Build a monthly cash-obligation model, not a single blended cents-per-kWh ranking. Large-load rate design can include minimum-payment, credit-support and infrastructure-cost protections; these deserve separate treatment in the buyer’s model. (eta-publications.lbl.gov)
The following is the desk’s recommended model structure. A line belongs in the comparison only when the applicable proposal, tariff or agreement supports it.
| Cost or obligation | Model treatment | Clarification to request |
|---|---|---|
| Capacity rent | Reserved critical IT kW × applicable monthly charge | Billing commencement, phased reservations, escalators and unused-capacity treatment |
| Metered electricity | Interval or monthly energy under the applicable charging formula | Meter boundary, losses, billing PUE and pass-through mark-ups |
| Demand charges and minimums | Apply each tariff component’s own demand and ratchet rules | Measurement interval, historical lookback and contract-capacity treatment |
| Riders, taxes and credits | Separate, dated line items | Applicable classes, adjustment mechanisms and reconciliation |
| Utility contributions and connection works | One-off cash-flow schedule | Refundability, cancellation exposure and ownership of funded assets |
| Deposits and collateral | Separate liquidity schedule | Cash versus guarantee, release conditions and financing cost |
| Cooling and electrical integration | Priced project scope, with contingency shown explicitly | Boundary between landlord, tenant, OEM and integrator |
| Network and operating services | Recurring and one-off charges | Cross-connects, remote hands, monitoring and support |
| Exit, relocation and restoration | Scenario-dependent cash flows | Early termination, equipment removal and reinstatement requirements |
Do not assume every minimum bill is an additional charge. Where a minimum is already embedded in a demand-charge calculation, adding it again would double-count the obligation. The model should reproduce the agreement’s mechanics, not impose a generic formula.
What assumptions must remain separate?
Use separate inputs for:
- Reserved capacity: what the buyer must pay to hold.
- Installed IT capacity: what has physically been deployed.
- Average IT electrical load: what the equipment consumes over the period.
- Metered peak demand: what the tariff’s measurement method records.
- Compute utilisation: how much useful workload the hardware performs.
Do not derive metered peak demand from average energy consumption. Likewise, do not treat GPU utilisation as a direct substitute for measured IT electrical load. These are modelling controls: obtain the buyer’s actual load assumptions and equipment profiles.
For an energy scenario, a period-appropriate PUE assumption can relate IT energy to facility energy. Because DOE defines PUE using energy quantities, an annual value should not silently become a guaranteed monthly billing factor. (energy.gov)
Can a higher $/kW/month offer cost less during ramp-up?
Yes, under the following explicitly hypothetical assumptions. This example is original arithmetic, not a supplier quote, tariff estimate or market benchmark.
Assume both offers meet the same technical and acceptance requirements, with identical integration costs and electricity treatment. Offer B’s expansion is contractually secured—not merely subject to future availability.
| Assumption or result | Offer A: lower unit price | Offer B: phased reservation |
|---|---|---|
| Capacity price | $170/kW/month | $185/kW/month |
| Reserved capacity, months 1–6 | 10 MW | 5 MW |
| Reserved capacity, months 7–12 | 10 MW | 10 MW |
| Average IT electrical load, months 1–6 | 2.5 MW | 2.5 MW |
| Average IT electrical load, months 7–12 | 7.5 MW | 7.5 MW |
| Annual capacity rent | $20.40m | $16.65m |
| Assumed energy component | $4.38m | $4.38m |
| Rent-plus-energy subtotal | $24.78m | $21.03m |
The energy illustration assumes two equal 4,380-hour periods, a constant PUE of 1.25 and an energy-only rate of $80/MWh:
(2.5 + 7.5) MW × 4,380 hours × 1.25 × $80/MWh = $4.38m
Offer B’s subtotal is $3.75m lower despite its higher unit rent. Before differences in other charges, its rent-only break-even price is approximately $226.67/kW/month: $20.40m ÷ 90,000 reserved kW-months.
This is deliberately not a full bill. It excludes demand charges, taxes, deposits, integration differences, financing and exit costs. Any of those could change the ranking. The example demonstrates the value of modelling reservation timing—not a guaranteed saving.
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.
Read the complete report and source register →