicable stationary-engine requirements and specific emergency-operation treatment. Do not assume permissions for emergency backup generation authorise the proposed routine bridge-power duty. Obtain a project-specific determination from the relevant environmental specialists and permitting authority. (epa.gov)

7. How should full electricity and colocation costs be scored?

Score the monthly payment obligation under the buyer’s ramp—not the advertised cents per kWh. Berkeley Lab’s August 2026 research examines large-load tariff structures and service agreements as mechanisms for managing operational and financial risks, including underutilised investment. It provides context, not a substitute for the tariff and contract applicable to a particular site. (eta.lbl.gov)

Build four separate schedules

Schedule Include Avoid
Recurring operating charges Capacity rent, energy, applicable demand charges, riders, taxes, support and connectivity Adding utility costs again when already included in the operator’s price
One-off expenditure Fit-out, connection contributions, integration, testing and mobilisation Treating a non-refundable contribution as recoverable security
Liquidity and security Deposits, collateral, letters of credit, release conditions and financing costs Treating posted collateral principal as an ordinary operating expense
Contingent liabilities Exit obligations, delay payments, unamortised infrastructure and restoration costs Assuming every contingency is both certain and immediately payable

For an all-grid-supplied model with consistent measurement boundaries:

IT energy, MWh = average IT MW × hours in the month

Facility energy, MWh = IT energy × modelled monthly PUE

Use separate energy balances where on-site generation, storage, exports or shared meters apply. Do not derive billing peak demand from monthly energy consumption.

Construct each bill from its actual charging rules. Different demand components may use different measured peaks, ratchets or contract floors; minimum-charge provisions must be applied to the appropriate components rather than stacked indiscriminately.

What does an actual minimum-demand provision illustrate?

AEP Ohio’s public DCT summary describes a contract-capacity minimum and an 11-month billing-demand ratchet. For the 25,001–75,000 kW band, the stated contract-capacity floor is 15,000 kW plus 85% of capacity above 25,000 kW. A 50,000 kW assumption therefore produces 36,250 kW before considering other applicable billing provisions. This is not a claim that every data centre pays for 85% of its contracted energy. (aepohio.com)

That calculation illustrates the published summary, not a customer bill. Confirm applicability, aggregation, ramp provisions, current tariff sheets and negotiated terms with the utility and the buyer’s energy adviser.

Which scenarios are mandatory in this methodology?

Model at least:

  • The buyer’s expected commissioning and utilisation ramp.
  • Later activation with original payment commencement dates.
  • Slower utilisation after activation.
  • A smaller first phase with unchanged minimum commitments.
  • Applicable curtailment or import restrictions.
  • Exit or cancellation at the next major decision point.

Report recurring cost per reserved IT kW-month, electricity cost per metered MWh, total monthly cash requirements and the maximum contingent exposure. If IT consumption is zero, report the consumption-based unit metric as not meaningful—not as zero cost.

How should delay exposure be presented?

Separate cash paid before production from incremental cost and deferred contribution.

Illustration only: reserving 10,000 kW at an assumed $150/kW-month for six months before productive use creates $9 million of pre-productive capacity rent if billing continues throughout. This is not automatically $9 million of incremental lifetime loss; the answer depends on commencement, term extension, recovery and utilisation assumptions.

Show hardware storage, financing, duplicate facilities and customer remedies separately. Model deferred contribution using buyer-confirmed margins and recovery assumptions. Do not add all delayed revenue to cash costs as though every delayed sale were permanently lost.

8. What evidence makes a facility genuinely liquid-ready?

Require a configuration-specific compatibility matrix, not a cooling label. NVIDIA’s DGX GB200 SuperPOD architecture explicitly combines liquid and air cooling. A facility assessment for that configuration must therefore address both heat-removal paths. This example should not be generalised into specifications for every AI rack. (docs.nvidia.com)

Use the following proposed procurement matrix:

Interface Buyer evidence requirement
Electrical supply Approved rack power envelope, feeds, protection, connectors, distribution and required failure-mode capability
Liquid circuit Manufacturer-approved coolant, supply/return conditions, flow, pressure, materials, filtration and connection interfaces
Heat rejection Capacity at the relevant design conditions, shared loads and required maintenance/degraded modes
Residual air cooling Non-liquid-cooled rack components, network equipment and other room loads
Controls Leak detection, isolation, alarm routing, shutdown responsibility and IT/operational-technology integration
Physical deployment Filled rack weight, structural review, handling route, clearances, hoses, cable paths and maintenance access
Commercial boundary Who supplies, installs, cleans, fills, tests, operates and warrants each interface

