Comparisons · 2026-10-16

How do AEP Ohio and Dominion’s large-load obligations compare?

Compare payment commitments and ramp exposure before comparing energy prices. The two examples below are not substitutes available to the same parcel, and they do not establish which territory is cheaper.

The distinction matters because large-load tariff design explicitly addresses underused infrastructure and stranded-investment risk. DOE and Lawrence Berkeley National Laboratory identify these issues as central to emerging large-load rate structures. (energy.gov)

Criterion AEP Ohio / Ohio Power DCT Dominion Energy Virginia GS-5 and related provisions
Status and date DCT became effective 23 July 2025. (aepohio.com) Approved in the SCC’s 25 November 2025 ruling; GS-5 takes effect 1 January 2027, after this report’s cut-off. (scc.virginia.gov)
Applicability screen New data-centre loads above 25 MW, subject to expansion and affiliated-load aggregation rules. (aepohio.com) The SCC announcement identifies customers demanding 25 MW or more. Confirm full classification, load-factor and transition criteria from the applicable tariff. (scc.virginia.gov)
Contract duration Ramp period of up to four years, followed by eight years. (aepohio.com) At least 14 years for new large-load customers contracting for service on or after 1 January 2027. (scc.virginia.gov)
Minimum-payment mechanism Graduated contract-capacity minimum demand plus a historical-demand ratchet; do not reduce it to a flat percentage of energy use. (aepohio.com) SCC identifies minimums of 85% of contracted transmission and distribution demand and 60% of generation demand for applicable customers. (scc.virginia.gov)
Credit support Where the specified exemption tests are not met, guarantee or collateral equal to 50% of minimum charges for the full term. (aepohio.com) Customers without sufficient credit may need guarantees covering up to 60% of minimum charges; the SCC identifies applicability to new customers contracting from 1 January 2027. (scc.virginia.gov)
Delivery-date evidence AEP describes its ESA energisation date as a good-faith estimate. (aepohio.com) Obtain the project’s service agreement and works schedule; the cited rate-class announcement does not establish a site delivery date.

Why is the AEP Ohio minimum-demand formula worth checking carefully?

AEP’s published framework includes a contract-capacity floor of 15 MW plus 85% of capacity above 25 MW for the relevant 25–75 MW band. It also includes an 85% historical billing-demand ratchet. (aepohio.com)

Illustrative calculation—not a customer bill: for a fully ramped, standalone 50 MW contract, the contract-capacity component is:

15 MW + 0.85 × (50 − 25) MW = 36.25 MW

It is not simply 50 MW × 85% = 42.5 MW. Actual-demand provisions, the historical ratchet, aggregation and other applicable terms must still be evaluated. The tariff book’s graduated structure is the basis for this calculation. (aepohio.com)

The buyer lesson: minimum billing demand is not the same as a commitment to purchase that percentage of energy in MWh. Ask the utility or energy adviser to reproduce the monthly bill, including each relevant charge, rather than applying a headline percentage to total electricity consumption.

What should Texas buyers revalidate before relying on a power date?

Distinguish the project’s study status, verification status and permission to energise. ERCOT’s 20 August 2026 presentation reported paused energisation approvals for data centres and cryptocurrency facilities of at least 75 MW, while stating that 25–<75 MW medium loads were outside that particular pause. It also explicitly said inclusion in a Quarterly Stability Assessment did not itself authorise energisation. (ercot.com)

ERCOT’s 14 September 2026 notice subsequently required community-impact information from specified unenergised projects, including qualifying 25–<75 MW data centres. The submission deadline was 12 October 2026, which had passed by this report’s cut-off. Submission or expiry of that deadline is not evidence of project approval. (ercot.com)

This review does not establish whether a particular project’s restrictions have been resolved. Require a fresh, project-specific confirmation from the relevant utility and ERCOT process participants before releasing capital against a Texas energisation assumption.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. www.energy.gov
  2. www.aepohio.com
  3. www.scc.virginia.gov
  4. www.aepohio.com
  5. www.scc.virginia.gov
  6. www.ercot.com
  7. www.ercot.com