Market data and deal flow · 2026-10-16

What does a 10 MW deployment cost under a slower ramp?

A useful model separates reserved capacity from actual electricity use. The following is a desk illustration dated 16 October 2026, not a supplier quote, forecast or complete operating budget.

Explicit assumptions

  • Reserved critical IT capacity: 10 MW.
  • Capacity charge: $175/kW/month, chosen solely for illustration.
  • Billing applies to the full reservation throughout the year.
  • Actual average IT draw: either 10 MW or 5 MW.
  • Assumed total-facility-to-IT energy ratio: 1.20 in both cases.
  • Assumed energy-only price: $80/MWh.
  • Annual hours: 8,760.
  • Excluded: demand charges, minimum utility bills, taxes, deposits, fit-out, hardware, staffing, financing and network costs.
Calculated item Full average IT draw Half average IT draw
Average IT load 10 MW 5 MW
Assumed average metered load 12 MW 6 MW
Annual metered energy 105,120 MWh 52,560 MWh
Annual reserved-capacity rent $21.00m $21.00m
Annual energy component $8.41m $4.20m
Rent plus energy subtotal $29.41m $25.20m
Subtotal per average utilised IT kW/month $245.08 $420.08

All outputs are desk calculations from the stated hypothetical assumptions. The constant 1.20 energy ratio is a simplifying assumption, not a prediction of part-load facility performance.

The result illustrates the commercial issue: halving utilisation does not halve a fixed capacity reservation. Actual tariff minimums could change the electricity component further; those must be modelled from the applicable documents rather than inferred from this example.

What does delayed activation expose?

Under the same hypothetical reservation, three months of rent is $5.25m if billing has commenced. That is a cash obligation, not automatically an incremental loss: the counterfactual and contract terms determine how much is avoidable.

For a buyer-specific delay model, show separately:

  • Rent and utility obligations that start before usable deployment.
  • Additional storage, handling and financing costs.
  • Customer penalties supported by actual contracts.
  • Deferred contribution from delayed service.
  • Revenue genuinely lost rather than shifted to a later period.

Do not publish a universal dollar cost of delay or treat all delayed revenue as permanently lost.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.