Market data and deal flow · 2026-10-16

What are current colocation prices—and which comparisons are defensible?

Public data supports benchmarks, not a universal high-density colocation price. Geography, commitment size, delivery date and contractual scope must remain visible.

Benchmark Price or movement Date and limitations
Northern Virginia, requirements above 10 MW $160–$185/kW/month asking-rent benchmark H1 2026, CBRE report published 27 August 2026. Not an executable offer or a guarantee of liquid-cooling compatibility. (cbre.com)
Silicon Valley $200–$275/kW/month asking rents H1 2026; CBRE release 1 September 2026. The release does not specify a matching 10-plus-MW tier, so this is not a like-for-like comparison with Northern Virginia. (cbre.com)
Primary markets, 3–10 MW requirements 8.3% increase during H1 2026 CBRE, 27 August 2026; asking-rate movement. (cbre.com)
Primary markets, requirements above 10 MW 6.7% increase during H1 2026 Same report and basis. (cbre.com)

Can disclosed lease values reveal a useful price range?

Yes—but only as an arithmetic lifetime average. Applied Digital’s 2026 filed presentation discloses the following base-term values, excluding pass-through power. The presentation was reviewed on 16 October 2026; its exact publication day was not established in this pass. (ir.applieddigital.com)

Campus Disclosed inputs Desk calculation
Polaris Forge 1 Approximately $11bn, 400 MW, approximately 15 years Approximately $153/kW/month
Delta Forge 1 Approximately $7.5bn, 300 MW, approximately 15 years Approximately $139/kW/month

Calculation: base-term revenue ÷ contracted IT kW ÷ base-term months. These are undiscounted averages, not opening rents. They do not reconstruct escalators, phasing, concessions, landlord obligations or the timing of revenue recognition. They should not be used to claim that a smaller near-term procurement should clear at the same price. (ir.applieddigital.com)

For offer normalisation, request:

  • Critical IT capacity available at acceptance—not campus potential.
  • Reserved capacity and billing commencement by phase.
  • Electricity, demand charges and losses: included, passed through or marked up.
  • Rack density and cooling scope priced into the offer.
  • Escalators, minimum commitments, deposits and termination exposure.
  • Responsibility for tenant fit-out, network integration and acceptance testing.

This is a recommended comparison format, not a statement that every supplier uses the same commercial structure.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. www.cbre.com
  2. www.cbre.com
  3. www.cbre.com
  4. ir.applieddigital.com
Read the complete report and source register →

Put the evidence to work.

Keep your requirements, open questions and commitment conditions together.