NVIDIA’s Mission Control documentation assigns different leak-detection functions across trays, racks and facility systems and identifies customer-provided building-management-system requirements. This is a concrete reason to make controls ownership part of procurement rather than leaving it to post-delivery integration. (docs.nvidia.com)

OCP’s pre-commissioning guidance addresses technology-cooling-system pipework cleaning, hydrotesting, flushing and preparation. Its stated scope does not include commissioning the CDUs and racks themselves. Request both the pipework preparation records and the additional equipment/system acceptance evidence. (opencompute.org)

Scoring rule: an unresolved interface capable of preventing the intended deployment holds G5. Strong evidence elsewhere in the cooling design cannot compensate for it.

9. How should time to compute and acceptance be tested?

Build the schedule backwards from customer-usable compute, then verify every predecessor and hand-off.

Use an integrated sequence covering:

  1. Utility/network readiness and required permissions.
  2. Facility electrical, cooling and controls completion.
  3. Fibre and external connectivity readiness.
  4. Equipment delivery, handling and installation.
  5. Facility-system testing and defect closure.
  6. Rack, network and software integration.
  7. Workload-specific acceptance and operational handover.

Do not simply add every task duration: some activities can run in parallel, while others cannot. For each activity, record its predecessors, duration basis, owner, evidence, resources, float and recovery option. Unknown durations remain unknown or explicitly scenario-based.

What belongs in acceptance criteria?

The desk recommends buyer-approved criteria for the required load, thermal conditions, interfaces, failover behaviour, alarms, connectivity, defect closure and handover documentation. Technical specialists should define safe procedures and pass/fail values for the actual design.

Uptime distinguishes design-document certification from constructed-facility certification; the latter includes live demonstrations of the installed facility. Its award terms also identify the particular phase or facility scope covered. Verify the certificate’s scope and status rather than treating a campus-level badge as acceptance of the buyer’s deployment. (uptimeinstitute.com)

As a primary-source procurement signal, Anthropic’s published power-and-cooling quality role includes supplier qualification, inspection/test plans, factory acceptance tests and documentation expectations embedded in RFPs and contracts. A job posting establishes those stated responsibilities—not the performance of any particular project or supplier. (job-boards.greenhouse.io)

Recommended contract question: what exact acceptance event starts each payment, and which buyer-caused or supplier-caused exceptions alter that event? Have counsel reconcile this across the facility, hardware, utility and integration agreements.

10. Can a higher-scoring supplier still lose?

Yes. The gates are deliberately stronger than the weighted average.

The following is a wholly fictional comparison for an AI operator seeking 10 MW by 31 March 2027. Ratings are assumed evidence-capped inputs, not assessments of real companies.

Criterion Operator weight Offer A rating Offer B rating
Service entitlement 18 5 4
Network delivery 12 5 4
Site and permissions 5 0 — NE 4
Technical compatibility 18 5 5
Time to compute 15 3 4
Economics 14 5 3
Contract protection 8 5 4
Acceptance and operations 6 4 4
Counterparty capacity 3 4 4
Evidence governance 1 4 4
Weighted total 100 85.0 80.8

Offer A: attractive documented technical and commercial terms, but the hypothetical proposed use lacks required permission evidence. G2 is not established. Hold the affected commitment despite 85 points. Its date assessment also remains conditional.

Offer B: all six gates are assumed clear for the specified contracting decision, not for immediate activation. Economics are less attractive but are assumed to remain within the buyer’s approved limits. Offer B is eligible for the next approval step, with subsequent mobilisation and acceptance gates retained.

The example demonstrates the method’s purpose: a five-point category can still contain a condition that stops the whole decision.

11. What recent developments should trigger revalidation?

Revalidate the project’s applicable process, not merely the date on the last presentation. These are dated developments, not a complete national regulatory update.

