Comparisons · 2026-10-16

Should you build, lease a powered shell, take colocation or buy GPU-cloud capacity?

Choose the scope that removes the dependencies your organisation cannot credibly complete before its deadline. Do not compare a building lease with a compute-service quote without adding the missing hardware, integration and operating responsibilities.

Public supplier descriptions illustrate the distinction. Digital Realty describes build-to-suit arrangements with custom structural, electrical, mechanical and cooling design; its disclosures also distinguish fitted facilities from powered buildings intended for customers able to build and operate their own facility. These descriptions establish procurement categories, not current site availability or suitability. (digitalrealty.com)

The table is an analyst-designed tender framework. Allocate each responsibility explicitly in the contract rather than relying on the category label.

Approach Scope to request Responsibilities the buyer should expect to allocate When it fits What should stop commitment?
Owner-developed greenfield Land, service arrangements, complete facility and operating model Development, utility interfaces, construction, equipment, operations and IT deployment A developer needs design control and has the delivery organisation and funding to execute Unresolved power, permits or equipment dependencies incompatible with the required date
Powered land or powered shell Precisely defined land/building and electrical handover boundary Remaining mechanical and electrical fit-out, cooling, controls, commissioning and operations A buyer can deliver the fit-out and values control over the technical design A seller’s power claim is unsupported, or the remaining scope has no integrated programme
Existing facility retrofit Existing asset plus a priced, engineered conversion scope Structural checks, distribution changes, cooling conversion and interference with existing operations An existing location has useful infrastructure and an acceptable conversion path The retrofit relies on unverified spare cooling, power or structural capacity
Existing fitted colocation Dedicated critical IT capacity, operating services and a defined integration scope Hardware, network and software deployment; cooling interfaces as negotiated The hardware deadline is the primary constraint Facility acceptance does not cover the actual rack configuration or deployment footprint
Build-to-suit or new-build wholesale lease Custom facility delivery with milestones, acceptance tests and operating scope Buyer design decisions, IT deployment and management of contractual interfaces Custom density or resilience is important and the buyer can wait for delivery Rent commencement and remedies do not address the buyer’s material delivery dependencies
GPU cloud or dedicated managed cluster Specified accelerators, topology, storage, networking, software and capacity rights Workload migration, security, performance validation and commitment management The buyer wants compute rather than ownership of the infrastructure stack The offer provides a price but no adequate capacity, topology or performance commitment

Does cloud eliminate capacity-commitment risk?

No: examine the reservation product, not just the hourly price. AWS documents that EC2 Capacity Blocks are purchased for a reserved period and charged upfront, with pricing fixed after purchase. Separately, EC2 Capacity Reservations are billed whether the reserved instances are used or not. These are examples of distinct commercial structures—not a description of every cloud provider. (docs.aws.amazon.com)

For colocation vs GPU cloud, request a workload-equivalent comparison:

  • Same accelerator model, memory and usable cluster topology.
  • Same workload, precision, dataset and performance target.
  • Same storage, networking, support and security scope.
  • Same availability window and treatment of interruptions.
  • Same utilisation scenarios and measurement period.
  • Explicit hardware financing, maintenance and residual-value assumptions for ownership options.

Our recommendation is to compare cost per accepted workload outcome alongside infrastructure cost. A universal GPU-utilisation break-even percentage is not established by the evidence reviewed.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.