What should the final commitment gatecard contain?

Use separate gates; do not average away a blocker. This is the desk’s recommended decision tool.

Gate Minimum question Example of evidence to request
1. Land control Can the buyer legally access and develop the required site? Executed rights, conditions and expiry dates
2. Planning and permits Are the permissions necessary for the selected configuration established? Jurisdiction-specific permit register and status evidence
3. Utility arrangements What service has actually been agreed? Executed arrangements, capacity definition, conditions and applicable tariff
4. Network works Which external works remain on the delivery path? Scope, responsible party, programme and dependencies
5. Equipment and facility systems Can the intended racks operate in the proposed design? Electrical, cooling, structural and connectivity compatibility evidence
6. Commissioning and acceptance What must pass before the buyer regards capacity as usable? Approved test programme, responsibility matrix and acceptance criteria

Classify each material claim as:

  • Document-supported: the document supports the specific claim within its stated scope.
  • Conditional: it depends on an identified event or obligation.
  • Conflicting: material evidence disagrees.
  • Not established: sufficient evidence was not obtained.

Not established does not mean unavailable. It means the comparison cannot yet rely on the claim.

What should go into the final comparison sheet?

For each option, record:

  • Required and offered critical IT MW, by phase.
  • Rack configuration and cooling requirements.
  • Acceptance date and evidence supporting it.
  • Remaining dependencies, owners and latest required completion dates.
  • Monthly recurring costs, upfront expenditure and separate collateral requirements.
  • Base, delayed and slow-ramp scenarios.
  • Cancellation, expansion, assignment and transition rights requiring legal review.
  • Source dates, document versions, assessment dates and next revalidation triggers.

Recommended decision rule: first exclude—or explicitly escalate—options that cannot substantiate the essential technical and delivery requirements. Rank the remaining options by supported economics, contractual flexibility and downside exposure. A low price should not compensate for a missing prerequisite unless the decision-maker knowingly accepts and funds that risk.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.