Start with the hardware’s requirements and the complete heat-removal path. Do not select a cooling category from an advertised rack-density ceiling alone.
NVIDIA’s DGX GB200 SuperPOD reference architecture explicitly describes both direct liquid cooling and air cooling. This is a useful warning against assuming that every liquid-cooled deployment eliminates the need for room air cooling; the exact requirement remains hardware-specific. (docs.nvidia.com)
| Cooling approach | Technical distinction | Suggested procurement fit | Evidence to request |
|---|---|---|---|
| Room or row air cooling | Heat is removed through the IT equipment’s air path | Hardware expressly supported by the proposed air environment | Rack-by-rack thermal assessment, airflow and failure-condition tests |
| Rear-door heat exchanger | A traditional arrangement transfers rack exhaust heat to facility coolant | Retaining suitable air-cooled equipment while adding liquid heat removal | Door/rack compatibility, coolant conditions, airflow effects and room heat balance. (opencompute.org) |
| Direct-to-chip with a facility liquid interface | Cold plates, manifolds, connections and CDUs form a technology cooling system | Hardware designed for direct liquid cooling, with compatible facility infrastructure | The complete interface specification—not merely a CDU nameplate. (opencompute.org) |
| Direct-to-chip with air-assisted heat rejection | Heat from the liquid loop is ultimately discharged to facility air in the described arrangement | A retrofit candidate where the existing air plant can support the verified heat load | Total room heat rejection and available air-system capacity. (opencompute.org) |
| Immersion cooling | Equipment and materials must be compatible with the chosen dielectric-fluid environment | A deliberately selected hardware and operating ecosystem | Material compatibility, service procedures, support and warranty confirmation. (opencompute.org) |
The fit assessments are analyst recommendations. The sources do not establish universal cost, density or deployment-speed rankings across these approaches.
What should a liquid-ready evidence audit contain?
Request a jointly completed compatibility schedule covering:
- Hardware identity: OEM, system configuration and specification revision.
- Electrical envelope: normal operation, relevant transients and agreed rack limits.
- Liquid interface: supply temperature, flow, pressure, fluid chemistry and connector requirements.
- Residual air cooling: the load not captured by the liquid system.
- Heat rejection: performance under the site’s design conditions and any relevant water constraints.
- Failure behaviour: CDU, pump, valve, controls and leak-response scenarios.
- Cleaning and commissioning: flushing, filtration, fluid sampling and acceptance responsibilities.
- Operating ownership: who maintains each side of the interface and resolves alarms.
OCP’s cold-plate work spans the system from cold plates to CDUs, including tubing, manifolds and quick disconnects. Uptime Institute’s commissioning analysis also identifies integration of CDUs into the wider fluid network as a distinct challenge. Our recommendation: make the boundary between facility and IT cooling a signed responsibility schedule. (opencompute.org)
A relevant operational cross-check is Align Communications’ published liquid-cooling project role, which includes design coordination, installation, testing, commissioning and turnover. That supports the importance of assigning the complete integration scope; it does not demonstrate capacity or readiness at any particular facility. (job-boards.greenhouse.io)