How should a buyer turn this playlist into a diligence pack?

Use each recording to improve a request for evidence. Do not use listening time as evidence of project readiness. The following is our proposed workflow, not a standard claimed by the speakers.

Step 1: Record the claim before researching it

Write the seller’s statement verbatim in your internal file. Examples might be “power secured”, “liquid-ready” or “available in Q3”. Beside it, record what you need that statement to mean for your decision.

Keep three capacity fields separate in the request: utility service MW, critical IT MW and advertised campus potential. Ask the counterparty to define its figure rather than silently translating it.

Step 2: Assign the right episode to the right owner

Workstream owner Suggested listening Evidence request to produce afterwards
Development lead PG&E ACEC Named approvals, remaining conditions, dates and responsible parties
Energy procurement and finance CoBank; Wood Mackenzie Applicable tariff, contract term, ramp treatment, security and exit schedule
Commercial counsel Vinson & Elkins Payment-trigger and dependency-risk matrix
Infrastructure engineering NVIDIA/OCP; OCP chemistry; Castrol Hardware-specific electrical and cooling compatibility pack
Network and deployment leads Oracle/DCD; ICxA Integrated installation, testing and acceptance sequence
Investment committee sponsor Catalyst; CBRE Alternatives, unresolved assumptions and explicit commitment conditions

Step 3: Separate speaker statements from project conclusions

For every material point, create four fields:

  1. What the source says: a short paraphrase with episode date and link.
  2. Why it may matter here: the desk’s project-specific inference.
  3. What would establish it: a document, test, approval or counterparty confirmation.
  4. Who must resolve it, and by when: a named owner and commitment deadline.

This prevents a useful general discussion from becoming an unsupported claim in an investment memorandum.

Step 4: Keep operating and payment milestones separate

For the desk’s proposed GPU-to-Power Deadline Test, use separate lines for utility service, facility access, cooling readiness, network readiness, hardware installation, acceptance and customer activation. Then place contractual billing dates beside them.

Do not insert standard durations from an unrelated project. Ask the responsible delivery party to supply its assumptions and dependencies, and leave unresolved intervals visibly unresolved.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

    Read the complete report and source register →