Source development What it establishes Scorecard implication
NERC, 15 October 2026 Computational-load standards passed final ballot and were to proceed to Board adoption and subsequent regulatory approval—not yet a statement of fully effective US requirements Ask which existing requirements apply and what emerging requirements could change studies, controls or obligations. (nerc.com)
ERCOT, October 2026 materials The large-load integration page includes Batch Zero verification guidance and distinguishes reference guides from controlling portal RFIs Obtain the project’s actual classification, outstanding conditions and applicable authorisation; do not treat queue inclusion as energisation approval. (ercot.com)
FERC, 18 June 2026 FERC directed six regional grid operators to justify or reform large-load tariff provisions through tailored proceedings Check the relevant subsequent filings and effective rules. The June announcement itself does not establish the tariff applicable to an October transaction. (ferc.gov)

This research did not audit every subsequent regional compliance filing. Project counsel and utility specialists should confirm the rules governing the proposed commitment.

What monitoring cadence should the buyer adopt?

As a proposed desk policy, review critical-path evidence weekly during active delivery, refresh the full scorecard monthly, and reconfirm material facts immediately before each irreversible commitment. Use faster review where circumstances warrant it.

Trigger an immediate reassessment after a change in:

  • Capacity allocation, service classification or curtailment conditions.
  • Utility milestones, equipment allocation or required approval.
  • Rack configuration, cooling design or power envelope.
  • Payment commencement, tariff, collateral or funding.
  • Contractor, responsible counterparty or acceptance criteria.
  • Any assumption supporting the customer activation date.

Preserve the previous assessment. The change memo should state what changed, which gate moved, how the cash or date exposure changed, and who must approve the response.

12. What should go to the investment committee or procurement committee?

Submit a decision sheet backed by an inspectable evidence register—not an unexplained number.

One-page decision sheet

  • [ ] Named supplier, site, phase, workload and commitment.
  • [ ] Utility MW, critical IT MW and buyer allocation shown separately.
  • [ ] Required date and independently assessed dependency schedule.
  • [ ] Six gate statuses, with no blended readiness percentage.
  • [ ] Weighted score, evidence coverage and individual ratings.
  • [ ] Base, delayed and slow-ramp cash requirements.
  • [ ] Upfront, security and contingent obligations separated.
  • [ ] Top unresolved issues, owners, cure dates and hold points.
  • [ ] Technical, energy, legal and commercial reviewer sign-offs.
  • [ ] Specific recommendation: proceed, conditional expenditure, hold or redesign.

Evidence-register fields

Claim ID | criterion/gate | site/phase | supplier assertion | source document and page | issuer | issue/effective date | reviewed date | conditions/expiry | evidence grade | reviewer | unresolved question | next confirmation

Restrict confidential utility, financial and engineering documents to authorised reviewers. Disclose referral remuneration and supplier funding; neither should purchase a higher rating.

Bottom line: use the weighted score to compare documented advantages. Use the gates to decide whether those advantages are relevant to the next commitment. The winning offer is the one whose evidence supports the buyer’s actual load, date and obligations.

Sources

Primary sources below support the factual examples and distinctions. The scoring system and decision rules are the desk’s proposed methodology.

