State electricity averages are screening indicators, not data-centre tariffs. EIA’s latest monthly table available at this cut-off covers July 2026, released 24 September 2026. It identifies the figures as preliminary estimates and notes that customer-sector classification can depend on utility practice. (eia.gov)
| Geography | Industrial average, July 2026 | Commercial average, July 2026 |
|---|---|---|
| Texas | 7.07¢/kWh | 8.47¢/kWh |
| North Dakota | 8.21¢/kWh | 8.22¢/kWh |
| Arizona | 9.35¢/kWh | 13.12¢/kWh |
| Georgia | 10.03¢/kWh | 12.54¢/kWh |
| Virginia | 10.07¢/kWh | 11.68¢/kWh |
| United States | 9.77¢/kWh | 14.53¢/kWh |
Source for every table entry: EIA Electric Power Monthly, Table 5.6.A, 24 September 2026. These are sector-wide averages, not energy-only quotes or prices offered to a particular facility. (eia.gov)
Which large-load tariff conditions materially change ramp economics?
The applicable minimum-demand formula matters more than a headline percentage.
AEP Ohio: its public tariff explainer, reviewed 16 October 2026, describes study fees of $10,000–$100,000, a contract lasting the ramp period plus eight years, and a ramp of no more than four years. Its minimum-demand calculation is tiered and also includes a historical-demand test. (aepohio.com)
For example, the published contract-capacity formula gives a 50 MW customer a 36.25 MW minimum: 15 MW + 85% × (50 − 25) MW, before any higher historical-demand requirement or applicable ramp provisions. It is therefore inaccurate to apply a flat 85% formula to every customer. This is a demand calculation—not a requirement to buy that percentage of unused energy. (aepohio.com)
Dominion Virginia: the SCC describes minimum service obligations of 14 years for new qualifying large-load customers contracting on or after 1 January 2027. It also describes minimum transmission and distribution charges and potential collateral of up to 60% of minimum contract charges for customers without sufficient credit, subject to applicability rules. These provisions should not be treated as already effective for every customer in October 2026. (scc.virginia.gov)
Practical limitation: this pass reviewed public utility and regulator explanations, not a complete customer-specific reconstruction of operative tariff sheets, riders and executed agreements. Obtain specialist confirmation before making a payment or signing service terms.
What changed recently in Texas large-load diligence?
ERCOT’s 14 September 2026 notice required specified unenergised data-centre projects to provide state and community impact information, including water information. The scope included relevant Batch Zero projects and certain substantiated 25–75 MW projects; the stated response deadline was 12 October 2026. (ercot.com)
That deadline has passed as of this report. For an affected site, request evidence of submission and its subsequent status. Do not assume that reaching the deadline meant audit clearance or permission to energise. This report does not establish project-specific clearance or a blanket release of affected projects.
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.