Require every proposal to identify its measurement boundary and delivery status. For this comparison, use the following procurement definitions rather than assuming suppliers use identical terminology.
| Capacity description | Definition to require in the tender | How to treat it |
|---|---|---|
| Advertised campus potential | Ultimate development ambition, with phases and dependencies identified | Exclude from near-term deliverable capacity until supported phase by phase |
| Utility service MW | Import capability or contracted demand at a specified point of connection | Record separately from power available to IT equipment |
| Contracted critical IT MW | Capacity reserved for computing, storage and networking equipment at an agreed electrical boundary | Identify whether it is reserved, installed, commissioned or accepted |
| Commissioned facility capacity | Capacity demonstrated under the agreed electrical and mechanical test programme | Obtain test scope, results and outstanding exceptions |
| Workload-accepted capacity | Capacity that has passed the buyer’s specified hardware, network and workload acceptance tests | Use as the commercial deployment endpoint |
Facility commissioning commonly uses load banks to test power and cooling infrastructure in place of IT equipment. Our inference: passing that test does not, by itself, demonstrate that the buyer’s complete GPU cluster and software environment are ready for customer workloads. (intelligence.uptimeinstitute.com)
Can PUE convert utility MW into usable IT MW?
Only as a clearly qualified screening calculation—not as proof of capacity. The Department of Energy defines power usage effectiveness, or PUE, as total facility energy divided by IT equipment energy. It is an energy-efficiency metric, not a certification of available electrical or cooling capacity. (energy.gov)
For example, an assumed 20 MW facility supply divided by an assumed overhead factor of 1.25 produces a 16 MW screening estimate. That arithmetic does not establish 16 MW of firm, deliverable IT capacity: the buyer still needs the electrical design, cooling capability, operating conditions and acceptance evidence.
Ask suppliers to disclose:
- The boundary at which each MW figure is measured.
- Whether capacity is dedicated, shared, interruptible or subject to another tenant’s ramp.
- Whether quoted electrical paths are redundant support for the same load or additive capacity.
- Supported simultaneous rack loads—not merely the highest density demonstrated in one rack.
- Whether the quoted PUE is measured, modelled or a contractual billing factor.
These are proposed diligence questions, not assumptions about any named facility.