  1. Dominion Energy — Data Center Requests. Site evaluation and connection dependencies. `https://www.dominionenergy.com/virginia/large-business-services/data-center-requests
  2. AEP Ohio — Data Center Tariff. Public process and commercial-term summary; project applicability requires confirmation. `https://www.aepohio.com/company/about/rates/data-center-tariff/
  3. Lawrence Berkeley National Laboratory — Electricity Rate Designs for Large Loads: 2026 Update. August 2026. `https://eta.lbl.gov/publications/electricity-rate-designs-large-0
  4. US Department of Energy — Best Practices Guide for Energy-Efficient Data Center Design. July 2024 edition. `https://www.energy.gov/sites/default/files/2024-07/best-practice-guide-data-center-design.pdf
  5. NVIDIA — DGX SuperPOD Architecture featuring DGX GB200. Updated 19 November 2025. `https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/dgx-superpod-architecture.html
  6. NVIDIA — Mission Control Integration with Building Management System. Version 2.2.0; updated 10 August 2026. `https://docs.nvidia.com/mission-control/docs/nmc-software-installation-guide/2.2.0/integration-of-bms-with-bcm.html
  7. Open Compute Project — Guidelines for Pre-Commission Preparation of Technology Cooling System Row Manifolds. 2025 document. `https://www.opencompute.org/documents/ocp-document-submission-guidelines-for-pre-commission-preparation-of-technology-cooling-system-tcs-row-manifolds-revq-pdf-1
  8. Uptime Institute — Tier Certification of Constructed Facility. `https://uptimeinstitute.com/tier-certification/construction
  9. Uptime Institute — Awards Terms and Conditions. Certification scope and status. `https://atd.uptimeinstitute.com/awards-terms-and-conditions
  10. US EPA — Physical PPA. Physical versus financial electricity procurement. `https://www.epa.gov/green-power-markets/physical-ppa
  11. US EPA — Clean Air Act Resources for Data Centers. Air-permitting and stationary-engine resources. `https://www.epa.gov/stationary-sources-air-pollution/clean-air-act-resources-data-centers
  12. NERC — Characteristics and Risks of Emerging Large Loads. July 2025. `https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-characteristics-and-risks-of-emerging-large-loads.pdf
  13. NERC — Computational Loads Standards Pass Final Ballot. 15 October 2026. `https://www.nerc.com/newsroom/nercs-computational-loads-standards-pass-final-ballot-advance-to-board-adoption
  14. ERCOT — Large Load Integration. Verification, study and energisation documentation. `https://www.ercot.com/services/rq/large-load-integration
  15. FERC — Targeted Action to Speed Large Load Integration. 18 June 2026. `https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration
  16. Anthropic — Manufacturing Quality Engineer, Data Center Power & Cooling. Published recruitment responsibilities; not evidence of project delivery. `https://job-boards.greenhouse.io/anthropic/jobs/5397596008

FAQs

How do I score a data center supplier before signing a contract?

First assess six separate gates: land, permissions, utility arrangements, network works, facility systems and commissioning. Then apply the weighted criteria and evidence caps; under this proposed methodology, a high total cannot override a blocked or unsubstantiated mandatory gate.

What does a utility will-serve letter guarantee?

Its significance depends on its actual wording, conditions and applicable legal framework; the title alone does not establish guaranteed capacity or timing. Dominion lists will-serve letters within site-selection assistance while separately describing design, rights of way, permitting, procurement and construction, so review the letter alongside the remaining delivery evidence. (dominionenergy.com)

Can I convert utility service MW into critical IT MW using PUE?

PUE relates facility energy to IT energy; it does not independently establish the electrical and cooling capability available at peak load or under required failure conditions. Use an engineer-reviewed capacity reconciliation for the specific phase and operating configuration rather than treating annual PUE as a firm-capacity conversion. (energy.gov)

What should a data center electricity cost comparison include?

The proposed scorecard requires recurring charges, one-off contributions, security requirements and contingent liabilities to be modelled separately under the buyer’s monthly ramp. Confirm each tariff’s charging logic: AEP Ohio’s published DCT summary, for example, includes contract-capacity minimum demand and a historical billing-demand ratchet. (aepohio.com)

What evidence should a liquid-ready colocation provider supply?

Request a rack-specific compatibility matrix covering electrical supply, liquid conditions, residual air cooling, heat rejection, controls and installation responsibilities. Also distinguish pipework preparation from equipment commissioning: OCP’s row-manifold pre-commissioning guidance expressly excludes commissioning the CDUs and racks themselves. (opencompute.org)

Does Tier certification prove that my AI deployment is ready?

Check which certification was awarded and which phase or facility it covers. Uptime distinguishes design-document assessment from constructed-facility demonstrations, so the scorecard requires separate evidence for the buyer’s particular hardware, interfaces and acceptance requirements. (uptimeinstitute.com)

Can a lower-scoring supplier be the better choice?

Yes: an option with clear commitment gates can be preferable to a higher-scoring option with a mandatory permission or delivery dependency still unsubstantiated. Compare scores only alongside the gate decision, buyer constraints and evidence quality.

How often should a data center power scorecard be updated?

The proposed desk policy is weekly review of critical-path evidence during active delivery, monthly full rescoring and immediate confirmation before irreversible commitments. A material change to utility timing, permissions, hardware, commercial terms or acceptance requirements should trigger an earlier reassessment.

How should I calculate the cost of delayed GPU activation?

Separate pre-productive cash payments, incremental expenses, financing effects and deferred contribution using buyer-confirmed assumptions. Do not automatically classify all rent paid before activation as additional lifetime loss, or all delayed revenue as permanently lost revenue.